LA SALLE SH 97 (0483-01-052)

Items: 115

County: LA SALLE
Length: N/A
Highway: SH 97
District: LAREDO
Control Number: 0483-01-052
DBE Goal: N/A
Project: F 2B23(147)
Guaranty: N/A
Time: 150 WORKING DAYS
Engineer's Estimate: $6,853,143.60
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
DENNICE GARZA
ANGEL MARTINEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$6,853,143.60
$7,207,235.43
Over/Under Est: 5.17% $354,091.83
Over/Under Est: 6.83% $467,770.26
Amt Left: 1.58% $113,678.43
Over/Under Est: 15.47% $1,060,423.92
Amt Left: 9.8% $706,332.09
Delta: -8.10% -$592,653.66
Subcontractor Percentage Amount
STX CIVIL 13.34% $955,124.93
AVILA AND SON'S L.L.C. 4.64% $332,217.37
DEPENDABLE FENCE 3.02% $216,227.68
D&G ENERGY CORPORATION 1.30% $93,078.14
HIGHWAY BARRICADES AND SERVICES, LLC 1.26% $90,214.20
A K FUQUAY CONSTRUCTION 0.44% $31,503.37
TORO BRAVO CONSTRUCTION, LLC 0.18% $12,887.74
PRIMATE CONSTRUCTION, LP 0.15% $10,739.79
SK CONCRETE SERVICES LLC 0.11% $7,875.84
Total: 24.44% $1,749,869.06

Bid Items & Bid Tabulations

115 Total 0 of 115
LA SALLE  |  SH 97  |  LAREDO  |  0483-01-052  |  08/03/2023  |  $6,853,143.60  |  F 2B23(147)  |  REHAB EXIST ROADWAY  |  150 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANDERSON COLUMBIA CO., INC.
J. CARROLL WEAVER, INC.
PREPARING ROW
STA 41.320 $7,700.000 $11,970.000 $2,500.000 $1,536.000
REMOVING CONC (SIDEWALKS)
SY 195.000 $36.000 $31.500 $44.000 $10.240
REMOVING CONC (CURB)
LF 25.000 $22.000 $31.500 $17.000 $128.000
REMOVING CONC (CURB AND GUTTER)
LF 4,088.000 $25.000 $31.500 $17.000 $7.680
REMOVE CONC (GUTTER)
LF 681.000 $15.000 $31.500 $20.000 $7.680
REMOVING CONC (MISC)
SY 336.000 $60.000 $31.500 $40.000 $19.200
REMOVING STAB BASE & ASPH PAV (5" - 6")
SY 1,666.000 $18.000 $17.500 $14.000 $22.010
EXCAVATION (ROADWAY)
CY 8,858.000 $34.000 $35.200 $40.000 $23.510
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 408.000 $70.000 $29.700 $40.000 $47.530
BLOCK SODDING
SY 1,513.000 $8.200 $10.000 $10.000 $15.360
VEGETATIVE WATERING
MG 24.000 $80.000 $24.500 $70.000 $128.000
PROOF ROLLING
HR 100.000 $120.000 $132.000 $90.000 $96.000
PRIME COAT (MC-30)
GAL 3,503.000 $13.000 $7.540 $8.000 $6.770
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 3,300.000 $150.000 $74.050 $70.000 $110.830
PLANE ASPH CONC PAV (8")
SY 431.000 $7.000 $16.980 $30.000 $57.600
CONC PVMT (CONT REINF)(FAST TRK)(12")
SY 2,210.000 $175.000 $215.060 $220.000 $198.400
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 10.300 $350.000 $315.000 $320.000 $339.200
CL C CONC (RAIL FOUNDATION)
CY 94.000 $1,100.000 $1,039.330 $900.000 $1,753.600
CL C CONC (COLLAR)
EA 1.000 $2,250.000 $1,988.170 $2,500.000 $3,328.000
CL C CONC (RAC-R)
CY 27.390 $2,700.000 $3,562.060 $8,000.000 $3,328.000
RIPRAP (CONC)(5 IN)
CY 752.000 $670.000 $670.800 $625.000 $768.000
RIPRAP (MOW STRIP)(4 IN)
CY 49.000 $650.000 $833.530 $850.000 $588.800
CLEANING AND SEALING EXISTING JOINTS
LF 172.000 $35.000 $37.410 $75.000 $44.800
STR STEEL (MISC NON - BRIDGE)
LB 288.000 $24.000 $33.610 $25.000 $16.640
RAIL (TY T223)
LF 875.000 $165.000 $206.610 $250.000 $217.600
RAIL (TY PR22)
LF 1,103.000 $165.000 $185.000 $100.000 $256.000
RETROFIT RAIL (TY T223)
LF 202.000 $330.000 $223.690 $300.000 $371.200
RETROFIT RAIL (TY PR1)
LF 8.000 $130.000 $400.000 $300.000 $499.200
RC PIPE (CL III)(18 IN)
LF 410.000 $120.000 $135.970 $280.000 $108.800
RC PIPE (CL III)(24 IN)
LF 15.000 $130.000 $252.930 $350.000 $135.680
