LIVE OAK CR (0916-29-006)

Items: 60

County: LIVE OAK
Length: N/A
Highway: CR
District: CORPUS CHRISTI
Control Number: 0916-29-006
DBE Goal: N/A
Project: BR 1502(204)
Guaranty: N/A
Time: 94 WORKING DAYS
Engineer's Estimate: $760,616.65
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (12)
E
Engineer's Estimate
$760,616.65
Over/Under Est: -14.65% -$111,425.97
Over/Under Est: -10.15% -$77,217.03
Amt Left: 5.27% $34,208.94
$727,474.05
Over/Under Est: -4.36% -$33,142.60
Amt Left: 12.06% $78,283.37
Delta: -6.45% -$44,074.43
$787,080.59
Over/Under Est: 3.48% $26,463.94
Amt Left: 21.24% $137,889.91
Delta: -8.19% -$59,606.54
Over/Under Est: 6.4% $48,663.10
Amt Left: 24.66% $160,089.07
Delta: -2.82% -$22,199.16
$911,267.68
Over/Under Est: 19.81% $150,651.03
Amt Left: 40.37% $262,077.00
Delta: -12.60% -$101,987.93
Over/Under Est: 26.14% $198,805.10
Amt Left: 47.79% $310,231.07
Delta: -5.28% -$48,154.07
$1,059,344.77
Over/Under Est: 39.27% $298,728.12
Amt Left: 63.18% $410,154.09
Delta: -10.41% -$99,923.02
Over/Under Est: 41.64% $316,749.39
Amt Left: 65.96% $428,175.36
Delta: -1.70% -$18,021.27
$1,087,683.01
Over/Under Est: 43% $327,066.36
Amt Left: 67.54% $438,492.33
Delta: -0.96% -$10,316.97
$1,104,193.00
Over/Under Est: 45.17% $343,576.35
Amt Left: 70.09% $455,002.32
Delta: -1.52% -$16,509.99
Over/Under Est: 73.21% $556,826.76
Amt Left: 102.94% $668,252.73
Delta: -19.31% -$213,250.41

Bid Items & Bid Tabulations

60 Total 0 of 60
LIVE OAK  |  CR  |  CORPUS CHRISTI  |  0916-29-006  |  03/07/2017  |  $760,616.65  |  BR 1502(204)  |  REPLACE BRIDGE AND APPROACHES  |  94 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LISKA CONSTRUCTION COMPANY, INC.
HILL COUNTRY BRIDGE, INC.
TMES LLC
RELMCO, INC.
ACME BRIDGE COMPANY, INC.
CRG
ANGEL BROTHERS HOLDINGS CORP.
IHS CONSTRUCTION, INC.
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
J. CARROLL WEAVER, INC.
IOC COMPANY, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREPARING ROW
STA 5.300 $1,500.000 $1,500.000 $2,840.000 $1,800.000 $5,000.000 $3,000.000 $16,000.000 $18,500.000 $1,766.680 $2,500.000 $630.000 $7,500.000 $1,226.250
REMOVING STAB BASE AND ASPH PAV (6")
SY 819.000 $20.000 $2.460 $7.400 $7.580 $8.000 $12.700 $8.500 $5.000 $15.000 $30.000 $8.790 $6.000 $24.140
EXCAVATION (ROADWAY)
CY 175.000 $10.000 $10.490 $38.000 $9.600 $12.000 $36.000 $18.150 $38.000 $70.000 $40.000 $41.130 $20.000 $32.230
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 557.000 $10.000 $12.760 $42.850 $39.000 $18.000 $36.000 $28.960 $25.000 $65.000 $60.000 $15.090 $30.000 $24.420
FURNISHING AND PLACING TOPSOIL (4")
SY 688.000 $2.000 $5.390 $4.600 $5.000 $5.300 $6.000 $6.080 $3.500 $8.430 $12.000 $18.020 $17.000 $11.060
BLOCK SODDING
SY 371.000 $3.000 $9.420 $12.900 $5.000 $10.000 $8.500 $8.080 $15.000 $5.880 $8.400 $15.750 $12.000 $10.940
