MADISON SH0021 (6375-25-001)

Items: 54

County: MADISON
Length: N/A
Highway: SH0021
District: BRYAN
Control Number: 6375-25-001
DBE Goal: N/A
Project: RMC - 637525001
Guaranty: N/A
Time: 48 W
Engineer's Estimate: $2,168,729.41
Date: 02/04/2021 (5 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (5)
E
Engineer's Estimate
$2,168,729.41
$1,673,115.05
Over/Under Est: -22.85% -$495,614.36
Over/Under Est: -12.61% -$273,458.27
Amt Left: 13.28% $222,156.09
Over/Under Est: -8.9% -$192,939.61
Amt Left: 18.09% $302,674.75
Delta: -4.25% -$80,518.66
$2,025,338.25
Over/Under Est: -6.61% -$143,391.16
Amt Left: 21.05% $352,223.20
Delta: -2.51% -$49,548.45
Over/Under Est: 26.79% $581,069.04
Amt Left: 64.35% $1,076,683.40
Delta: -35.77% -$724,460.20

Bid Items & Bid Tabulations

54 Total 0 of 54
MADISON  |  SH0021  |  BRYAN  |  6375-25-001  |  02/04/2021  |  $2,168,729.41  |  RMC - 637525001  |  MILL AND INLAY  |  48 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
ANGEL BROTHERS HOLDINGS CORP.
VULCAN CONSTRUCTION
TEXCON GENERAL CONTRACTORS
PREPARING ROW
STA 1.000 $6,000.000 $2,500.000 $6,100.000 $2,500.000 $3,775.000 $3,500.000
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 6.000 $600.000 $600.000 $800.000 $825.000 $978.500 $1,250.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY A)
CY 730.000 $30.000 $35.000 $27.350 $30.000 $29.000 $23.000
BACKFILL (TY A OR B)
STA 230.000 $140.000 $150.000 $105.000 $165.000 $321.000 $168.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 22.000 $70.000 $100.000 $120.000 $135.000 $150.000 $200.000
TOM (ASPHALT) PG 76-22
TON 44.000 $118.000 $120.000 $108.000 $155.000 $0.100 $625.000
TOM-C (AGGREGATE) SAC-A
TON 615.000 $120.000 $120.000 $108.000 $155.000 $126.000 $115.000
PLANE ASPH CONC PAV(0" TO 2")
SY 8,559.000 $1.650 $1.500 $2.500 $2.550 $4.650 $2.700
PLANE ASPH CONC PAV(MICRO-MLLING)(3/4")
SY 15,890.000 $2.500 $1.000 $1.320 $1.600 $1.900 $2.700
CEM STABIL BKFL
CY 106.000 $130.000 $120.000 $75.000 $110.000 $137.000 $139.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 20.000 $150.000 $250.000 $32.000 $50.000 $219.000 $223.000
RIPRAP (MOW STRIP)(4 IN)
CY 238.000 $530.000 $450.000 $465.000 $575.000 $712.000 $725.000
CLEANING AND SEALING EXISTING JOINTS
LF 782.000 $80.000 $30.000 $28.000 $20.000 $32.000 $35.000
RETROFIT RAIL (TY T631)
LF 1,078.000 $100.000 $62.000 $85.880 $50.000 $90.000 $64.000
RC PIPE (CL III)(48 IN)
LF 224.000 $145.000 $175.000 $139.000 $200.000 $274.000 $278.000
SET (TY II) (48 IN) (RCP) (6: 1) (P)
EA 2.000 $7,000.000 $8,000.000 $8,300.000 $20,000.000 $10,953.000 $11,150.000
MOBILIZATION
LS 1.000 $103,273.000 $50,000.000 $79,000.000 $185,000.000 $42,486.000 $205,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $7,500.000 $4,000.000 $1,545.000 $3,000.000 $14,178.000 $50,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,065.000 $3.500 $2.500 $2.660 $1.500 $2.750 $2.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,065.000 $1.500 $0.500 $0.800 $0.750 $0.800 $0.840
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 1,650.000 $60.000 $30.000 $18.300 $27.000 $15.000 $100.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 1,650.000 $20.000 $6.250 $15.200 $12.000 $6.500 $45.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 1,650.000 $20.000 $8.000 $15.750 $16.000 $10.000 $10.000
