LAVACA UA 90 (0445-02-068)

Items: 88

County: LAVACA
Length: 0.5490 MILES
Highway: UA 90
District: YOAKUM
Control Number: 0445-02-068
DBE Goal: 0.0%
Project: STP 2026(340)HES
Guaranty: $46,000.00
Time: WORKING DAYS
Engineer's Estimate: $2,279,413.30
Date: 02/04/2026 (4 months ago)
Contract Number: 2263026
Type: INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT T
Project ID: A00184364
Contract Type: Federal
Project Description: ADD TURN LANE - HSIP
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,279,413.30
$2,212,468.60
Over/Under Est: -2.94% -$66,944.70
$2,371,341.28
Over/Under Est: 4.03% $91,927.98
Amt Left: 7.18% $158,872.68
Over/Under Est: 4.3% $98,029.10
Amt Left: 7.46% $164,973.80
Delta: -0.26% -$6,101.12
Over/Under Est: 15.62% $355,979.61
Amt Left: 19.12% $422,924.31
Delta: -10.85% -$257,950.51
Over/Under Est: 15.2% $346,557.48
Amt Left: 18.69% $413,502.18
Delta: 0.36% $9,422.13
Over/Under Est: 25.81% $588,389.70
Amt Left: 29.62% $655,334.40
Delta: -9.21% -$241,832.22
Over/Under Est: 39.82% $907,586.10
Amt Left: 44.05% $974,530.80
Delta: -11.13% -$319,196.40

Bid Items & Bid Tabulations

88 Total 0 of 88
LAVACA  |  UA 90  |  YOAKUM  |  0445-02-068  |  02/04/2026  |  $2,279,413.30  |  STP 2026(340)HES  |  INTERS IMPRVS WITH RIGHT AND/OR LEFT...  |  WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
STX CIVIL
E-Z BEL CONSTRUCTION, LLC
CLARK CONSTRUCTION OF TEXAS, INC.
DEAN WORD COMPANY, LTD.
ACME BRIDGE COMPANY, INC.
MATAGORDA CONSTRUCTION & MATERIALS
PREPARING ROW
STA 7.000 $3,000.000 $1,098.900 $2,650.000 $10,500.000 $3,572.000 $8,700.000 $3,400.000 $3,000.000
REMOV CONC (DRIVEWAYS)
SY 99.000 $8.000 $19.800 $21.000 $30.000 $25.000 $28.250 $31.800 $62.000
EXCAV (ROADWAY)
CY 3,538.000 $15.000 $16.500 $10.000 $12.000 $14.850 $16.000 $22.600 $17.000
EMBANK (FNL)(DC)(TY C)
CY 4,441.000 $16.000 $19.710 $18.500 $14.000 $22.370 $16.000 $17.500 $17.000
BACKFILL (TY A)
STA 8.500 $500.000 $131.510 $250.000 $205.000 $408.810 $1,010.500 $320.000 $1,600.000
BLADING
HR 50.000 $120.000 $110.000 $70.000 $135.000 $103.750 $55.750 $97.000 $175.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 21,370.000 $0.250 $0.230 $0.260 $0.350 $0.220 $0.250 $0.340 $0.400
BROADCAST SEED (TEMP_WARM)
SY 5,343.000 $0.250 $0.190 $0.270 $0.450 $0.230 $0.250 $0.320 $0.400
BROADCAST SEED (TEMP_COOL)
SY 5,343.000 $0.250 $0.190 $0.270 $0.450 $0.230 $0.250 $0.320 $0.400
VEGETATIVE WATERING
TGL 180.140 $20.000 $35.980 $70.000 $60.000 $37.500 $1.000 $48.100 $50.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 2,507.000 $80.000 $67.060 $60.000 $100.000 $98.680 $112.750 $101.000 $95.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 57.000 $250.000 $353.100 $300.000 $420.000 $324.750 $391.250 $526.000 $395.000
LIME TRT (EXIST MATL)(8")
SY 5,932.000 $3.000 $5.500 $5.000 $2.750 $5.890 $7.500 $3.350 $9.500
CEMENT
TON 57.000 $250.000 $225.600 $185.000 $265.000 $206.780 $234.750 $351.000 $283.000
CEMENT TRT (EXIST MATL)(8")
SY 5,932.000 $3.250 $5.500 $4.250 $1.450 $4.910 $5.750 $2.450 $6.000
PRIME COAT (MC-30)
GAL 2,140.000 $5.000 $6.480 $3.250 $3.000 $7.790 $4.500 $3.150 $5.000
AGGR (TY-PE, GR-3)(SAC-B)
CY 126.000 $140.000 $128.270 $145.000 $145.000 $180.080 $221.000 $340.000 $295.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 151.000 $140.000 $129.740 $145.000 $145.000 $165.560 $140.500 $312.000 $265.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 10,971.000 $4.000 $3.670 $3.500 $3.400 $6.250 $3.750 $7.400 $5.000
D-GR HMA TY-B PG64-22
TON 5,120.000 $105.000 $87.750 $110.000 $98.000 $114.350 $103.750 $99.900 $181.000
D-GR HMA TY-D SAC-B PG70-22
TON 4,093.000 $115.000 $96.310 $122.000 $106.000 $110.930 $109.500 $112.000 $181.000
TACK COAT
GAL 3,364.000 $4.000 $3.220 $3.250 $3.000 $5.000 $3.000 $3.250 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 100.000 $48.000 $86.550 $110.000 $100.000 $262.500 $69.750 $151.000 $155.000
