Show Job Controls
Bid Cobra

LA SALLE IH 35 (0018-01-094)

Items: 105

County: LA SALLE
Length: N/A
Highway: IH 35
District: LAREDO
Control Number: 0018-01-094
DBE Goal: N/A
Project: C 18-1-94
Guaranty: N/A
Time: 124 WORKING DAYS
Engineer's Estimate: $4,596,123.76
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (7)
E
Engineer's Estimate
$4,596,123.76
$4,380,301.84
Over/Under Est: -4.7% -$215,821.92
$4,388,970.79
Over/Under Est: -4.51% -$207,152.97
Amt Left: 0.2% $8,668.95
Over/Under Est: 2.37% $109,058.10
Amt Left: 7.42% $324,880.02
Delta: -7.20% -$316,211.07
$5,344,404.40
Over/Under Est: 16.28% $748,280.64
Amt Left: 22.01% $964,102.56
Delta: -13.59% -$639,222.54
Over/Under Est: 19.66% $903,492.63
Amt Left: 25.55% $1,119,314.55
Delta: -2.90% -$155,211.99
Over/Under Est: 23.04% $1,059,140.28
Amt Left: 29.11% $1,274,962.20
Delta: -2.83% -$155,647.65
$6,039,418.37
Over/Under Est: 31.4% $1,443,294.61
Amt Left: 37.88% $1,659,116.53
Delta: -6.79% -$384,154.33

