LIVE OAK IH 37 (0073-07-064)
Items: 79
County: LIVE OAK
Length: N/A
Highway: IH 37
District: CORPUS CHRISTI
Control Number: 0073-07-064
DBE Goal: N/A
Project: NH 2020(208)
Guaranty: N/A
Time: 121 WORKING DAYS
Engineer's Estimate: $6,900,251.85
Date: 11/06/2019 (6 years ago)
Contract Number: N/A
Type: REHAB AND OVERLAY WEST AND EAST FRONTAGE ROADS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,900,251.85 | |||
| $6,699,673.01 |
-2.91%
-$200,578.84
|
|||
| $7,139,999.74 |
3.47%
$239,747.89
|
6.57%
$440,326.73
|
||
| $7,604,547.66 |
10.21%
$704,295.81
|
13.51%
$904,874.65
|
-6.51%
-$464,547.92
|
|
| $7,640,458.38 |
10.73%
$740,206.53
|
14.04%
$940,785.37
|
-0.47%
-$35,910.72
|
|
| $7,707,344.39 |
11.7%
$807,092.54
|
15.04%
$1,007,671.38
|
-0.88%
-$66,886.01
|
|
| $8,453,001.30 |
22.5%
$1,552,749.45
|
26.17%
$1,753,328.29
|
-9.67%
-$745,656.91
|
E
Engineer's Estimate
$6,900,251.85
1
Awarded
$6,699,673.01
Over/Under Est:
-2.91%
-$200,578.84
$7,139,999.74
Over/Under Est:
3.47%
$239,747.89
Amt Left:
6.57%
$440,326.73
$7,604,547.66
Over/Under Est:
10.21%
$704,295.81
Amt Left:
13.51%
$904,874.65
Delta:
-6.51%
-$464,547.92
$7,640,458.38
Over/Under Est:
10.73%
$740,206.53
Amt Left:
14.04%
$940,785.37
Delta:
-0.47%
-$35,910.72
$7,707,344.39
Over/Under Est:
11.7%
$807,092.54
Amt Left:
15.04%
$1,007,671.38
Delta:
-0.88%
-$66,886.01
$8,453,001.30
Over/Under Est:
22.5%
$1,552,749.45
Amt Left:
26.17%
$1,753,328.29
Delta:
-9.67%
-$745,656.91
Bid Items & Bid Tabulations
79
Total
0 of 79