LIPSCOMB SH 23 (1337-01-026)

Items: 81

County: LIPSCOMB
Length: 1.6690 MILES
Highway: SH 23
District: AMARILLO
Control Number: 1337-01-026
DBE Goal: 7.0%
Project: BR 2025(551)
Guaranty: $100,000.00
Time: 172 WORKING DAYS
Engineer's Estimate: $19,101,995.50
Date: 03/04/2025 (1 year ago)
Contract Number: 3253006
Type: BRIDGE REPLACEMENT
Project ID: A00130847
Contract Type: Federal
Project Description: REPLACE EXISTING BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ZACHARY MAYER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$19,101,995.50
$18,726,656.18
Over/Under Est: -1.96% -$375,339.32
Over/Under Est: 10.42% $1,991,138.75
Amt Left: 12.64% $2,366,478.07
$22,991,544.97
Over/Under Est: 20.36% $3,889,549.47
Amt Left: 22.77% $4,264,888.79
Delta: -9.00% -$1,898,410.72
Over/Under Est: 21.19% $4,047,080.99
Amt Left: 23.62% $4,422,420.31
Delta: -0.69% -$157,531.52
$31,672,541.10
Over/Under Est: 65.81% $12,570,545.60
Amt Left: 69.13% $12,945,884.92
Delta: -36.82% -$8,523,464.61
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 5.79% $1,084,273.39
JB PINNACLE GROUP, LLC 1.71% $320,225.82
MORRIS COUNTY CONTRACTORS, L.L.C. 1.36% $254,682.52
LANCO TURF & SEEDING, INC. 0.47% $88,015.28
TRP CONSTRUCTION GROUP, LLC 0.34% $63,670.63
TORO BRAVO CONSTRUCTION, LLC 0.31% $58,052.63
TORO BRAVO CONSTRUCTION, LLC 0.16% $29,962.65
FC TRAFFIC CONTROL, INC. 0.07% $13,108.66
WEST TEXAS RUMBLE STRIP LLC 0.00% $0.00
PENHALL COMPANY 0.00% $0.00
S & S BRIDGE PAINTING, INC. 0.00% $0.00
Total: 10.21% $1,911,991.58

Bid Items & Bid Tabulations

81 Total 0 of 81
LIPSCOMB  |  SH 23  |  AMARILLO  |  1337-01-026  |  03/04/2025  |  $19,101,995.50  |  BR 2025(551)  |  BRIDGE REPL  |  172 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EARTH BUILDERS, L.P.
COPPELL CONSTRUCTION CO., INC.
WEBBER, LLC
KIEWIT INFRASTRUCTURE SOUTH CO.
C. E. BARKER, LTD.
PREP ROW (TREE REMOVE) (0"-12" DIA)
EA 126.000 $100.000 $1,000.000 $160.000 $500.000 $928.210 $498.440
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 13.000 $1,000.000 $1,500.000 $300.000 $2,000.000 $1,856.430 $712.050
PREP ROW (TREE REMOVE) (24"-36" DIA)
EA 4.000 $1,600.000 $2,000.000 $2,000.000 $4,000.000 $2,784.640 $925.670
REMOV CONC (RIPRAP)
SY 849.000 $60.000 $10.000 $40.000 $19.550 $47.660 $54.610
REMOV CONC (MISC)
SY 307.000 $60.000 $20.000 $111.000 $61.330 $95.640 $76.530
RMV (7"-11") TRT/UNTRT BASE & ASPH PAV
SY 2,010.000 $14.000 $20.000 $21.000 $26.880 $19.410 $43.060
EXCAV (ROADWAY)
CY 6,828.000 $22.000 $30.000 $21.000 $46.770 $28.580 $45.460
EMBANK (FNL)(DC)(TY B)
CY 4,569.000 $44.000 $30.000 $46.000 $41.570 $47.310 $71.920
DRILL SEED (PERM_RURAL_SAND)
AC 3.500 $625.000 $2,200.000 $2,080.000 $2,080.000 $3,064.580 $2,136.150
DRILL SEED (TEMP_WARM_COOL)
AC 3.500 $500.000 $2,200.000 $1,940.000 $1,940.000 $2,858.310 $2,136.150
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
SY 1,049.000 $5.000 $6.000 $2.250 $3.000 $2.900 $21.360
SP MIXES SP-B PG64-22
TON 1,472.000 $195.000 $280.000 $160.000 $355.000 $354.230 $448.590
SP MIXES SP-D SAC-A PG70-28
TON 1,155.000 $220.000 $300.000 $500.000 $390.000 $350.930 $534.040
TACK COAT
GAL 1,799.000 $6.000 $8.000 $15.000 $15.000 $11.610 $18.510
PLANE ASPH CONC PAV(0" TO 2")
SY 1,973.000 $10.000 $8.000 $15.000 $14.760 $28.710 $56.960
CEM STABIL BKFL
CY 369.000 $320.000 $450.000 $310.000 $488.360 $265.380 $347.120