Bid Items & Bid Tabulations

105 Total 0 of 105
LA SALLE  |  IH 35  |  LAREDO  |  0018-01-094  |  01/07/2022  |  $4,596,123.76  |  C 18-1-94  |  REHAB EXIST ROADWAY  |  124 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. CARROLL WEAVER, INC.
FARIS INDUSTRIES, INC.
ANDERSON COLUMBIA CO., INC.
CK NEWBERRY, LLC
HUNTER INDUSTRIES, LTD.
TEXAS MATERIALS GROUP, INC.
TRIUN, LLC
PREPARING ROW
STA 155.000 $1,579.840 $275.000 $471.000 $300.000 $200.000 $1,108.890 $1,000.000 $120.000
REMOVING CONC (RIPRAP)
SY 140.000 $10.000 $8.740 $17.340 $17.000 $30.000 $16.650 $29.500 $18.000
REMOVING CONC (DRIVEWAYS)
SY 200.000 $13.680 $12.240 $18.810 $22.000 $15.000 $16.650 $29.500 $18.000
REMOVING CONC (CURB)
LF 262.000 $7.000 $4.670 $10.450 $10.000 $6.000 $9.990 $11.000 $10.000
REMOVING CONCRETE(MOW STRIP)
LF 60.000 $4.500 $40.800 $34.250 $10.000 $12.000 $29.970 $13.000 $50.560
REMOVING STAB BASE AND ASPH PAV (6")
SY 35,239.000 $3.500 $5.160 $4.010 $8.000 $2.000 $5.610 $6.000 $4.710
EXCAVATION (ROADWAY AND CHANNEL)
CY 28,813.000 $11.210 $8.030 $6.900 $9.000 $10.000 $16.650 $14.000 $11.850
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 4,383.000 $15.600 $5.750 $12.540 $7.000 $12.000 $11.400 $19.000 $11.850
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 12.100 $686.430 $700.000 $1,675.000 $1,200.000 $600.000 $1,370.250 $600.000 $650.000
DRILL SEEDING (TEMP) (WARM)
AC 12.100 $510.000 $555.000 $915.000 $825.000 $500.000 $999.180 $500.000 $600.000
PROOF ROLLING
HR 38.000 $100.000 $72.150 $62.700 $80.000 $100.000 $102.600 $85.000 $88.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 19,767.000 $63.500 $37.000 $43.340 $52.000 $75.000 $66.850 $80.000 $102.000
CEMENT
TON 1,078.000 $168.000 $152.600 $358.590 $200.000 $250.000 $178.500 $195.000 $185.410
CEMENT TREAT (NEW BASE)(12")
SY 59,038.000 $3.030 $3.750 $1.960 $4.000 $3.500 $3.420 $4.250 $1.550
ASPH (RC-250)
GAL 23,615.000 $4.600 $3.770 $4.450 $4.000 $4.000 $4.590 $4.750 $5.000
AGGR(TY-PB GR-5 SAC-B)
CY 393.000 $110.000 $196.540 $91.290 $200.000 $125.000 $116.370 $194.000 $195.000
TRENCH EXCAVATION PROTECTION
LF 391.000 $3.500 $5.550 $12.000 $7.000 $6.000 $7.690 $12.000 $15.000
TEMPORARY SPL SHORING
SF 2,573.000 $12.500 $11.100 $25.000 $19.000 $17.000 $20.830 $25.000 $62.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 90.000 $220.000 $310.800 $195.000 $137.000 $200.000 $267.290 $280.000 $246.750
CL C CONC (RAIL FOUNDATION)
CY 158.000 $322.000 $999.000 $425.000 $500.000 $500.000 $558.530 $425.000 $450.000
CL C CONC (COLLAR)
EA 4.000 $1,075.000 $1,332.000 $1,200.000 $1,200.000 $1,500.000 $1,486.050 $1,200.000 $1,100.000
RIPRAP (CONC)(4 IN)
CY 120.000 $428.520 $478.410 $435.000 $440.000 $550.000 $627.810 $435.000 $489.500
RIPRAP (CONC)(6 IN)
CY 19.000 $500.000 $507.270 $450.000 $460.000 $600.000 $655.810 $450.000 $517.000
RIPRAP (CONC)(CL B)
CY 4.000 $435.000 $489.510 $800.000 $470.000 $550.000 $598.610 $800.000 $528.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 172.000 $140.000 $217.560 $165.000 $170.000 $125.000 $203.880 $165.000 $164.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 107.000 $140.000 $222.000 $165.000 $175.000 $225.000 $224.960 $165.000 $174.000
RIPRAP (MOW STRIP)(4 IN)
CY 53.000 $500.000 $760.350 $450.000 $450.000 $550.000 $628.080 $450.000 $503.800
RIPRAP (STONE COMMON)(GROUT)(18 IN)
CY 202.000 $260.000 $305.250 $165.000 $280.000 $300.000 $368.980 $165.000 $175.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 1,130.000 $38.000 $112.110 $77.280 $75.000 $70.000 $79.670 $78.000 $72.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 31.000 $730.000 $1,141.180 $693.000 $1,300.000 $1,200.000 $1,412.380 $700.000 $1,145.000
RC PIPE (CL III)(24 IN)
LF 69.000 $65.000 $146.660 $84.630 $83.000 $80.000 $91.460 $85.000 $207.230
RC PIPE (CL III)(30 IN)
LF 17.000 $92.440 $287.020 $212.450 $118.000 $115.000 $129.270 $215.000 $597.470
RC PIPE (CL IV)(24 IN)
LF 165.000 $95.000 $127.480 $106.750 $96.000 $95.000 $105.570 $107.000 $202.020
RC PIPE (ARCH)(CL III)(DES 2)
LF 114.000 $160.740 $158.640 $204.330 $190.000 $200.000 $209.070 $205.000 $232.700