INTERSECTIONS (ACP)
SY 281.000 $30.000 $30.000 $44.000 $27.000 $28.000 $20.000
DRIVEWAYS (ACP)
SY 2,053.000 $30.000 $25.000 $41.650 $32.000 $31.500 $20.000
DRIVEWAYS (BASE)
SY 1,157.000 $35.000 $15.000 $20.000 $17.000 $11.000 $50.000
RUMBLE STRIPS (CENTERLINE)
LF 22,310.000 $0.200 $0.340 $0.240 $0.450 $0.350 $0.530
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 44,470.000 $0.150 $0.230 $0.190 $0.200 $0.350 $0.450
MTL W-BEAM GD FEN (STEEL POST)
LF 2,000.000 $27.000 $27.000 $22.340 $20.000 $22.000 $24.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 50.000 $45.000 $58.000 $143.000 $45.000 $65.500 $55.000
REMOVE METAL BEAM GUARD FENCE
LF 1,075.000 $3.000 $4.000 $2.000 $1.250 $2.200 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $200.000 $200.000 $266.000 $150.000 $328.500 $170.000
RM MTL BM GD FEN TRANS (T101)
EA 20.000 $275.000 $220.000 $213.000 $125.000 $164.500 $170.000
GUARDRAIL END TREATMENT (INSTALL)
EA 26.000 $2,500.000 $2,700.000 $2,605.000 $2,200.000 $2,684.000 $2,650.000
GUARDRAIL END TREATMENT (REMOVE)
EA 20.000 $250.000 $250.000 $200.000 $125.000 $164.500 $225.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 12.000 $2,000.000 $1,600.000 $2,400.000 $650.000 $3,094.000 $1,600.000
CRASH CUSH ATTEN (REMOVE)
EA 12.000 $1,000.000 $850.000 $1,050.000 $500.000 $547.500 $890.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 12.000 $8,500.000 $7,800.000 $9,250.000 $7,500.000 $9,661.000 $8,100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 75.000 $20.000 $25.000 $5.000 $15.000 $19.500 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 84.000 $30.000 $37.000 $36.000 $20.000 $30.500 $37.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 46,093.000 $0.200 $0.220 $0.230 $0.220 $0.150 $0.160
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 4,950.000 $0.120 $0.220 $0.280 $0.220 $0.150 $0.160
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 34,297.000 $0.180 $0.220 $0.230 $0.220 $0.150 $0.160
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,342.000 $1.000 $1.000 $1.000 $0.900 $0.850 $6.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 46,093.000 $0.300 $0.330 $0.390 $0.320 $0.500 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,950.000 $0.500 $0.330 $0.470 $0.320 $0.550 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 16,957.000 $0.300 $0.330 $0.390 $0.320 $0.500 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 26.000 $12.000 $12.500 $20.000 $12.250 $16.500 $17.000
REFL PAV MRKR TY II-A-A
EA 917.000 $3.500 $3.750 $4.000 $3.750 $3.650 $3.800
BONDING COURSE
GAL 11,300.000 $2.750 $3.500 $3.300 $2.750 $2.450 $4.000
SP MIXES SP-D SAC-A PG64-22
TON 8,173.000 $95.000 $72.000 $86.650 $90.000 $87.500 $116.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $5,000.000 $3,900.000 $2,500.000 $2,191.000 $2,000.000
TMA (STATIONARY)
DAY 50.000 $300.000 $200.000 $300.000 $125.000 $264.500 $500.000
TMA (MOBILE OPERATION)
HR 200.000 $45.000 $70.000 $70.000 $25.000 $27.500 $110.000
Totals: $2,168,729.410 $1,673,115.050 $1,895,271.140 $1,975,789.800 $2,025,338.250 $2,749,798.450