LEON IH 45 (0675-04-069)
Items: 50
County: LEON
Length: N/A
Highway: IH 45
District: BRYAN
Control Number: 0675-04-069
DBE Goal: N/A
Project: C 675-4-69
Guaranty: N/A
Time: 175 WORKING DAYS
Engineer's Estimate: $19,451,438.35
Date: 12/02/2022 (3 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
DELMY REYES
MATT HENSARLING
Bidders (1)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$19,451,438.35 | |||
| $17,287,257.60 |
-11.13%
-$2,164,180.75
|
E
Engineer's Estimate
$19,451,438.35
1
Awarded
$17,287,257.60
Over/Under Est:
-11.13%
-$2,164,180.75
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPING TECHNOLOGY, L.P. | 3.06% | $528,990.08 |
| SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. | 0.71% | $122,739.53 |
| CPAVE, INC. | 0.55% | $95,079.92 |
| FLASHER EQUIPMENT COMPANY | 0.13% | $22,473.43 |
| WEST TEXAS ROCK RESOURCES, LLC | 0.13% | $22,473.43 |
| Total: | 4.58% | $791,756.39 |
Bid Items & Bid Tabulations
50
Total
0 of 50