Show Job Controls
Bid Cobra

LIVE OAK US 59 (0542-06-053)

Items: 59

County: LIVE OAK
Length: 0.0000 MILES
Highway: US 59
District: CORPUS CHRISTI
Control Number: 0542-06-053
DBE Goal: 0.0%
Project: F 2026(421)
Guaranty: $100,000.00
Time: 144 WORKING DAYS
Engineer's Estimate: $5,608,038.25
Date: 03/04/2026 (3 months ago)
Contract Number: 3263010
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00209030
Contract Type: Federal
Project Description: OVERLAY AND SPOT BASE REPAIR
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ERIC MARTINEZ
LUCIA ADAME
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$5,608,038.25
$5,311,274.02
Over/Under Est: -5.29% -$296,764.23
Over/Under Est: -1.01% -$56,505.50
Amt Left: 4.52% $240,258.73
Over/Under Est: 3.62% $202,854.15
Amt Left: 9.41% $499,618.38
Delta: -4.67% -$259,359.65
$5,983,829.33
Over/Under Est: 6.7% $375,791.08
Amt Left: 12.66% $672,555.31
Delta: -2.98% -$172,936.93
Over/Under Est: 8.32% $466,572.91
Amt Left: 14.37% $763,337.14
Delta: -1.52% -$90,781.83