INLET (COMPL)(PCO)(3FT)(NONE)
EA 2.000 $6,600.000 $8,057.770 $18,000.000 $7,808.000
INLET (COMPL)(PCO)(3FT)(LEFT)
EA 1.000 $7,200.000 $7,369.820 $20,000.000 $2,560.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 4.000 $1,200.000 $2,372.280 $6,200.000 $2,560.000
REMOV STR (INLET)
EA 1.000 $1,200.000 $1,905.500 $4,000.000 $1,792.000
REMOV STR (PIPE)
EA 1.000 $740.000 $1,905.500 $16,000.000 $512.000
MOBILIZATION
LS 1.000 $375,000.000 $627,439.520 $700,000.000 $434,205.470
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $12,000.000 $48,073.860 $5,500.000 $9,600.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $34.500 $28.000 $40.000 $92.160
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $12.000 $8.000 $15.000 $62.720
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,210.000 $4.500 $4.500 $6.000 $6.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,210.000 $1.600 $2.000 $2.000 $3.840
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 83.000 $8.000 $9.000 $15.000 $15.360
BIODEG EROSN CONT LOGS (REMOVE)
LF 83.000 $2.600 $2.000 $2.000 $7.680
CONSTRUCTING DETOURS
SY 374.000 $100.000 $104.290 $200.000 $450.200
COLORED TEXTURED CONC (5")
SY 894.000 $117.000 $144.640 $120.000 $166.400
CONC CURB (TY II)
LF 786.000 $42.000 $27.100 $24.000 $32.000
CONC CURB & GUTTER (TY II)
LF 4,053.000 $56.000 $34.820 $40.000 $39.680
INTERSECTIONS (CONC)
SY 380.000 $135.000 $204.930 $260.000 $286.930
INTERSECTIONS (ACP)
SY 878.000 $65.000 $81.500 $140.000 $285.700
DRIVEWAYS (CONC)
SY 552.000 $123.000 $135.300 $250.000 $196.410
DRIVEWAYS (ACP)
SY 947.000 $72.000 $81.500 $200.000 $264.880
CONC SIDEWALKS (5")
SY 2,125.000 $150.000 $89.840 $77.000 $92.160
CURB RAMPS (TY 1)
EA 4.000 $2,600.000 $2,038.060 $2,800.000 $2,432.000
CURB RAMPS (TY 2)
EA 1.000 $3,250.000 $2,791.920 $3,560.000 $3,584.000
CURB RAMPS (TY 5)
EA 1.000 $3,600.000 $2,903.500 $3,740.000 $4,352.000
CURB RAMPS (TY 7)
EA 3.000 $2,900.000 $2,314.840 $3,740.000 $2,560.000
CURB RAMPS (TY 10)
EA 10.000 $3,300.000 $2,694.780 $3,740.000 $3,200.000
MTL W-BEAM GD FEN (TIM POST)
LF 668.000 $32.000 $26.250 $33.000 $32.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,400.000 $2,696.400 $3,100.000 $2,816.000
REMOVE METAL BEAM GUARD FENCE
LF 787.000 $5.000 $2.630 $5.000 $3.200
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,300.000 $3,454.500 $3,900.000 $4,224.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $340.000 $236.250 $560.000 $288.000
CONDT (PVC) (SCH 40) (1")
LF 34.000 $16.000 $21.000 $15.000 $16.640
CONDT (PVC) (SCH 40) (2")
LF 32.000 $20.000 $24.150 $18.000 $19.200
CONDT (PVC) (SCH 80) (2") (BORE)
LF 399.000 $32.000 $47.250 $42.000 $44.800
ELEC CONDR (NO.6) BARE
LF 465.000 $2.500 $1.840 $2.100 $2.560
ELEC CONDR (NO.6) INSULATED
LF 64.000 $3.000 $2.050 $2.500 $2.560
GROUND BOX TY C (162911)W/APRON
EA 6.000 $1,400.000 $1,470.000 $1,750.000 $1,920.000
ELC SRV TY T 120/240 000(NS)GS(L)SP(O)
EA 1.000 $3,500.000 $6,300.000 $6,900.000 $7,168.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 32.000 $800.000 $615.000 $760.000 $787.200
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $950.000 $625.000 $780.000 $1,011.200
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,100.000 $810.000 $1,010.000 $1,036.800
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,300.000 $850.000 $1,060.000 $1,036.800
