Show Job Controls
Bid Cobra

LEE US 290 (0114-07-036)

Items: 125

County: LEE
Length: N/A
Highway: US 290
District: AUSTIN
Control Number: 0114-07-036
DBE Goal: N/A
Project: NH 2019(609)
Guaranty: N/A
Time: 549 WORKING DAYS
Engineer's Estimate: $30,340,010.90
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: WIDEN GR STRS BS & SURF
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$30,340,010.90
$28,375,953.87
Over/Under Est: -6.47% -$1,964,057.03
Over/Under Est: 6.57% $1,993,630.12
Amt Left: 13.95% $3,957,687.15
$32,375,314.69
Over/Under Est: 6.71% $2,035,303.79
Amt Left: 14.09% $3,999,360.82
Delta: -0.13% -$41,673.67
Over/Under Est: 7.49% $2,271,143.91
Amt Left: 14.93% $4,235,200.94
Delta: -0.73% -$235,840.12

Bid Items & Bid Tabulations

125 Total 0 of 125
LEE  |  US 290  |  AUSTIN  |  0114-07-036  |  03/06/2019  |  $30,340,010.90  |  NH 2019(609)  |  WIDEN GR STRS BS & SURF  |  549 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
ANGEL BROTHERS HOLDINGS CORP.
HUNTER INDUSTRIES, LTD.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 375.000 $2,500.000 $1,500.000 $2,175.000 $1,421.280 $3,250.000
REMOVING CONC (RIPRAP)
SY 7.000 $15.000 $50.000 $80.000 $73.260 $65.000
REMOV STAB BASE AND ASPH PAV (22")
SY 39,313.000 $8.000 $5.000 $7.350 $6.660 $6.700
EXCAVATION (ROADWAY)
CY 113,250.000 $6.000 $5.000 $6.650 $7.890 $3.500
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 282,818.000 $8.000 $5.000 $12.650 $8.240 $15.100
FURNISHING AND PLACING TOPSOIL (4")
SY 600,791.000 $0.750 $0.500 $0.500 $0.850 $0.800
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 600,791.000 $0.300 $0.120 $0.100 $0.190 $0.150
VEGETATIVE WATERING
MG 13,609.000 $17.750 $5.000 $5.000 $19.980 $15.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 75,250.000 $1.000 $1.000 $0.850 $1.050 $1.000
SOIL RETENTION BLANKETS (CL 2) (TY E)
SY 51,516.000 $1.500 $1.000 $0.950 $1.350 $4.500
PROOF ROLLING
HR 40.000 $100.000 $100.000 $83.000 $79.800 $90.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 47,723.000 $50.000 $47.000 $59.000 $56.270 $59.000
LIME (HYDRATED LIME (SLURRY))
TON 3,024.000 $150.000 $165.000 $170.000 $162.750 $200.000
LIME TRT (EXST MATL)(8")
SY 168,223.000 $2.500 $2.000 $1.550 $1.820 $3.500
CEMENT
TON 1,008.000 $150.000 $140.000 $140.000 $136.500 $155.000
CEMENT TREAT(EXIST MATL)(8")
SY 56,081.000 $2.500 $1.500 $1.500 $1.710 $1.750
PRIME COAT (MULTI OPTION)
GAL 42,944.000 $3.000 $3.500 $3.750 $3.830 $3.630
D-GR HMA(SQ) TY-B PG64-22 (LEVEL UP)
TON 54,466.000 $65.000 $62.000 $66.250 $66.360 $52.800
D-GR HMA TY-B PG64-22
TON 133,796.000 $57.000 $58.000 $64.000 $66.360 $51.400
D-GR HMA TY-D SAC-B PG70-22
TON 424.000 $70.000 $90.000 $83.500 $83.340 $80.000
D-GR HMA TY-D PG70-22
TON 16,171.000 $70.000 $68.000 $73.000 $78.000 $65.000
PFC (ASPHALT) PG76-22
TON 1,458.000 $110.000 $102.000 $115.000 $122.100 $99.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 22,841.000 $110.000 $102.000 $115.000 $122.100 $99.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 4,800.000 $25.000 $30.000 $30.500 $35.310 $29.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 8,400.000 $15.000 $15.000 $16.250 $17.660 $17.000
CUT & RESTORING PAV
SY 127.000 $100.000 $75.000 $128.000 $105.000 $100.000
FLOWABLE BACKFILL
CY 359.000 $145.000 $125.000 $125.000 $136.500 $135.000
RIPRAP (CONC)(4 IN)
CY 124.000 $380.000 $400.000 $450.000 $471.180 $500.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 179.000 $200.000 $175.000 $95.000 $120.750 $165.000
RIPRAP (MOW STRIP)(4 IN)
CY 117.000 $450.000 $500.000 $450.000 $461.620 $525.000
RC PIPE (CL III)(18 IN)
LF 3,482.000 $52.500 $45.000 $40.000 $47.250 $78.000
RC PIPE (CL III)(24 IN)
LF 1,989.000 $70.000 $55.000 $84.000 $52.500 $84.000
RC PIPE (CL III)(30 IN)
LF 864.000 $80.000 $65.000 $105.000 $75.600 $110.000
RC PIPE (CL III)(36 IN)
LF 753.000 $200.000 $100.000 $130.000 $92.400 $132.000
RC PIPE (CL III)(42 IN)
LF 472.000 $220.000 $125.000 $182.000 $131.250 $165.000
RC PIPE (CL III)(48 IN)
LF 97.000 $230.000 $150.000 $200.000 $152.240 $225.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 12.000 $4,000.000 $4,000.000 $3,250.000 $3,674.880 $3,800.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $5,000.000 $5,000.000 $4,250.000 $4,724.840 $5,300.000
