Show Job Controls
Bid Cobra

LUBBOCK SL 289 (0783-02-099)

Items: 23

County: LUBBOCK
Length: N/A
Highway: SL 289
District: LUBBOCK
Control Number: 0783-02-099
DBE Goal: N/A
Project: STP 1902(149)HES
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $1,356,002.00
Date: 07/09/2019 (6 years ago)
Contract Number: N/A
Type: SAFETY IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,356,002.00
$1,071,270.00
Over/Under Est: -21% -$284,732.00
Over/Under Est: -10.9% -$147,778.00
Amt Left: 12.78% $136,954.00
$1,292,303.60
Over/Under Est: -4.7% -$63,698.40
Amt Left: 20.63% $221,033.60
Delta: -6.96% -$84,079.60
$1,310,127.00
Over/Under Est: -3.38% -$45,875.00
Amt Left: 22.3% $238,857.00
Delta: -1.38% -$17,823.40
Over/Under Est: -2.84% -$38,510.85
Amt Left: 22.98% $246,221.15
Delta: -0.56% -$7,364.15

Bid Items & Bid Tabulations

23 Total 0 of 23
LUBBOCK  |  SL 289  |  LUBBOCK  |  0783-02-099  |  07/09/2019  |  $1,356,002.00  |  STP 1902(149)HES  |  SAFETY IMPRVS  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA CONSTRUCTION INC.
BLACKSTONE CONCRETE VENTURES, LLC
DBI SERVICES, LLC
VANN/ELLI, INC.
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 3,397.000 $30.000 $10.000 $5.000 $20.000 $35.000 $24.000
BLADING
STA 159.000 $125.000 $135.000 $350.000 $160.000 $180.000 $290.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 7,300.000 $5.000 $4.000 $8.000 $12.000 $6.750 $5.600
RIPRAP (CONC)(5 IN)
CY 471.000 $600.000 $450.000 $550.000 $460.000 $550.000 $631.000
RIPRAP (MOW STRIP)(5 IN)
CY 732.000 $600.000 $440.000 $450.000 $410.000 $500.000 $450.000
MOBILIZATION
LS 1.000 $123,000.000 $51,206.250 $175,000.000 $220,000.000 $120,000.000 $127,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $10,000.000 $15,000.000 $3,000.000 $4,000.000 $9,000.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 444.000 $30.000 $30.000 $45.000 $35.000 $40.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $10.000 $8.000 $15.000 $6.000 $10.000 $28.000
SANDBAGS FOR EROSION CONTROL
EA 644.000 $5.000 $8.000 $5.000 $4.000 $9.000 $8.000
CABLE BARRIER SYSTEM (TL-4)
LF 15,795.000 $12.000 $13.250 $13.000 $11.000 $11.000 $13.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 10.000 $2,500.000 $8,352.000 $3,200.000 $2,000.000 $2,500.000 $3,400.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 1,132.000 $2.000 $2.000 $1.000 $7.000 $3.500 $3.350
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,528.000 $2.000 $1.000 $1.000 $7.000 $1.250 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 340.000 $2.000 $1.250 $1.000 $2.000 $1.250 $2.250
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 1,132.000 $1.000 $1.000 $2.000 $6.000 $3.000 $2.250
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 4,528.000 $1.000 $0.500 $2.000 $4.500 $3.000 $2.250
REFL PAV MRKR TY II-C-R
EA 57.000 $5.000 $4.000 $2.000 $15.000 $25.000 $22.350
ELIM EXT PAV MRK & MRKS (4")
LF 4,528.000 $2.000 $0.500 $1.000 $1.500 $0.850 $0.600
ELIM EXT PAV MRK & MRKS (6")
LF 1,132.000 $3.000 $0.500 $1.000 $2.300 $1.100 $0.850
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $7,500.000 $2,500.000 $6,800.000 $15,000.000 $10,000.000
TMA (STATIONARY)
DAY 90.000 $250.000 $110.000 $55.000 $540.000 $400.000 $330.000
TMA (MOBILE OPERATION)
DAY 15.000 $300.000 $200.000 $300.000 $540.000 $1,000.000 $1,100.000
Totals: $1,356,002.000 $1,071,270.000 $1,208,224.000 $1,292,303.600 $1,310,127.000 $1,317,491.150