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 317.000 $0.200 $1.200 $5.350 $1.750 $3.000 $1.050 $1.320 $2.000 $1.110 $1.100 $2.100 $5.000 $4.190
BROADCAST SEED (TEMP) (WARM)
SY 159.000 $0.150 $1.200 $3.060 $3.450 $3.000 $1.050 $1.320 $3.150 $2.080 $1.100 $3.310 $5.000 $6.720
BROADCAST SEED (TEMP) (COOL)
SY 158.000 $0.150 $1.200 $3.060 $1.150 $3.000 $1.050 $1.320 $3.150 $1.470 $1.100 $3.310 $5.000 $6.720
VEGETATIVE WATERING
MG 38.000 $20.000 $80.870 $35.200 $92.000 $50.000 $30.000 $89.280 $19.000 $51.370 $78.000 $36.750 $60.000 $81.110
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 241.000 $50.000 $84.900 $82.600 $73.750 $85.000 $80.000 $110.240 $120.000 $157.180 $160.000 $125.430 $100.000 $116.400
PRIME COAT (MULTI OPTION)
GAL 216.000 $4.000 $17.890 $7.150 $8.050 $5.000 $17.200 $9.500 $13.000 $12.200 $19.000 $8.790 $7.000 $9.120
ASPH (MULTI OPTION)
GAL 847.000 $3.000 $8.050 $5.050 $5.700 $5.000 $12.400 $6.650 $8.000 $15.000 $14.000 $3.960 $6.000 $6.190
AGGR(TY-PB GR-4 SAC-B)
CY 20.000 $100.000 $495.070 $408.000 $460.100 $350.000 $494.000 $530.000 $600.000 $203.580 $530.000 $716.000 $250.000 $411.090
CEM STABIL BKFL
CY 88.000 $65.000 $182.860 $167.000 $150.000 $120.000 $200.000 $150.000 $245.000 $160.000 $230.000 $189.000 $225.000 $181.130
DRILL SHAFT (18 IN)
LF 120.000 $100.000 $109.250 $105.700 $107.680 $125.000 $101.000 $85.790 $150.000 $145.000 $88.200 $63.000 $110.000 $134.240
DRILL SHAFT (36 IN)
LF 264.000 $175.000 $193.940 $190.500 $212.250 $225.000 $195.000 $288.230 $250.000 $400.000 $270.000 $252.000 $190.000 $240.270
CL C CONC (ABUT)
CY 44.200 $1,200.000 $795.910 $758.000 $850.000 $874.900 $850.000 $639.370 $950.000 $950.000 $1,100.000 $872.520 $1,025.000 $1,655.230
CL C CONC (BENT)
CY 35.900 $1,200.000 $928.920 $830.000 $1,200.000 $926.900 $950.000 $1,227.890 $1,100.000 $1,475.000 $1,200.000 $1,412.750 $2,800.000 $2,389.530
REINF CONC SLAB
SF 5,460.000 $15.000 $14.110 $16.850 $18.000 $14.000 $22.000 $16.740 $23.000 $11.500 $21.000 $38.130 $18.500 $35.440
PRESTR CONC GIRDER (TX28)
LF 834.000 $140.000 $121.650 $127.000 $119.350 $120.000 $157.500 $133.390 $150.000 $235.000 $130.000 $121.270 $111.000 $191.290
RIPRAP (CONC)(5 IN)
CY 2.000 $400.000 $750.000 $718.000 $500.000 $1,500.000 $800.000 $759.660 $1,050.000 $2,075.000 $1,200.000 $735.000 $750.000 $1,704.880
RIPRAP (STONE PROTECTION)(12 IN)
CY 106.000 $275.000 $126.700 $126.700 $100.000 $135.000 $145.000 $131.030 $155.000 $85.000 $95.000 $210.000 $145.000 $217.320
RIPRAP (MOW STRIP)(4 IN)
CY 34.000 $475.000 $514.090 $520.000 $450.000 $465.000 $500.000 $312.370 $560.000 $450.000 $680.000 $630.000 $500.000 $816.940
RAIL (TY T223)
LF 496.000 $200.000 $102.220 $92.400 $110.000 $75.400 $70.000 $148.620 $110.000 $90.000 $170.000 $154.350 $95.000 $207.000
ARMOR JOINT (SEALED)
