Bid Cobra

LA SALLE FM 624 (2373-01-022)

Items: 66

County: LA SALLE
Length: N/A
Highway: FM 624
District: LAREDO
Control Number: 2373-01-022
DBE Goal: N/A
Project: STP 2020(936)HES
Guaranty: N/A
Time: 290 WORKING DAYS
Engineer's Estimate: $5,754,069.11
Date: 06/04/2021 (5 years ago)
Contract Number: N/A
Type: WIDEN SHLDR, SEALCOAT, PROF MRK ON EDGE&CTR LINES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (10)
E
Engineer's Estimate
$5,754,069.11
$5,569,435.78
Over/Under Est: -3.21% -$184,633.33
$5,821,977.05
Over/Under Est: 1.18% $67,907.94
Amt Left: 4.53% $252,541.27
Over/Under Est: 2.69% $154,811.80
Amt Left: 6.09% $339,445.13
Delta: -1.49% -$86,903.86
Over/Under Est: 6.23% $358,325.24
Amt Left: 9.75% $542,958.57
Delta: -3.44% -$203,513.44
$6,665,619.60
Over/Under Est: 15.84% $911,550.49
Amt Left: 19.68% $1,096,183.82
Delta: -9.05% -$553,225.25
Over/Under Est: 15.88% $913,909.19
Amt Left: 19.72% $1,098,542.52
Delta: -0.04% -$2,358.70
Over/Under Est: 16.69% $960,174.96
Amt Left: 20.56% $1,144,808.29
Delta: -0.69% -$46,265.77
Over/Under Est: 19.81% $1,139,637.30
Amt Left: 23.78% $1,324,270.63
Delta: -2.67% -$179,462.34
$6,894,425.26
Over/Under Est: 19.82% $1,140,356.15
Amt Left: 23.79% $1,324,989.48
Delta: -0.01% -$718.85
Over/Under Est: 25.8% $1,484,498.59
Amt Left: 29.97% $1,669,131.92
Delta: -4.99% -$344,142.44

Bid Items & Bid Tabulations

66 Total 0 of 66
LA SALLE  |  FM 624  |  LAREDO  |  2373-01-022  |  06/04/2021  |  $5,754,069.11  |  STP 2020(936)HES  |  WIDEN SHLDR, SEALCOAT, PROF MRK ON E...  |  290 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BRANNAN PAVING CO., LTD.
CK NEWBERRY, LLC
J. CARROLL WEAVER, INC.
HUNTER INDUSTRIES, LTD.
VECTOR UTILITIES LLC
J E CONSTRUCTION SERVICES, LLC
DEAN WORD COMPANY, LTD.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
FARIS INDUSTRIES, INC.
ANGEL BROTHERS HOLDINGS CORP.
EXCAVATION (ROADWAY)
CY 20,926.000 $9.160 $8.590 $6.000 $8.430 $11.130 $6.640 $17.800 $16.191 $13.140 $20.160 $8.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 39,663.000 $14.500 $9.210 $10.000 $10.830 $9.990 $12.630 $8.300 $11.841 $9.000 $16.180 $19.750
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 52.100 $600.000 $600.000 $675.000 $271.040 $707.250 $908.340 $1,300.000 $618.000 $667.000 $775.000 $275.000
DRILL SEEDING (TEMP) (WARM)
AC 52.100 $500.000 $500.000 $250.000 $704.480 $589.380 $720.620 $1,200.000 $515.000 $543.310 $600.000 $725.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 26,484.000 $55.000 $70.220 $75.500 $63.500 $65.000 $70.840 $71.000 $79.754 $74.170 $70.440 $91.350
PRIME COAT (MC-30)
GAL 14,302.000 $4.750 $4.140 $3.750 $4.280 $3.830 $5.450 $4.300 $4.534 $5.120 $4.770 $4.650
ASPH (AC-15P)
GAL 191,154.000 $2.500 $3.440 $2.750 $3.870 $3.740 $4.840 $3.200 $3.339 $3.560 $3.390 $3.000
AGGR(TY-PD GR-3 SAC-B)