CUT & RESTORING PAV
SY 137.000 $15.000 $130.000 $105.000 $23.000 $44.000 $40.000 $109.000 $172.000
CEM STABIL BKFL
CY 117.000 $185.000 $165.000 $200.000 $325.000 $149.000 $260.250 $358.000 $113.000
TEMPORARY SPL SHORING
SF 462.000 $20.000 $12.500 $25.000 $10.250 $30.000 $23.750 $11.500 $10.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 90.000 $205.000 $255.000 $350.000 $165.000 $255.000 $227.500 $270.000 $340.000
RIPRAP (CONC)(5 IN)
CY 9.000 $385.000 $791.180 $625.000 $440.000 $800.000 $642.500 $816.000 $1,000.000
RIPRAP (CONC)(CL B)
CY 3.150 $550.000 $791.180 $800.000 $1,200.000 $1,800.000 $824.250 $1,890.000 $1,700.000
CONC BOX CULV (6 FT X 6 FT)
LF 39.000 $1,000.000 $1,525.640 $800.000 $1,200.000 $1,250.000 $1,551.500 $1,800.000 $2,000.000
RC PIPE (CL III)(18 IN)
LF 220.000 $100.000 $109.130 $85.000 $68.000 $131.000 $70.750 $96.100 $75.000
RC PIPE (CL III)(24 IN)
LF 92.000 $125.000 $111.360 $105.000 $82.000 $177.000 $90.250 $147.000 $93.000
SET (TY I)(S= 6 FT)(HW= 7 FT)(3:1)(C)
EA 1.000 $12,000.000 $21,436.970 $19,500.000 $20,500.000 $24,000.000 $23,167.500 $29,300.000 $25,000.000
SET (TY I)(S= 6 FT)(HW= 7 FT)(4:1)(C)
EA 1.000 $12,500.000 $22,105.140 $24,500.000 $24,500.000 $30,000.000 $26,713.500 $36,600.000 $25,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 8.000 $1,600.000 $1,280.650 $1,500.000 $1,525.000 $2,222.000 $1,653.000 $2,970.000 $2,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $2,000.000 $1,948.820 $1,800.000 $1,700.000 $2,800.000 $1,832.250 $3,230.000 $3,000.000
REMOV STR (SMALL)
EA 4.000 $1,500.000 $827.270 $615.000 $3,320.000 $1,190.000 $2,614.000 $1,000.000 $1,500.000
MOBILIZATION
LS 1.000 $200,000.000 $165,725.660 $185,000.000 $225,000.000 $214,600.000 $125,000.000 $270,000.000 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $4,000.000 $9,348.640 $1,985.000 $1,765.000 $2,637.000 $10,500.000 $25,400.000 $6,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $5,000.000 $3,570.410 $7,500.000 $6,200.000 $10,250.000 $14,822.000 $17,500.000 $1,800.000
TMA (STATIONARY)
DAY 20.000 $300.000 $153.020 $1.000 $275.000 $215.000 $458.000 $181.000 $300.000
TMA (MOBILE OPERATION)
DAY 20.000 $500.000 $306.030 $1.000 $480.000 $275.000 $892.000 $361.000 $1,300.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 50.000 $50.000 $66.960 $80.000 $60.000 $70.000 $54.250 $51.400 $38.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $10.000 $22.330 $10.000 $20.000 $15.000 $24.000 $22.800 $12.000
SANDBAGS FOR EROSION CONTROL
EA 50.000 $12.000 $19.580 $5.000 $15.000 $15.000 $3.500 $3.400 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,310.000 $5.000 $5.940 $4.000 $4.250 $4.000 $4.000 $3.700 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,310.000 $2.000 $1.150 $1.500 $0.750 $1.250 $1.750 $1.700 $1.000
DRIVEWAYS (CONC)
SY 110.000 $110.000 $158.240 $125.000 $110.000 $125.000 $195.500 $125.000 $175.000
DRIVEWAYS (SURF TREAT)
SY 1,191.000 $30.000 $39.330 $12.000 $38.000 $20.650 $12.750 $35.600 $40.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 4.000 $175.000 $175.000 $500.000 $230.000 $175.000 $210.750 $185.000 $255.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 9.000 $4,250.000 $5,125.000 $6,435.000 $5,750.000 $5,125.000 $7,210.000 $5,420.000 $6,000.000
CONDT (PVC) (SCH 40) (2")
LF 3,010.000 $12.000 $16.550 $17.500 $10.500 $16.550 $21.500 $17.500 $18.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 847.000 $16.000 $19.610 $47.000 $35.000 $19.610 $32.500 $20.800 $22.000
ELEC CONDR (NO.10) BARE
LF 2,281.000 $1.500 $1.700 $1.700 $1.650 $1.700 $3.000 $1.800 $2.000
ELEC CONDR (NO.10) INSULATED
LF 6,927.000 $1.000 $1.750 $1.760 $1.750 $1.750 $3.250 $1.850 $2.000
ELEC CONDR (NO.8) BARE
LF 1,814.000 $2.000 $1.800 $1.870 $1.850 $1.800 $3.250 $1.900 $2.000
ELEC CONDR (NO.8) INSULATED
LF 3,978.000 $2.000 $2.200 $1.990 $2.150 $2.200 $4.000 $2.350 $2.500