HEADWALL (CH - FW - 0) (DIA= 24 IN)
EA 1.000 $5,300.000 $4,000.000 $2,000.000 $5,564.810 $8,300.000
HEADWALL (CH - FW - 0) (DIA= 30 IN)
EA 3.000 $5,500.000 $5,000.000 $3,000.000 $5,459.810 $8,900.000
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 5.000 $6,000.000 $6,000.000 $4,000.000 $5,459.810 $11,000.000
HEADWALL (CH - FW - 0) (DIA= 42 IN)
EA 4.000 $6,500.000 $6,500.000 $5,500.000 $5,774.800 $14,000.000
HEADWALL (CH - FW - 0) (DIA= 48 IN)
EA 1.000 $7,000.000 $10,000.000 $7,000.000 $6,824.770 $18,000.000
HEADWALL (CH - FW - 15) (DIA= 36 IN)
EA 1.000 $6,800.000 $6,000.000 $5,500.000 $8,399.710 $9,200.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $6,000.000 $10,000.000 $4,500.000 $9,712.170 $12,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 1.000 $900.000 $800.000 $750.000 $1,259.960 $1,400.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 103.000 $975.000 $800.000 $750.000 $1,049.960 $1,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 3.000 $1,700.000 $1,000.000 $900.000 $1,049.960 $1,800.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 54.000 $1,200.000 $1,000.000 $900.000 $1,154.960 $1,400.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $2,200.000 $1,500.000 $2,000.000 $1,049.960 $2,200.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 22.000 $2,300.000 $2,500.000 $2,500.000 $1,259.960 $2,800.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 1.000 $3,000.000 $2,000.000 $3,000.000 $2,652.620 $3,900.000
MOBILIZATION
LS 1.000 $2,428,100.000 $2,800,000.750 $2,205,000.000 $2,638,173.390 $2,650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 28.000 $5,000.000 $5,000.000 $2,400.000 $3,207.960 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 5,480.000 $25.000 $28.000 $25.000 $29.500 $28.500
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 554.000 $45.000 $46.000 $43.000 $60.000 $42.500
ROCK FILTER DAMS (REMOVE)
LF 6,034.000 $7.500 $3.000 $7.000 $15.750 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 13,316.000 $2.250 $3.000 $2.750 $2.150 $2.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 13,316.000 $1.000 $0.250 $0.250 $0.350 $0.750
CONSTRUCTING DETOURS
SY 1,387.000 $60.000 $75.000 $69.000 $32.850 $59.730
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 2,975.000 $35.000 $40.000 $40.000 $10.000 $38.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 2,975.000 $8.000 $8.500 $5.000 $10.000 $15.000
CONC CURB & GUTTER (TY II)
LF 885.000 $20.000 $20.000 $28.000 $19.840 $28.000
DRIVEWAYS (CONC)
SY 759.000 $83.000 $70.000 $90.000 $67.800 $95.000
DRIVEWAYS (ACP)
SY 10,449.000 $42.500 $20.000 $30.000 $29.610 $35.730
TURNOUTS (ACP)
SY 730.000 $35.000 $50.000 $41.000 $39.420 $70.850
CONC SIDEWALKS (4")
SY 450.000 $60.000 $50.000 $65.000 $46.650 $70.000
CURB RAMPS (TY 7)
EA 5.000 $1,900.000 $1,500.000 $2,500.000 $1,627.440 $2,600.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,048.000 $20.000 $22.000 $20.150 $22.020 $20.150
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,100.000 $1,200.000 $895.000 $1,027.390 $895.000
CABLE BARRIER SYSTEM (TL-4)
LF 19,590.000 $10.000 $27.000 $25.000 $27.450 $26.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 23.000 $2,300.000 $2,500.000 $2,000.000 $3,941.070 $2,950.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,500.000 $3,000.000 $2,630.000 $2,826.680 $2,630.000
CRASH CUSH ATTEN (REMOVE)
EA 10.000 $800.000 $750.000 $850.000 $1,000.210 $850.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $11,000.000 $7,500.000 $6,500.000 $8,779.020 $8,523.000
CHAIN LINK FENCE(INSTALL)(6 )(BARB TOP)
LF 1,000.000 $25.000 $25.000 $32.750 $27.450 $26.500
PIPE UNDERDRAINS (TY 6) (6")
LF 500.000 $20.000 $30.000 $33.000 $30.000 $69.280