LF 44.000 $100.000 $65.050 $80.000 $88.000 $65.000 $120.000 $97.160 $120.000 $159.470 $170.000 $52.500 $100.000 $165.230
RC PIPE (CL III)(18 IN)
LF 123.000 $55.000 $57.510 $34.050 $77.000 $48.000 $60.000 $56.300 $88.000 $134.140 $90.000 $41.370 $85.000 $69.850
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,200.000 $1,000.000 $1,140.000 $1,600.000 $1,250.000 $1,000.000 $2,802.540 $2,000.000 $2,800.000 $2,400.000 $1,155.000 $1,000.000 $1,050.310
REMOV STR (ABUTMENT)
EA 2.000 $2,500.000 $1,250.000 $4,700.000 $1,500.000 $25,000.000 $1,000.000 $4,939.870 $7,500.000 $6,500.000 $3,500.000 $7,689.150 $5,000.000 $5,000.000
MOBILIZATION
LS 1.000 $70,000.000 $52,064.000 $59,200.000 $84,163.000 $65,000.000 $61,200.000 $86,278.000 $96,000.000 $104,700.000 $107,736.600 $134,679.250 $109,000.000 $194,766.420
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,500.000 $1,846.070 $2,520.000 $1,590.000 $3,500.000 $1,500.000 $1,967.290 $2,000.000 $5,407.000 $3,500.000 $1,260.000 $3,500.000 $867.920
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 260.000 $30.000 $28.460 $26.000 $28.750 $22.000 $26.500 $43.680 $26.000 $37.490 $26.000 $26.660 $30.000 $28.460
ROCK FILTER DAMS (REMOVE)
LF 260.000 $10.000 $7.890 $6.650 $9.200 $8.000 $8.500 $13.590 $6.000 $8.670 $8.400 $6.300 $8.000 $6.900
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 99.000 $25.000 $16.500 $21.200 $17.250 $25.000 $15.900 $15.730 $33.000 $28.000 $15.500 $35.480 $15.000 $22.750
CONSTRUCTION EXITS (REMOVE)
SY 99.000 $10.000 $5.500 $9.800 $5.750 $8.000 $5.300 $6.570 $6.000 $10.290 $5.200 $6.300 $5.000 $9.440
BACKHOE WORK (EROSION & SEDMT CONT)
HR 20.000 $100.000 $72.000 $96.900 $75.000 $85.000 $75.650 $88.400 $175.000 $97.970 $75.000 $47.250 $75.000 $81.860
TEMP SEDMT CONT FENCE (INSTALL)
LF 812.000 $1.000 $3.850 $3.270 $2.250 $3.000 $3.700 $2.300 $2.500 $5.150 $3.700 $2.370 $7.000 $3.160
TEMP SEDMT CONT FENCE (REMOVE)
LF 812.000 $1.000 $1.100 $0.860 $0.750 $1.500 $1.050 $1.210 $0.600 $1.470 $1.100 $0.530 $1.000 $0.960
DRIVEWAYS (SURF TREAT)
SY 73.000 $25.000 $50.220 $32.750 $93.000 $85.000 $64.000 $32.790 $100.000 $175.000 $45.000 $36.750 $30.000 $105.520
MTL W-BEAM GD FEN (TIM POST)
LF 275.000 $20.000 $20.610 $17.100 $20.000 $18.000 $19.900 $45.890 $19.000 $17.000 $19.500 $19.680 $19.000 $26.400
MTL BEAM GD FEN TRANS (TL2)
EA 3.000 $1,400.000 $978.680 $714.000 $800.000 $875.000 $944.000 $1,967.290 $890.000 $750.000 $930.000 $934.200 $1,000.000 $1,075.000
SHORT RADIUS
LF 40.000 $30.000 $32.120 $22.950 $28.000 $30.000 $31.000 $131.150 $30.000 $21.500 $30.500 $30.660 $40.000 $42.260
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $900.000 $695.590 $510.000 $600.000 $600.000 $671.000 $1,573.830 $635.000 $525.000 $660.000 $663.970 $1,000.000 $1,141.150