GROUND BOX TY A (122311)W/APRON
EA 21.000 $1,200.000 $1,180.000 $1,404.000 $1,085.000 $1,180.000 $1,627.000 $1,250.000 $1,500.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $8,600.000 $9,620.000 $7,723.000 $9,500.000 $9,620.000 $11,511.000 $10,200.000 $12,000.000
ALUMINUM SIGNS (TY A)
SF 22.000 $35.000 $35.000 $50.000 $5.000 $35.000 $42.250 $37.000 $28.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $650.000 $900.000 $885.000 $755.000 $900.000 $1,083.250 $952.000 $1,800.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $750.000 $1,000.000 $1,060.000 $905.000 $1,000.000 $1,203.750 $1,060.000 $1,800.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 15.000 $500.000 $525.000 $357.000 $305.000 $525.000 $632.000 $555.000 $1,200.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $550.000 $550.000 $397.000 $340.000 $550.000 $662.000 $582.000 $1,200.000
REMOVE SM RD SN SUP&AM
EA 16.000 $75.000 $125.000 $100.000 $85.000 $125.000 $150.500 $132.000 $200.000
INSTL OM ASSM (OM-2Z)(YFLX)GNDHH(BI)
EA 2.000 $65.000 $95.000 $550.000 $240.000 $95.000 $114.250 $101.000 $400.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 12,800.000 $0.300 $0.460 $0.540 $0.500 $0.350 $0.500 $0.490 $0.520
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 780.000 $1.000 $0.620 $0.730 $0.650 $0.450 $0.500 $0.660 $0.700
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,560.000 $0.500 $0.620 $0.730 $0.650 $0.450 $0.500 $0.660 $0.700
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 17,700.000 $0.300 $0.460 $0.540 $0.500 $0.350 $0.500 $0.490 $0.520
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 11,600.000 $0.300 $0.340 $0.400 $0.350 $0.950 $0.500 $0.360 $0.400
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 11,600.000 $0.300 $0.340 $0.400 $0.350 $0.950 $0.500 $0.360 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 260.000 $2.000 $1.600 $0.590 $1.000 $2.000 $2.500 $2.200 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,688.000 $1.000 $1.600 $0.590 $1.000 $2.000 $2.000 $2.200 $2.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 390.000 $2.500 $2.000 $2.340 $2.000 $2.250 $2.500 $2.100 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,280.000 $2.500 $1.100 $1.290 $1.150 $2.250 $1.250 $1.150 $1.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 6,400.000 $0.850 $0.720 $0.840 $0.750 $1.650 $0.750 $0.760 $0.800
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 8,850.000 $0.850 $0.720 $0.840 $0.750 $1.650 $0.750 $0.760 $0.800
PREFAB PM TY C (W)(24")(SLD)
LF 34.000 $17.000 $24.000 $28.090 $24.000 $12.000 $29.000 $25.400 $27.000
PREFAB PM TY C (W)(ARROW)
EA 6.000 $250.000 $200.000 $234.040 $200.000 $200.000 $240.750 $212.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 6.000 $265.000 $300.000 $351.070 $300.000 $200.000 $361.000 $317.000 $300.000
REFL PAV MRKR TY I-C
EA 98.000 $8.000 $7.500 $8.780 $8.000 $6.000 $9.000 $7.900 $10.000
REFL PAV MRKR TY II-A-A
EA 387.000 $7.000 $7.500 $8.780 $8.000 $6.000 $9.000 $7.900 $8.000
ELIM EXT PM & MRKS (6")
LF 1,520.000 $0.500 $1.750 $2.050 $2.000 $1.000 $2.000 $1.850 $2.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 2.000 $4,500.000 $5,214.000 $6,670.260 $6,250.000 $5,214.000 $8,001.000 $5,520.000 $6,000.000
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 2.000 $850.000 $551.000 $971.290 $275.000 $551.000 $589.000 $583.000 $600.000
NO. OF DAYS MILESTONE 1
$/D 6,717.000 $6,717.000 $80.000 $70.000 $80.000 $65.000 $74.000 $80.000 $80.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $8,000.000 $7,650.870 $13,500.000 $3,500.000 $10,000.000 $15,317.000 $15,200.000 $2,200.000
Totals: $47,397,502.300 $2,749,828.589 $2,841,531.280 $2,914,802.400 $3,071,997.905 $3,123,028.778 $3,405,163.004 $3,724,359.400
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $1.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $2,001.00