LEE US 77 (0211-02-026)

Items: 53

County: LEE
Length: N/A
Highway: US 77
District: AUSTIN
Control Number: 0211-02-026
DBE Goal: N/A
Project: NH 2018(531)
Guaranty: N/A
Time: 86 WORKING DAYS
Engineer's Estimate: $7,209,200.22
Date: 02/01/2018 (8 years ago)
Contract Number: N/A
Type: LEVEL-UP, FULL DEPTH REPAIR AND TOM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$7,209,200.22
$5,387,885.79
Over/Under Est: -25.26% -$1,821,314.43
Over/Under Est: -23.6% -$1,701,425.37
Amt Left: 2.23% $119,889.06
Over/Under Est: -17.11% -$1,233,315.64
Amt Left: 10.91% $587,998.79
Delta: -8.50% -$468,109.73
Over/Under Est: -15.75% -$1,135,697.46
Amt Left: 12.73% $685,616.97
Delta: -1.63% -$97,618.18
Over/Under Est: -0.58% -$41,940.14
Amt Left: 33.03% $1,779,374.29
Delta: -18.01% -$1,093,757.32
Over/Under Est: 1.86% $133,993.78
Amt Left: 36.29% $1,955,308.21
Delta: -2.45% -$175,933.92
$7,459,053.11
Over/Under Est: 3.47% $249,852.89
Amt Left: 38.44% $2,071,167.32
Delta: -1.58% -$115,859.11