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,000.000 $2,725.280 $1,821.000 $2,100.000 $2,350.000 $2,630.000 $3,147.660 $2,500.000 $1,900.000 $2,600.000 $2,601.410 $2,500.000 $3,969.100
CRASH CUSH ATTEN (INSTL)
EA 1.000 $1,200.000 $15,290.000 $12,660.000 $15,985.000 $14,500.000 $14,800.000 $14,486.620 $13,900.000 $14,000.000 $14,500.000 $14,595.000 $15,500.000 $17,943.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $500.000 $517.500 $367.250 $425.000 $467.500 $451.000 $430.000 $425.000 $450.000 $440.000 $559.650 $450.000 $478.150
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $500.000 $619.250 $433.500 $490.000 $544.500 $525.000 $495.000 $495.000 $550.000 $520.000 $733.950 $550.000 $555.150
REMOVE SM RD SN SUP&AM
EA 4.000 $65.000 $50.000 $58.550 $95.000 $104.500 $101.000 $97.050 $95.000 $125.000 $99.000 $105.000 $100.000 $115.150
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 7.000 $40.000 $71.500 $61.200 $74.750 $71.500 $69.000 $66.970 $50.000 $80.850 $68.000 $52.340 $50.000 $82.150
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $14.400 $22.450 $14.000 $13.200 $12.700 $29.120 $10.000 $17.640 $12.500 $10.500 $31.000 $23.850
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 1.000 $70.000 $78.000 $53.550 $74.750 $71.500 $69.000 $72.130 $50.000 $85.260 $68.000 $0.740 $100.000 $82.150
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 29.000 $7.000 $8.960 $10.200 $9.200 $8.800 $8.500 $10.680 $8.000 $14.700 $10.500 $1.520 $10.000 $12.470
REFL PAV MRK TY II (W) 4" (SLD)
LF 1,176.000 $0.150 $1.120 $0.710 $1.150 $1.100 $1.050 $1.630 $1.000 $1.030 $0.730 $1.520 $1.000 $1.190
REFL PAV MRK TY II (W) 24" (SLD)
LF 29.000 $2.500 $4.480 $4.080 $4.600 $4.400 $4.250 $7.210 $4.000 $5.880 $4.200 $4.200 $4.000 $8.070
REFL PAV MRK TY II (Y) 4" (SLD)
LF 1,062.000 $0.150 $1.120 $0.710 $1.150 $1.100 $1.050 $1.630 $1.000 $1.030 $0.730 $0.740 $1.000 $1.200
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,176.000 $0.250 $1.680 $1.480 $1.730 $1.650 $1.600 $1.630 $1.500 $2.210 $1.500 $1.520 $1.500 $1.740
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,062.000 $0.250 $1.680 $1.480 $1.730 $1.650 $1.050 $1.630 $1.500 $2.210 $1.500 $1.520 $1.500 $1.750
REFL PAV MRKR TY II-A-A
EA 14.000 $3.000 $11.200 $7.650 $11.500 $11.000 $10.600 $7.870 $10.000 $11.030 $7.800 $7.880 $7.500 $17.610
RELOCATE EXISTING TRUSS BRIDGE
LS 1.000 $50,000.000 $22,567.500 $17,570.000 $22,352.440 $80,000.000 $80,000.000 $55,343.420 $35,000.000 $100,774.000 $160,000.000 $149,374.790 $250,000.000 $135,403.960
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $100.000 $147.810 $240.000 $125.000 $200.000 $42.500 $262.300 $135.000 $105.000 $140.000 $78.750 $400.000 $172.610
Totals: $760,616.650 $649,190.690 $683,399.620 $727,474.050 $787,080.590 $809,279.750 $911,267.685 $959,421.750 $1,059,344.774 $1,077,366.040 $1,087,683.019 $1,104,193.000 $1,317,443.428