SHEET PILING (PZ - 22)
SF 5,650.000 $44.000 $100.000 $70.000 $59.200 $56.010 $227.050
DRILL SHAFT (18 IN)
LF 438.000 $300.000 $200.000 $750.000 $678.040 $139.330 $280.920
DRILL SHAFT (36 IN)
LF 976.000 $500.000 $550.000 $950.000 $989.270 $530.370 $733.070
DRILL SHAFT (48 IN)
LF 1,740.000 $700.000 $700.000 $1,200.000 $1,628.170 $900.000 $2,262.550
CL C CONC (ABUT)
CY 119.000 $2,250.000 $3,000.000 $5,500.000 $5,614.900 $4,380.190 $5,005.760
CL C CONC (CAP)
CY 536.400 $2,250.000 $3,000.000 $3,000.000 $4,596.540 $2,652.670 $3,345.100
CL C CONC (COLUMN)
CY 110.900 $1,800.000 $3,000.000 $2,200.000 $3,739.230 $2,208.860 $2,690.140
CLASS K CONCRETE (MISC)
CY 37.200 $4,000.000 $3,000.000 $1,300.000 $5,767.090 $9,664.730 $3,083.180
APPROACH SLAB
CY 217.800 $1,150.000 $1,500.000 $1,100.000 $1,918.490 $1,315.260 $1,409.450
REINF CONC SLAB (PRECAST SUPER ASSEM)
SF 54,740.000 $66.000 $60.000 $73.000 $12.550 $0.010 $133.430
PRESTR CONC GIRDER (TX28)
LF 9,452.000 $350.000 $250.000 $277.000 $225.000 $750.000 $215.000
EPOXY WATERPROOF FINISH (TY X)
SF 2,985.000 $13.500 $10.000 $8.000 $14.710 $21.320 $17.800
RIPRAP (CONC)(4 IN)
CY 472.000 $760.000 $850.000 $800.000 $817.650 $1,304.480 $762.060
RIPRAP (CONC)(FLUME)
CY 14.000 $760.000 $850.000 $950.000 $1,055.350 $2,059.700 $867.880
RIPRAP (MOW STRIP)(4 IN)
CY 140.000 $760.000 $850.000 $800.000 $794.070 $1,270.150 $771.010
RIPRAP (STONE PROTECTION)(12 IN)
CY 992.000 $300.000 $200.000 $275.000 $283.200 $236.740 $276.850
RIPRAP (STONE PROTECTION)(24 IN)
CY 988.000 $440.000 $200.000 $330.000 $291.170 $205.230 $269.380
RAIL (TY T223)
LF 2,524.000 $150.000 $200.000 $185.000 $365.320 $245.230 $249.170
HEADER TYPE EXPANSION JOINT
CF 61.600 $440.000 $400.000 $470.000 $528.650 $780.950 $689.260
JOINT SEALANT
LF 368.000 $35.000 $45.000 $52.000 $125.920 $104.420 $115.350
DIAMOND GRINDING SLAB (ABC)
SY 6,084.000 $36.000 $10.000 $8.500 $10.100 $10.580 $9.480
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 3.000 $300,000.000 $450,000.000 $200,000.000 $777,660.560 $89,169.140 $138,019.030
MOBILIZATION
LS 1.000 $1,650,000.000 $2,000,000.000 $2,000,000.000 $2,250,000.000 $2,263,392.640 $2,834,595.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $17,500.000 $15,000.000 $40,000.000 $95,000.000 $160,000.000 $246,904.760
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $15,000.000 $20,000.000 $9,500.000 $22,500.000 $27,791.790 $42,723.000
TMA (STATIONARY)
DAY 70.000 $400.000 $350.000 $550.000 $421.760 $588.550 $1,708.920
TMA (MOBILE OPERATION)
HR 24.000 $150.000 $150.000 $250.000 $104.170 $121.040 $1,068.080
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 468.000 $40.000 $70.000 $60.000 $36.770 $15.970 $49.840
CONSTRUCTION EXITS (REMOVE)
SY 468.000 $20.000 $20.000 $22.000 $14.120 $44.770 $28.480
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 9,575.000 $6.000 $10.000 $3.000 $2.950 $3.800 $71.210
BIODEG EROSN CONT LOGS (REMOVE)
LF 9,575.000 $3.000 $2.000 $0.600 $0.600 $0.770 $28.480
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 1,560.000 $28.000 $0.010 $30.000 $30.290 $100.000 $58.970
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 8,160.000 $15.000 $0.010 $12.000 $12.450 $7.820 $49.840
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 1,560.000 $28.000 $0.010 $25.000 $13.770 $17.540 $58.970
