LUBBOCK US 84 (0052-07-070)

Items: 26

County: LUBBOCK
Length: N/A
Highway: US 84
District: LUBBOCK
Control Number: 0052-07-070
DBE Goal: N/A
Project: C 52-7-70
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $6,974,761.30
Date: 04/04/2017 (9 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$6,974,761.30
$5,963,457.12
Over/Under Est: -14.5% -$1,011,304.18
Over/Under Est: -14.41% -$1,005,015.55
Amt Left: 0.11% $6,288.63
$6,184,275.82
Over/Under Est: -11.33% -$790,485.48
Amt Left: 3.7% $220,818.70
Delta: -3.59% -$214,530.07
$7,075,503.09
Over/Under Est: 1.44% $100,741.79
Amt Left: 18.65% $1,112,045.97
Delta: -14.41% -$891,227.27

Bid Items & Bid Tabulations

26 Total 0 of 26
LUBBOCK  |  US 84  |  LUBBOCK  |  0052-07-070  |  04/04/2017  |  $6,974,761.30  |  C 52-7-70  |  MILL AND INLAY  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNF CONSTRUCTION, INC.
ALLEN BUTLER CONSTRUCTION, INC.
DUININCK, INC.
J. LEE MILLIGAN, INC.
D-GR HMA TY-F SAC-B PG70-28
TON 8,406.000 $100.000 $86.250 $93.040 $99.000 $107.400
STONE-MTRX-ASPH SMA-D SAC-B PG70-28
TON 25,329.000 $130.000 $90.500 $108.960 $106.000 $123.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 11,800.000 $70.000 $30.100 $34.210 $40.500 $45.400
PLANE ASPH CONC PAV(0" TO 3")
SY 214,667.000 $2.000 $2.200 $0.760 $1.700 $1.550
CLEANING AND SEALING EXISTING JOINTS
LF 2,842.000 $30.000 $39.500 $30.260 $31.000 $22.300
MOBILIZATION
LS 1.000 $634,000.000 $594,478.190 $430,631.330 $265,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $15,000.000 $10,000.000 $5,852.360 $32,500.000 $15,350.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 18,522.000 $0.150 $0.120 $0.120 $0.110 $0.120
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 18,522.000 $0.150 $0.120 $0.120 $0.110 $0.120
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 18,522.000 $1.000 $0.400 $0.400 $0.390 $0.400
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 18,522.000 $1.000 $0.400 $0.400 $0.390 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,309.000 $2.000 $2.000 $2.570 $1.050 $1.130
REFL PAV MRK TY I (W)4"(LNDP)(060MIL)
LF 290.000 $1.000 $0.250 $0.250 $0.250 $0.250
REFL PAV MRK TY I (W)8"(SLD)(060MIL)
LF 10,917.000 $1.000 $0.500 $0.510 $0.500 $0.510
PAVEMENT SEALER 4"
LF 1,728.000 $0.200 $0.200 $0.210 $0.210 $0.210
PAVEMENT SEALER 6"
LF 216.000 $0.500 $0.300 $0.320 $0.310 $0.320
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 90,084.000 $0.400 $0.250 $0.250 $0.250 $0.250
RE PM W/RET REQ TY I (W)6"(BRK)(060MIL)
LF 22,521.000 $0.400 $0.400 $0.380 $0.370 $0.380
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 90,084.000 $0.400 $0.250 $0.250 $0.250 $0.250
PREFAB PAV MRK TY C (W) (12") (LNDP)
LF 644.000 $10.000 $10.500 $10.580 $10.500 $10.540
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 1,403.000 $10.000 $10.250 $10.580 $10.500 $10.540
ELIM EXT PAV MRK & MRKS (4")
LF 18,522.000 $0.750 $1.750 $0.630 $0.620 $0.630
PAV SURF PREP FOR MRK (4")
LF 1,728.000 $0.500 $0.900 $0.630 $0.880 $0.900
PAV SURF PREP FOR MRK (6")
LF 216.000 $1.000 $0.900 $0.900 $0.880 $0.900
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 195,467.000 $3.000 $6.000 $6.020 $6.000 $6.100
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $25,000.000 $9,448.520 $10,500.000 $13,550.000
Totals: $6,974,761.300 $5,963,457.120 $5,969,745.750 $6,184,275.820 $7,075,503.090