LIVE OAK IH 37 (0074-01-055)
Items: 52
County: LIVE OAK
Length: N/A
Highway: IH 37
District: CORPUS CHRISTI
Control Number: 0074-01-055
DBE Goal: N/A
Project: C 74-1-55
Guaranty: N/A
Time: 119 WORKING DAYS
Engineer's Estimate: $1,927,012.90
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: REHAB AND WIDEN-WEST FRTG LANES ONLY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,927,012.90 | |||
| $1,839,971.96 |
-4.52%
-$87,040.94
|
|||
| $1,964,783.11 |
1.96%
$37,770.21
|
6.78%
$124,811.15
|
||
| $1,989,112.07 |
3.22%
$62,099.17
|
8.11%
$149,140.11
|
-1.24%
-$24,328.96
|
|
| $2,079,430.59 |
7.91%
$152,417.69
|
13.01%
$239,458.63
|
-4.54%
-$90,318.52
|
|
| $2,137,278.35 |
10.91%
$210,265.45
|
16.16%
$297,306.39
|
-2.78%
-$57,847.76
|
|
| $2,332,783.87 |
21.06%
$405,770.97
|
26.78%
$492,811.91
|
-9.15%
-$195,505.52
|
|
| $2,358,056.85 |
22.37%
$431,043.95
|
28.16%
$518,084.89
|
-1.08%
-$25,272.98
|
|
|
8
|
$2,687,433.13 |
39.46%
$760,420.23
|
46.06%
$847,461.17
|
-13.97%
-$329,376.28
|
E
Engineer's Estimate
$1,927,012.90
1
Awarded
$1,839,971.96
Over/Under Est:
-4.52%
-$87,040.94
$1,964,783.11
Over/Under Est:
1.96%
$37,770.21
Amt Left:
6.78%
$124,811.15
$1,989,112.07
Over/Under Est:
3.22%
$62,099.17
Amt Left:
8.11%
$149,140.11
Delta:
-1.24%
-$24,328.96
$2,079,430.59
Over/Under Est:
7.91%
$152,417.69
Amt Left:
13.01%
$239,458.63
Delta:
-4.54%
-$90,318.52
$2,137,278.35
Over/Under Est:
10.91%
$210,265.45
Amt Left:
16.16%
$297,306.39
Delta:
-2.78%
-$57,847.76
$2,332,783.87
Over/Under Est:
21.06%
$405,770.97
Amt Left:
26.78%
$492,811.91
Delta:
-9.15%
-$195,505.52
$2,358,056.85
Over/Under Est:
22.37%
$431,043.95
Amt Left:
28.16%
$518,084.89
Delta:
-1.08%
-$25,272.98
8
$2,687,433.13
Over/Under Est:
39.46%
$760,420.23
Amt Left:
46.06%
$847,461.17
Delta:
-13.97%
-$329,376.28
Bid Items & Bid Tabulations
52
Total
0 of 52