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,300.000 $950.000 $1,180.000 $1,216.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,300.000 $950.000 $1,250.000 $1,248.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 3.000 $1,450.000 $975.000 $1,400.000 $1,248.000
REMOVE SM RD SN SUP&AM
EA 29.000 $150.000 $75.000 $100.000 $96.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 17.000 $45.000 $48.000 $60.000 $61.440
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 11.000 $30.000 $28.000 $35.000 $35.840
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 9,550.000 $1.400 $1.480 $0.600 $0.640
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 850.000 $2.000 $1.880 $1.000 $0.960
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 745.000 $1.300 $2.470 $1.200 $1.280
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 9,550.000 $2.000 $1.450 $0.600 $0.640
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 90.000 $1.800 $1.630 $2.500 $5.120
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,179.000 $1.700 $1.630 $2.500 $5.120
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 939.000 $1.600 $1.230 $2.500 $1.600
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 4,346.000 $0.900 $0.720 $1.500 $1.410
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 935.000 $0.900 $0.710 $1.700 $1.600
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 8,948.000 $1.000 $0.750 $1.500 $1.410
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 137.000 $20.000 $16.620 $20.000 $17.920
PREFAB PAV MRK TY C (W) (ARROW)
EA 10.000 $270.000 $240.210 $230.000 $224.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $350.000 $286.780 $400.000 $352.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $700.000 $633.940 $800.000 $768.000
REFL PAV MRKR TY II-A-A
EA 136.000 $9.500 $4.880 $6.500 $6.400
ELIM EXT PAV MRK & MRKS (6")
LF 260.000 $1.000 $0.550 $1.400 $2.560
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $29,000.000 $30,030.000 $52,000.000 $51,200.000
VEH SIG SEC (12")LED(GRN)
EA 2.000 $380.000 $257.250 $400.000 $384.000
VEH SIG SEC (12")LED(YEL)
EA 2.000 $380.000 $257.250 $400.000 $384.000
VEH SIG SEC (12")LED(RED)
EA 2.000 $380.000 $257.250 $400.000 $384.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 2.000 $170.000 $131.250 $320.000 $320.000
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 100.000 $3.400 $2.520 $4.000 $3.840
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 419.000 $3.400 $2.940 $5.000 $5.120
TRF SIG CBL (TY A)(12 AWG)(9 CONDR)
LF 80.000 $3.400 $3.410 $6.000 $6.400
TRF SIG CBL (TY C)(18 AWG)(2 CONDR)
LF 120.000 $3.000 $1.730 $2.000 $2.560
INS TRF SIG PL AM (S)1 ARM(28')
EA 1.000 $10,000.000 $14,280.000 $14,000.000 $12,800.000
VEH LP DETECT (SAWCUT)
LF 54.000 $15.000 $16.800 $20.340 $21.760
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 530.000 $215.000 $143.000 $220.000 $249.600
SP MIXES SP-B SAC-B PG70-22
TON 6,747.000 $140.000 $143.000 $160.000 $204.800
SP MIXES SP-C SAC-B PG70-22
TON 2,909.000 $150.000 $150.700 $190.000 $217.600
SP MIXES SP-C SAC-A PG76-22
TON 1,825.000 $230.000 $156.200 $190.000 $224.000
BONDING COURSE
GAL 6,489.000 $10.000 $4.880 $6.500 $7.680
PORTABLE CHANGEABLE MESSAGE SIGN
EA 8.000 $12,000.000 $9,201.250 $14,000.000 $17,920.000
BBU SYSTEM (EXTERNAL BATT CABINET)
EA 1.000 $8,500.000 $8,925.000 $14,000.000 $14,080.000
TMA (STATIONARY)
DAY 15.000 $250.000 $324.750 $500.000 $1,536.000
TMA (MOBILE OPERATION)
DAY 10.000 $350.000 $324.750 $800.000 $2,304.000
Totals: $6,853,143.600 $7,207,235.433 $7,320,913.860 $7,913,567.520