CY 2,825.000 $61.440 $101.110 $110.000 $97.370 $81.320 $130.800 $101.000 $129.364 $138.380 $100.060 $112.000
AGGR(TY-PD GR-4 SAC-B)
CY 2,324.000 $95.000 $102.310 $85.000 $96.710 $81.300 $139.280 $109.000 $109.101 $149.750 $104.540 $113.000
FLOWABLE BACKFILL
CY 3.000 $200.000 $216.740 $500.000 $350.000 $260.000 $426.230 $223.000 $223.242 $336.030 $192.000 $390.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 19.600 $590.000 $635.620 $1,000.000 $712.320 $1,050.000 $1,924.410 $1,600.000 $654.689 $2,295.460 $880.000 $3,355.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 45.600 $750.000 $765.820 $600.000 $857.920 $1,100.000 $1,685.950 $740.000 $788.795 $1,338.880 $935.000 $1,540.000
RC PIPE (CL III)(24 IN)
LF 116.700 $75.000 $54.760 $100.000 $61.600 $180.000 $165.250 $270.000 $56.403 $343.490 $70.000 $295.000
RC PIPE (CL III)(36 IN)
LF 103.200 $120.000 $95.710 $150.000 $107.520 $205.000 $225.130 $335.000 $98.581 $344.860 $115.000 $270.000
RC PIPE (CL III)(48 IN)
LF 102.900 $175.000 $145.750 $200.000 $163.520 $240.000 $345.950 $350.000 $150.123 $443.840 $202.000 $675.000
RC PIPE (ARCH)(CL IV)(DES 4)
LF 30.000 $150.000 $175.750 $205.000 $197.120 $300.000 $280.600 $200.000 $181.023 $362.130 $260.000 $290.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $6,500.000 $7,787.580 $10,000.000 $8,722.560 $8,500.000 $10,267.310 $12,000.000 $8,021.207 $11,030.120 $6,780.000 $12,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 2.000 $25,000.000 $10,558.380 $12,000.000 $11,826.080 $12,000.000 $12,249.420 $15,000.000 $10,875.131 $11,491.750 $8,900.000 $22,600.000
WINGWALL (PW - 1) (HW=10 FT)
EA 2.000 $40,000.000 $40,271.430 $32,000.000 $45,104.640 $31,000.000 $45,604.210 $51,000.000 $41,479.573 $28,798.740 $42,000.000 $35,000.000
SET (TY I)(S= 6 FT)(HW= 6 FT)(4:1) (C)
EA 3.000 $11,000.000 $6,220.330 $9,200.000 $6,966.400 $9,500.000 $11,909.780 $12,000.000 $6,406.940 $10,474.560 $8,800.000 $10,140.000
SET (TY I)(S= 6 FT)(HW= 7 FT)(4:1) (C)
EA 15.000 $10,850.000 $7,895.890 $8,700.000 $8,843.520 $12,000.000 $12,235.080 $12,000.000 $8,132.767 $10,678.860 $9,050.000 $13,200.000
SET (TY I)(S= 6 FT)(HW= 9 FT)(4:1) (C)
EA 12.000 $13,000.000 $9,752.790 $8,150.000 $10,923.360 $15,000.000 $8,695.920 $15,000.000 $10,045.374 $10,935.110 $9,980.000 $9,560.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 52.000 $1,500.000 $978.740 $1,525.000 $1,096.480 $1,800.000 $2,066.130 $2,000.000 $1,008.102 $1,173.160 $1,700.000 $2,750.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 20.000 $2,500.000 $1,593.960 $2,300.000 $1,785.280 $3,500.000 $3,789.480 $5,000.000 $1,641.779 $4,211.790 $2,450.000 $3,900.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 22.000 $5,400.000 $3,694.590 $4,000.000 $4,138.400 $6,000.000 $6,813.570 $9,400.000 $3,805.428 $8,297.650 $4,300.000 $6,600.000
SET (TY II) (DES 4) (RCP) (6: 1) (P)