Bid Items & Bid Tabulations

53 Total 0 of 53
LEE  |  US 77  |  AUSTIN  |  0211-02-026  |  02/01/2018  |  $7,209,200.22  |  NH 2018(531)  |  LEVEL-UP, FULL DEPTH REPAIR AND TOM  |  86 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
LONE STAR PAVING COMPANY
ANGEL BROTHERS HOLDINGS CORP.
HUNTER INDUSTRIES, LTD.
OLDCASTLE MATERIALS TEXAS, INC.
AUSTIN MATERIALS, LLC
PREPARING ROW
STA 927.010 $250.000 $100.000 $98.000 $100.000 $200.000 $338.910 $175.000 $243.000
REMOVING CONC (SIDEWALKS)
SY 38.000 $25.000 $30.000 $31.000 $25.000 $16.000 $78.000 $50.000 $150.000
BACKFILL (TY A)
STA 852.820 $70.000 $50.000 $53.000 $40.000 $100.000 $135.750 $150.000 $104.500
D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP)
TON 11,906.000 $75.000 $60.000 $65.600 $65.000 $68.500 $68.060 $79.000 $78.750
TOM (ASPHALT) PG 76-22
TON 1,769.000 $95.000 $87.000 $507.000 $90.000 $85.250 $103.130 $96.000 $99.250
TOM-C (AGGREGATE) SAC-A
TON 27,538.000 $95.000 $87.000 $54.800 $90.000 $85.250 $103.130 $96.000 $99.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 57,247.000 $30.000 $20.000 $22.950 $29.000 $26.500 $26.220 $34.000 $29.750
PLANE ASPH CONC PAV(0" TO 1")
SY 165,901.000 $1.500 $0.800 $0.530 $0.600 $0.900 $1.070 $1.000 $1.430
CLEANING AND SEALING EXISTING JOINTS
LF 490.000 $20.000 $30.000 $25.000 $25.000 $23.000 $26.400 $22.000 $26.000
MOBILIZATION
LS 1.000 $517,640.000 $38,000.000 $87,000.000 $125,000.000 $282,000.000 $519,740.870 $650,000.000 $524,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,500.000 $3,000.000 $3,350.000 $5,000.000 $2,500.000 $2,204.470 $9,500.000 $29,750.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 40.000 $2.750 $10.000 $4.500 $5.000 $5.000 $10.000 $35.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 40.000 $0.850 $1.000 $3.000 $3.000 $1.000 $10.000 $35.000 $5.000
CONC SIDEWALKS (4")
SY 6.000 $300.000 $300.000 $545.000 $135.000 $105.000 $175.000 $100.000 $250.000
CURB RAMPS
SY 32.000 $450.000 $100.000 $334.000 $265.000 $105.000 $200.000 $195.000 $350.000
RUMBLE STRIPS (CENTERLINE)
LF 56,233.000 $0.250 $0.190 $0.180 $0.200 $0.350 $0.180 $0.180 $0.210
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $500.000 $500.000 $600.000 $550.000 $670.000 $750.000 $750.000 $200.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 50,880.000 $0.300 $0.120 $0.110 $0.110 $0.110 $0.110 $0.110 $0.110
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 218,262.000 $0.350 $0.120 $0.110 $0.110 $0.110 $0.110 $0.110 $0.110
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 215.000 $0.750 $1.000 $0.260 $0.250 $0.250 $0.220 $0.250 $0.250
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 11,684.000 $0.450 $0.120 $0.110 $0.110 $0.110 $0.110 $0.110 $0.110
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 219,691.000 $0.300 $0.120 $0.110 $0.110 $0.110 $0.110 $0.110 $0.110
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 21,181.000 $1.000 $0.800 $0.900 $0.450 $0.500 $1.250 $1.400 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 20,008.000 $1.000 $0.800 $0.900 $0.450 $0.500 $1.250 $1.400 $1.000
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 6,735.000 $1.750 $1.000 $1.000 $0.750 $0.750 $1.000 $1.400 $0.820
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 22,716.000 $1.500 $1.200 $1.000 $0.750 $0.750 $1.000 $1.400 $0.820
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 215.000 $1.250 $1.000 $0.780 $0.750 $0.750 $0.600 $0.750 $0.750
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 768.000 $1.950 $3.000 $3.630 $3.500 $3.500 $3.000 $3.500 $3.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 424.000 $6.000 $6.000 $6.220 $6.000 $6.000 $5.500 $6.000 $6.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 4.000 $150.000 $100.000 $103.630 $100.000 $100.000 $75.000 $100.000 $100.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 4.000 $125.000 $125.000 $119.180 $120.000 $115.000 $95.000 $115.000 $115.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 5.000 $40.000 $60.000 $36.270 $35.000 $35.000 $55.000 $35.000 $35.000
PAVEMENT SEALER 4"
LF 5,402.000 $0.050 $0.110 $0.370 $0.350 $0.360 $0.100 $0.360 $0.360
PAVEMENT SEALER 8"
LF 196.000 $0.200 $0.110 $0.750 $0.750 $0.720 $0.100 $0.720 $0.720
PAVEMENT SEALER 12"
LF 320.000 $1.000 $0.600 $1.970 $2.000 $1.900 $0.500 $1.900 $1.900
PAVEMENT SEALER 24"
LF 88.000 $1.500 $1.000 $3.940 $4.000 $3.800 $0.500 $3.800 $3.800
PAVEMENT SEALER (ARROW)
EA 4.000 $55.000 $15.000 $77.720 $75.000 $75.000 $10.000 $75.000 $75.000
PAVEMENT SEALER (WORD)
EA 4.000 $55.000 $15.000 $88.090 $90.000 $85.000 $10.000 $85.000 $85.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 41,442.000 $0.400 $0.340 $0.290 $0.290 $0.280 $0.330 $0.280 $0.280
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 45,290.000 $0.400 $0.310 $0.290 $0.290 $0.280 $0.300 $0.280 $0.280
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 10,447.000 $0.400 $0.340 $0.290 $0.290 $0.280 $0.330 $0.280 $0.280
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 181,270.000 $0.400 $0.310 $0.260 $0.250 $0.250 $0.300 $0.250 $0.250
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 140,112.000 $0.550 $0.900 $0.610 $0.600 $0.590 $0.850 $0.590 $0.590
REFL PAV MRKR TY I-C
EA 2,129.000 $4.500 $3.000 $3.370 $3.250 $3.250 $2.770 $3.250 $3.250
REFL PAV MRKR TY II-A-A
EA 3,101.000 $4.500 $3.000 $3.370 $3.250 $3.250 $2.650 $3.250 $3.250
PAV SURF PREP FOR MRK (4")
LF 5,402.000 $0.010 $0.220 $0.310 $0.300 $0.300 $0.200 $0.300 $0.300
PAV SURF PREP FOR MRK (8")
LF 196.000 $0.200 $0.550 $0.620 $0.600 $0.600 $0.500 $0.600 $0.600
PAV SURF PREP FOR MRK (12")
LF 320.000 $0.250 $1.100 $1.760 $1.770 $1.700 $1.000 $1.700 $1.700
PAV SURF PREP FOR MRK (24")
LF 88.000 $0.150 $2.200 $3.470 $3.500 $3.350 $2.000 $3.350 $3.350
PAV SURF PREP FOR MRK (ARROW)
EA 4.000 $25.000 $25.000 $72.540 $70.000 $70.000 $20.000 $70.000 $70.000
PAV SURF PREP FOR MRK (WORD)
EA 4.000 $25.000 $25.000 $77.720 $75.000 $75.000 $20.000 $75.000 $75.000
UNDERSEAL COURSE
GAL 101,056.000 $2.250 $2.500 $3.190 $2.000 $2.000 $2.890 $1.000 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 30.000 $100.000 $100.000 $25.000 $65.000 $100.000 $83.350 $175.000 $83.500
Totals: $7,209,200.220 $5,387,885.790 $5,507,774.850 $5,975,884.580 $6,073,502.760 $7,167,260.094 $7,343,194.000 $7,459,053.110