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 27.000 $200.000 $200.000 $185.000 $185.000 $185.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 5.000 $250.000 $250.000 $205.000 $210.000 $205.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 10.000 $550.000 $500.000 $450.000 $460.000 $450.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $450.000 $400.000 $483.000 $395.000 $483.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 22.000 $500.000 $600.000 $550.000 $535.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $550.000 $500.000 $545.000 $475.000 $545.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 129.000 $380.000 $300.000 $358.000 $270.000 $358.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 25.000 $475.000 $350.000 $375.000 $295.000 $375.000
REMOVE SM RD SN SUP&AM
EA 50.000 $85.000 $75.000 $100.000 $45.000 $100.000
INSTL DEL ASSM (D-DY)SZ 2(WC)GND
EA 22.000 $65.000 $60.000 $45.000 $55.000 $45.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 18.000 $65.000 $60.000 $45.000 $56.000 $45.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 34.000 $20.000 $40.000 $17.000 $29.000 $17.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,428.000 $4.000 $3.250 $2.500 $2.500 $2.950
WK ZN PAV MRK REMOV (REFL) TY II-C-R
EA 2,779.000 $3.000 $3.250 $2.500 $2.500 $2.950
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 31,451.000 $0.700 $1.000 $0.670 $0.670 $0.750
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 126,493.000 $0.500 $0.650 $0.550 $0.550 $0.600
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 17,112.000 $1.250 $1.300 $1.440 $1.440 $1.100
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 850.000 $6.000 $12.000 $6.000 $6.000 $10.000
WK ZN PAV MRK REMOV (W)(ARROW)
EA 42.000 $140.000 $150.000 $200.000 $200.000 $110.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 42.000 $150.000 $150.000 $200.000 $200.000 $110.000
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 14,071.000 $0.600 $0.700 $0.630 $0.630 $0.600
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 140,865.000 $0.600 $0.700 $0.550 $0.550 $0.600
WK ZN PAV MRK REMOV (Y)12"(SLD)
LF 871.000 $1.500 $7.000 $3.000 $3.000 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 7,122.000 $0.900 $1.000 $0.550 $1.500 $1.030
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,864.000 $0.800 $1.000 $0.550 $1.500 $1.030
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,291.000 $0.800 $1.200 $0.400 $0.400 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 18,675.000 $0.650 $0.900 $0.670 $0.670 $0.770
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 320.000 $6.500 $10.000 $5.000 $5.000 $6.250
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 66.000 $105.000 $150.000 $117.000 $117.000 $110.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 4.000 $345.000 $300.000 $224.000 $224.000 $235.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 44.000 $130.000 $175.000 $134.000 $134.000 $170.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 298.000 $35.000 $70.000 $37.000 $37.000 $55.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 18,955.000 $0.400 $0.420 $0.360 $0.360 $0.380
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 7,385.000 $0.300 $0.420 $0.360 $0.360 $0.380
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 30,635.000 $0.350 $0.420 $0.360 $0.360 $0.380
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 74,385.000 $0.700 $0.750 $0.680 $0.680 $0.700
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 43,205.000 $0.600 $0.750 $0.680 $0.680 $0.700
REFL PAV MRKR TY I-C
EA 378.000 $3.500 $4.000 $3.330 $3.330 $3.200
REFL PAV MRKR TY II-A-A
EA 746.000 $3.200 $4.000 $3.330 $3.330 $3.200
REFL PAV MRKR TY II-C-R
EA 2,427.000 $3.200 $4.000 $3.330 $3.330 $3.200
ELIM EXT PAV MRK & MRKS (4")
LF 103,608.000 $0.500 $0.500 $0.470 $0.470 $0.420
REMOVAL OF TIMBER POLES
EA 3.000 $950.000 $2,500.000 $550.000 $108.720 $560.780
FULL - WIDTH MOWING
CYC 6.000 $3,500.000 $10,000.000 $4,500.000 $3,500.000 $12,000.000
LITTER REMOVAL
CYC 6.000 $1,500.000 $2,500.000 $1,500.000 $1,250.000 $3,500.000
UNDERSEAL COURSE
GAL 71,984.000 $2.600 $3.000 $2.950 $3.270 $3.620
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $10,000.000 $7,500.000 $7,956.580 $10,000.000
TMA (STATIONARY)
DAY 311.000 $180.000 $150.000 $175.000 $167.620 $158.000
TMA (MOBILE OPERATION)
HR 232.000 $65.000 $50.000 $39.000 $68.960 $65.000
Totals: $30,340,010.900 $28,375,953.870 $32,333,641.020 $32,375,314.690 $32,611,154.810