EA 2.000 $7,225.000 $3,399.510 $5,800.000 $3,740.800 $7,000.000 $5,916.590 $5,700.000 $3,501.495 $10,138.690 $9,800.000 $7,700.000
CLEAN EXIST CULVERTS
EA 60.000 $2,000.000 $2,024.090 $675.000 $2,268.000 $1,000.000 $1,717.090 $750.000 $2,084.813 $1,763.730 $1,850.000 $1,000.000
REMOV STR (SET)
EA 48.000 $575.000 $230.000 $500.000 $782.880 $1,000.000 $595.770 $600.000 $236.900 $413.370 $1,050.000 $300.000
REMOV STR (WINGWALL)
EA 12.000 $1,400.000 $980.000 $1,200.000 $1,097.600 $1,150.000 $1,110.790 $2,500.000 $1,009.400 $2,530.080 $1,110.000 $1,700.000
REMOV STR (HEADWALL)
EA 52.000 $1,200.000 $910.000 $950.000 $1,019.200 $1,000.000 $1,025.350 $990.000 $937.300 $1,347.930 $1,050.000 $680.000
REMOV STR (PIPE)
EA 42.500 $900.000 $250.000 $15.000 $280.000 $25.000 $143.950 $32.000 $257.500 $560.240 $18.000 $5.000
MOBILIZATION
LS 1.000 $494,466.190 $241,050.000 $400,000.000 $447,835.840 $480,000.000 $133,312.390 $594,500.000 $671,411.720 $516,586.620 $757,108.580 $533,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $3,500.000 $7,138.000 $3,000.000 $4,480.000 $3,500.000 $2,119.470 $1,400.000 $3,983.529 $2,224.240 $12,643.340 $2,600.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 845.000 $60.000 $60.000 $42.000 $73.920 $70.730 $62.980 $55.000 $61.800 $63.340 $52.500 $76.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $22.000 $18.000 $20.000 $19.600 $21.220 $62.980 $33.000 $18.540 $19.510 $52.500 $20.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $7.000 $5.000 $5.000 $8.400 $5.890 $39.060 $13.000 $5.150 $5.860 $32.500 $8.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 301.000 $70.000 $50.000 $70.000 $50.400 $74.100 $60.560 $57.000 $85.882 $97.720 $55.000 $95.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 12,011.000 $2.400 $2.250 $2.350 $2.460 $2.650 $3.150 $2.800 $2.318 $2.440 $2.650 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 12,011.000 $1.000 $0.850 $0.550 $0.560 $1.000 $1.210 $0.500 $0.876 $0.900 $1.100 $0.500
ONE-WAY TRAF CONT (PILOT CAR)
HR 300.000 $115.000 $1.000 $82.000 $116.200 $96.900 $53.160 $82.000 $94.058 $99.860 $100.800 $140.000
DRIVEWAYS (CONC)
SY 320.000 $78.000 $75.520 $130.000 $86.240 $100.000 $174.180 $93.000 $77.786 $112.650 $88.720 $148.000
DRIVEWAYS (SURF TREAT)
SY 1,435.000 $30.000 $20.490 $17.000 $13.970 $35.040 $57.270 $47.000 $27.864 $36.720 $32.750 $26.000
DRIVEWAYS (BASE)
SY 1,624.000 $21.000 $15.840 $15.000 $32.270 $13.140 $11.080 $29.000 $22.896 $27.680 $32.750 $25.000
REMOVE METAL BEAM GUARD FENCE
LF 2,100.000 $2.500 $6.200 $3.000 $4.480 $1.190 $6.160 $2.000 $1.030 $3.240 $6.250 $1.300
GUARDRAIL END TREATMENT (REMOVE)
EA 24.000 $275.000 $695.000 $275.000 $336.000 $356.700 $540.580 $360.000 $309.000 $217.950 $700.000 $400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $550.000 $575.000 $650.000 $613.760 $561.700 $696.400 $650.000 $564.440 $584.940 $548.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 20.000 $750.000 $750.000 $800.000 $787.360 $719.550 $908.340 $840.000 $723.060 $746.640 $702.000 $745.000