Bid Items & Bid Tabulations

59 Total 0 of 59
LIVE OAK  |  US 59  |  CORPUS CHRISTI  |  0542-06-053  |  03/04/2026  |  $5,608,038.25  |  F 2026(421)  |  SURF/ROADWAY RESTOR  |  144 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANDERSON COLUMBIA CO., INC.
LONE STAR PAVING COMPANY
CK NEWBERRY, LLC
TEXAS MATERIALS GROUP, INC.
PRIME COAT (RC-250)
GAL 2,499.000 $3.500 $4.240 $2.000 $3.600 $3.750 $5.000
D-GR HMA TY-D SAC-B PG70-22
TON 27,388.000 $105.000 $91.490 $100.000 $114.000 $106.000 $122.000
TACK COAT
GAL 19,929.000 $3.500 $2.360 $1.000 $3.300 $4.000 $0.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 12,664.000 $28.000 $20.100 $28.000 $30.000 $26.000 $26.500
PLANE ASPH CONC PAV(2")
SY 248,738.000 $2.000 $0.920 $1.000 $1.100 $0.500 $1.550
RIPRAP (MOW STRIP)(4 IN)
CY 741.000 $140.000 $618.110 $625.000 $505.000 $690.380 $525.000
CLEANING AND SEALING EXISTING JOINTS
LF 136.000 $60.000 $89.230 $82.000 $84.000 $85.000 $80.000
SET (REPLACE PIPE RUNNER ASSEMBLY)
EA 8.000 $340.000 $2,400.000 $8,500.000 $5,250.000 $3,000.000 $5,500.000
CLEAN EXIST CULVERTS
EA 11.000 $1,000.000 $1,300.000 $4,000.000 $3,500.000 $2,500.000 $4,000.000
MOBILIZATION
LS 1.000 $281,481.950 $370,576.990 $530,000.000 $168,000.000 $550,000.000 $210,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $2,000.000 $11,211.860 $1,000.000 $2,000.000 $12,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 360.000 $100.000 $50.510 $10.000 $85.000 $55.000 $100.000
TMA (STATIONARY)
DAY 360.000 $300.000 $126.280 $20.000 $290.000 $250.000 $50.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,620.000 $5.000 $4.750 $4.500 $6.500 $6.500 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,620.000 $2.000 $1.750 $2.400 $1.000 $1.000 $0.500
CONC CURB (TY II)
LF 384.000 $30.000 $35.000 $38.000 $30.000 $45.000 $50.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 96,200.000 $0.150 $0.100 $0.170 $0.190 $0.100 $0.200
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 96,200.000 $0.150 $0.120 $0.190 $0.190 $0.120 $0.200
MTL W-BEAM GD FEN (TIM POST)
LF 8,100.000 $12.500 $27.280 $25.000 $24.500 $25.000 $24.850
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 32.000 $1,650.000 $2,324.240 $1,900.000 $1,969.000 $1,950.000 $1,969.000
MTL BEAM GD FEN TRANS (T101)
EA 20.000 $275.000 $1,717.920 $1,300.000 $1,375.000 $1,350.000 $1,375.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 4.000 $1,200.000 $1,515.810 $1,300.000 $1,460.000 $1,300.000 $1,460.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 28.000 $280.000 $808.430 $900.000 $1,215.000 $900.000 $1,215.000
REMOVE METAL BEAM GUARD FENCE
LF 6,347.000 $1.500 $1.770 $2.400 $2.300 $2.500 $3.250
GUARDRAIL END TREATMENT (INSTALL)
EA 62.000 $3,200.000 $3,031.620 $3,550.000 $3,050.000 $3,000.000 $3,525.000
GUARDRAIL END TREATMENT (REMOVE)
EA 62.000 $200.000 $303.160 $200.000 $250.000 $250.000 $350.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 44.000 $26.000 $60.000 $62.000 $40.000 $21.000 $40.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 128.000 $4.000 $50.000 $52.000 $48.000 $24.000 $48.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 60.000 $95.000 $115.000 $120.000 $98.500 $115.000 $98.500
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 4,128.000 $0.800 $0.260 $0.700 $0.250 $0.250 $1.000
WK ZN PAV MRK REMOV (W)6"(DOT)
LF 793.000 $1.000 $0.310 $1.350 $0.300 $0.300 $1.250
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 167,095.000 $0.500 $0.210 $0.300 $0.200 $0.200 $0.750
WK ZN PAV MRK REMOV (W)8"(DOT)
LF 563.000 $2.000 $2.060 $2.600 $2.000 $2.000 $1.500
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 1,017.000 $1.600 $1.030 $0.600 $1.000 $1.000 $1.500
WK ZN PAV MRK REMOV (W)(ARROW)
EA 11.000 $100.000 $154.200 $155.000 $150.000 $150.000 $40.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 11.000 $175.000 $205.590 $260.000 $200.000 $200.000 $45.000
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 9,696.000 $0.750 $0.260 $0.700 $0.250 $0.250 $1.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 124,545.000 $0.750 $0.210 $0.300 $0.200 $0.200 $0.750
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,832.000 $2.000 $1.600 $2.000 $1.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 19,627.000 $2.000 $1.600 $2.000 $1.000 $1.000 $1.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 120.000 $2.000 $2.060 $1.150 $2.000 $2.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,299.000 $1.250 $1.130 $1.000 $1.100 $1.100 $0.840
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 2,087.000 $0.600 $0.580 $0.700 $0.550 $0.600 $0.590
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 93,000.000 $0.600 $0.580 $0.500 $0.550 $0.600 $0.520
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 3,161.000 $0.600 $0.580 $0.700 $0.550 $0.600 $0.590
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 86,464.000 $0.600 $0.580 $0.500 $0.550 $0.600 $0.520
PREFAB PM TY C (W)(24")(SLD)
LF 64.000 $14.000 $20.560 $17.000 $20.000 $20.000 $13.000
PREFAB PM TY C (W)(ARROW)
EA 10.000 $215.000 $256.990 $155.000 $250.000 $250.000 $200.000
PREFAB PM TY C (W)(LN REDUCT ARROW)
EA 2.000 $450.000 $770.980 $500.000 $750.000 $750.000 $390.000
PREFAB PM TY C (W)(WORD)
EA 10.000 $275.000 $359.790 $260.000 $350.000 $350.000 $250.000
REFL PAV MRKR TY I-C
EA 254.000 $5.000 $4.630 $8.000 $4.500 $4.500 $3.800
REFL PAV MRKR TY II-A-A
EA 3,020.000 $5.000 $4.630 $5.000 $4.500 $4.500 $3.600
LITTER REMOVAL
AC 4.000 $100.000 $1,000.000 $1,560.000 $1,000.000 $750.000 $1,000.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 22.000 $1,327.000 $3,638.000 $1,560.000 $1,000.000 $2,500.000 $3,400.000
TREE REMOVAL (4" - 12" DIA)
EA 9.000 $43.000 $535.000 $470.000 $350.000 $275.000 $500.000
TREE REMOVAL (12" - 18" DIA)
EA 8.000 $75.000 $1,070.000 $1,000.000 $350.000 $450.000 $1,000.000
TREE REMOVAL (18" - 24" DIA)
EA 3.000 $110.000 $1,926.000 $1,560.000 $500.000 $850.000 $1,800.000
TREE REMOVAL (24" - 30" DIA)
EA 1.000 $251.000 $3,745.000 $1,880.000 $1,000.000 $1,800.000 $3,500.000
UNDERSEAL COURSE
GAL 74,621.000 $5.000 $3.210 $1.000 $4.000 $4.000 $0.050
Totals: $5,608,038.250 $5,311,274.020 $5,551,532.750 $5,810,892.400 $5,983,829.330 $6,074,611.160
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
Total: $50,000.00