LAVACA SH0095 (6484-96-001)

Items: 23

County: LAVACA
Length: 0.0100 MILES
Highway: SH0095
District: YOAKUM
Control Number: 6484-96-001
DBE Goal: N/A
Project: RMC - A00215731
Guaranty: $20,000.00
Time: 30 WORKING DAYS
Engineer's Estimate: $981,505.10
Date: 05/29/2025 (1 year ago)
Contract Number: 5251303
Type: ASPHALTIC CONCRETE PAVEMENT REPAIRS
Project ID: A00215731
Project Description: ASPHALTIC CONCRETE PAVEMENT REPAIRS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
403 HUCK ST, YOAKUM, TX 77995
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$981,505.10
$791,562.44
Over/Under Est: -19.35% -$189,942.66
Over/Under Est: -9.34% -$91,668.95
Amt Left: 12.42% $98,273.71
Over/Under Est: 16.08% $157,805.90
Amt Left: 43.93% $347,748.56
Delta: -28.04% -$249,474.85
Subcontractor Percentage Amount
STRIPE LINES, INC. 8.63% $69,421.76
CHEROKEE SERVICES 1.15% $9,250.87
Total: 9.78% $78,672.63

Bid Items & Bid Tabulations

23 Total 0 of 23
LAVACA  |  SH0095  |  YOAKUM  |  6484-96-001  |  05/29/2025  |  $981,505.10  |  RMC - A00215731  |  ASPHIC CONC PAVMT REPAIRS  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
BLACKSMITH VENTURES LLC
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 14,954.000 $4.500 $3.960 $4.850 $10.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 339.000 $180.000 $109.340 $127.500 $200.000
D-GR HMA TY-D SAC-B PG70-22
TON 4,839.000 $130.000 $99.000 $115.000 $120.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 100.000 $75.000 $52.360 $185.000 $150.000
PLANE CONC PAV(0" TO 2")
SY 43,979.000 $2.000 $1.430 $2.250 $4.000
ADJUSTING MANHOLES
EA 3.000 $1,000.000 $1,250.000 $2,000.000 $500.000
MOBILIZATION
LS 1.000 $65,000.000 $62,238.250 $40,000.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,000.000 $2,280.220 $4,000.000 $10,000.000
TMA (STATIONARY)
DAY 10.000 $250.000 $350.000 $100.000 $400.000
TMA (MOBILE OPERATION)
DAY 5.000 $250.000 $550.000 $100.000 $400.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 70.000 $1.500 $1.630 $1.000 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,086.000 $1.500 $1.630 $1.000 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 135.000 $1.000 $3.850 $1.400 $1.400
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 18,572.000 $0.850 $1.350 $0.750 $0.750
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 2,660.000 $0.850 $1.350 $1.000 $1.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 17,004.000 $0.850 $1.350 $0.750 $0.750
PREFAB PM TY C (W)(24")(SLD)
LF 621.000 $15.000 $15.250 $12.000 $12.000
PREFAB PM TY C (W)(ARROW)
EA 1.000 $220.000 $335.000 $300.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 1.000 $250.000 $345.000 $315.000 $315.000
PREFAB PM TY C (W)(RR XING)
EA 1.000 $600.000 $535.000 $775.000 $775.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 6.000 $30.000 $88.000 $60.000 $60.000
REFL PAV MRKR TY I-C
EA 7.000 $5.000 $6.080 $6.000 $6.000
REFL PAV MRKR TY II-A-A
EA 453.000 $6.500 $6.080 $6.000 $6.000
Totals: $981,505.100 $791,562.440 $889,836.150 $1,139,311.000