REMOVE SM RD SN SUP&AM
EA 3.000 $90.000 $60.000 $25.000 $100.800 $97.380 $121.110 $112.000 $97.850 $109.290 $95.000 $100.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 84.000 $12.110 $15.000 $10.000 $16.800 $23.910 $30.280 $56.000 $10.800 $18.020 $88.000 $25.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 560.000 $4.000 $2.900 $2.950 $3.080 $3.210 $3.330 $3.000 $3.224 $3.460 $3.130 $3.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 146,670.000 $0.700 $0.480 $0.450 $0.450 $0.480 $0.480 $0.450 $0.484 $0.510 $0.470 $0.400
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 336.000 $8.000 $6.400 $13.000 $13.440 $6.150 $14.530 $13.000 $6.180 $6.870 $6.000 $6.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 67,200.000 $0.650 $0.520 $0.450 $0.450 $0.500 $0.480 $0.500 $0.505 $0.520 $0.490 $0.450
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,395.000 $0.750 $1.500 $2.000 $0.840 $1.410 $1.210 $1.000 $1.409 $0.820 $1.170 $0.950
PAVEMENT SEALER 4"
LF 229,223.000 $0.140 $0.100 $0.300 $0.280 $0.120 $0.300 $0.300 $0.124 $0.130 $0.120 $0.100
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 143,600.000 $0.530 $0.440 $0.650 $0.650 $0.590 $0.700 $0.650 $0.597 $0.620 $0.580 $0.500
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 70,760.000 $0.550 $0.520 $0.700 $0.710 $0.590 $0.760 $0.700 $0.597 $0.620 $0.580 $0.600
REFL PAV MRKR TY II-A-A
EA 1,616.000 $2.850 $3.200 $4.500 $4.480 $3.380 $4.840 $4.500 $3.399 $3.580 $3.300 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 85,623.000 $0.350 $0.440 $1.250 $0.560 $0.410 $0.610 $0.500 $0.412 $0.420 $0.400 $0.400
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 2,240.000 $8.000 $1.000 $2.000 $1.120 $2.050 $1.210 $1.000 $12.700 $2.140 $2.000 $2.100
TEMP TRAF SIGNALS
EA 2.000 $55,000.000 $19,000.000 $35,000.000 $24,640.000 $40,000.000 $42,389.370 $12,000.000 $36,008.280 $45,868.320 $8,500.000 $15,900.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $15,000.000 $10,000.000 $7,280.000 $7,000.000 $19,983.560 $20,000.000 $8,100.000 $14,188.320 $1,000.000 $10,700.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 2,240.000 $14.000 $9.000 $7.500 $7.840 $12.640 $8.480 $7.000 $12.700 $12.990 $12.330 $7.400
PREFORMED CENTERLINE RUMBLE STRIP
LF 1,575.000 $5.000 $6.000 $5.000 $5.040 $6.490 $5.450 $5.000 $6.520 $6.710 $6.330 $4.700
TMA (STATIONARY)
DAY 335.000 $150.000 $167.000 $275.000 $72.800 $225.000 $181.670 $100.000 $189.000 $185.890 $30.000 $150.000
TMA (MOBILE OPERATION)
HR 300.000 $60.000 $50.000 $15.000 $72.800 $110.000 $44.320 $30.000 $51.840 $185.890 $30.000 $42.000
Totals: $5,754,069.110 $5,569,435.793 $5,821,977.050 $5,908,880.938 $6,112,394.363 $6,665,619.633 $6,667,978.300 $6,714,244.208 $6,893,706.436 $6,894,425.260 $7,238,567.700