PORT CTB (CONNECTION HARDWARE)
EA 104.000 $44.000 $0.010 $65.000 $360.590 $96.080 $149.530
INTERSECTIONS (ACP)
SY 103.000 $65.000 $165.000 $250.000 $162.500 $95.010 $213.620
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 4,590.000 $0.200 $3.000 $3.000 $1.170 $0.420 $0.470
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 2,180.000 $0.200 $3.000 $3.000 $2.210 $0.670 $0.730
MTL W-BEAM GD FEN (STEEL POST)
LF 1,875.000 $36.000 $35.000 $30.000 $40.010 $46.040 $71.210
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 11.000 $3,100.000 $2,500.000 $2,500.000 $2,652.000 $3,071.540 $3,560.250
REMOVE METAL BEAM GUARD FENCE
LF 4,196.000 $3.000 $4.000 $3.000 $4.080 $9.050 $14.240
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $3,750.000 $3,400.000 $7,100.000 $3,366.000 $4,238.310 $4,984.350
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $500.000 $300.000 $200.000 $408.000 $738.010 $1,068.080
CRASH CUSH ATTEN (MOVE & RESET)
EA 26.000 $3,000.000 $0.010 $2,500.000 $4,182.000 $885.770 $7,120.500
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,200.000 $0.010 $1,000.000 $2,550.000 $505.820 $2,136.150
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $30,000.000 $25,000.000 $25,000.000 $30,294.000 $46,620.580 $42,723.000
CCA (INSTL)(N)(TL3)(WORK ZONE)
EA 4.000 $10,000.000 $0.010 $10,000.000 $10,455.000 $13,591.300 $9,256.650
REMOVE AND INSTALL EXISTING GATE
EA 1.000 $1,000.000 $1,500.000 $4,000.000 $4,500.000 $1,630.660 $7,476.530
WIRE FENCE (TY C)
LF 2,320.000 $16.000 $25.000 $35.000 $55.160 $36.900 $58.390
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $1,000.000 $1,200.000 $1,000.000 $1,893.510 $1,082.420 $1,780.130
REMOVE SM RD SN SUP&AM
EA 14.000 $150.000 $150.000 $100.000 $210.390 $140.570 $925.670
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 28.000 $35.000 $30.000 $20.000 $35.700 $65.370 $106.810
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 31.000 $35.000 $35.000 $25.000 $41.820 $65.370 $106.810
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 7,460.000 $0.700 $3.000 $2.500 $2.500 $3.220 $2.850
PAVEMENT SLER 6"
LF 4,680.000 $0.200 $1.000 $1.000 $0.750 $0.970 $1.420
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 7,120.000 $0.850 $3.500 $3.000 $3.000 $3.870 $2.850
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 190.000 $0.850 $3.500 $3.000 $3.000 $3.870 $2.850
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 5,480.000 $0.850 $3.500 $3.000 $3.000 $3.870 $2.850
PREFAB PM TY C (W)(24")(SLD)
LF 30.000 $20.000 $30.000 $25.000 $25.000 $32.230 $28.480
REFL PAV MRKR TY II-A-A
EA 89.000 $7.000 $12.000 $10.000 $10.000 $12.890 $71.210
PAV SURF PREP FOR MRK (6")
LF 4,680.000 $0.200 $1.000 $0.500 $0.500 $0.640 $1.420
TIP TESTING(DRILL SHAFT)
EA 40.000 $8,000.000 $4,200.000 $4,500.000 $8,500.000 $5,363.010 $7,120.500
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 6.000 $300.000 $1,000.000 $500.000 $356.090 $408.860 $890.060
ULTRA-HIGH PERFORMANCE CONCRETE
CY 86.200 $12,500.000 $6,000.000 $8,000.000 $6,419.180 $17,000.000 $498.440
INSTALL BAT HOUSE MEDIUM
EA 2.000 $2,750.000 $1,500.000 $5,000.000 $7,327.350 $4,604.810 $2,171.750
Totals: $19,101,995.500 $18,726,656.180 $21,093,134.250 $22,991,544.959 $23,149,076.481 $31,672,541.076
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $20,000.00