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $3,650.000 $6,700.000 $6,174.000 $6,000.000 $6,000.000 $6,676.040 $6,200.000 $17,840.000
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $21,650.000 $29,548.530 $35,910.000 $37,300.000 $35,000.000 $41,189.690 $35,000.000 $20,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $23,100.000 $38,808.150 $37,310.000 $38,650.000 $40,000.000 $42,698.210 $37,000.000 $25,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,380.000 $3,885.000 $1,505.000 $1,570.000 $1,500.000 $1,733.520 $1,505.000 $1,575.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 6.000 $2,115.000 $3,885.000 $1,505.000 $1,830.000 $1,800.000 $2,027.930 $1,505.000 $789.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,400.000 $3,885.000 $1,505.000 $1,750.000 $1,700.000 $1,949.240 $1,505.000 $789.000
SET (TY II) (DES 2) (RCP) (3: 1) (C)
EA 2.000 $2,000.000 $3,885.000 $3,668.000 $1,750.000 $1,700.000 $1,935.320 $3,668.000 $6,008.000
SET (TY II) (DES 2) (RCP) (4: 1) (C)
EA 2.000 $3,751.000 $3,885.000 $3,668.000 $2,500.000 $2,500.000 $2,757.770 $3,668.000 $12,024.000
CLEAN EXIST CULVERTS
EA 5.000 $2,085.000 $2,220.000 $1,200.000 $2,350.000 $2,500.000 $2,601.530 $1,200.000 $4,765.000
REMOV STR (INLET)
EA 1.000 $536.000 $3,049.780 $1,200.000 $910.000 $750.000 $1,003.520 $1,200.000 $1,215.000
REMOV STR (WINGWALL)
EA 5.000 $948.000 $2,033.190 $800.000 $1,800.000 $1,500.000 $2,007.050 $800.000 $975.000
REMOV STR (PIPE)
LF 256.000 $12.000 $2.970 $12.000 $18.000 $15.000 $20.070 $12.000 $118.500
REMOVING ROCK RIPRAP
LF 72.000 $5.000 $8.750 $65.000 $16.000 $20.000 $18.130 $65.000 $20.000
REMOVE STR (GABION)
LF 72.000 $51.000 $8.750 $65.000 $38.000 $40.000 $41.820 $65.000 $20.000
MOBILIZATION
LS 1.000 $537,430.080 $380,774.220 $484,041.670 $440,000.000 $600,000.000 $455,000.000 $525,000.000 $709,910.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $3,832.650 $3,330.000 $3,290.000 $2,000.000 $12,500.000 $11,000.000 $7,500.000 $2,765.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 1,738.000 $48.000 $52.910 $67.000 $75.000 $45.000 $119.000 $65.000 $65.000
ROCK FILTER DAMS (REMOVE)
LF 1,738.000 $11.850 $4.440 $15.000 $17.000 $10.000 $23.190 $18.000 $18.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 122.000 $19.630 $49.950 $18.000 $20.000 $20.000 $24.360 $24.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 122.000 $5.620 $3.330 $4.000 $5.000 $10.000 $7.460 $8.000 $30.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 985.000 $2.300 $5.550 $3.550 $4.000 $4.000 $4.720 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 985.000 $0.890 $1.110 $1.250 $1.400 $1.000 $1.050 $1.000 $1.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 80.000 $75.000 $132.500 $83.600 $67.000 $150.000 $114.000 $275.000 $58.300
INTERSECTIONS (ACP)
SY 1,133.000 $40.000 $49.950 $66.670 $53.000 $70.000 $30.660 $45.000 $26.750
DRIVEWAYS (CONC)
SY 204.000 $76.000 $86.580 $90.850 $110.000 $100.000 $94.770 $90.000 $92.000
DRIVEWAYS (ACP)
SY 160.000 $39.000 $49.950 $42.350 $50.000 $50.000 $49.180 $45.000 $26.750
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 32,267.000 $0.220 $0.110 $0.050 $0.060 $0.200 $0.220 $0.330 $0.170
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 16,134.000 $0.160 $0.220 $0.090 $0.110 $0.200 $0.370 $0.400 $0.170
CONC MEDIAN
SY 1,230.000 $66.500 $69.930 $52.000 $83.000 $75.000 $84.590 $55.000 $78.750
MTL W-BEAM GD FEN (TIM POST)
LF 350.000 $27.100 $45.510 $25.770 $36.000 $26.000 $29.140 $26.000 $34.760
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,791.450 $3,163.500 $2,206.000 $2,970.000 $2,100.000 $2,175.220 $1,900.000 $2,344.000
REMOVE METAL BEAM GUARD FENCE
LF 800.000 $2.850 $3.330 $1.500 $3.000 $2.000 $1.190 $1.000 $3.030
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $200.000 $538.350 $350.000 $340.000 $250.000 $248.590 $215.000 $335.500
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $345.000 $444.000 $350.000 $370.000 $250.000 $271.500 $235.000 $357.500
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $2,650.000 $4,616.490 $2,885.000 $3,700.000 $2,700.000 $3,138.540 $2,700.000 $3,617.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $300.000 $654.900 $350.000 $360.000 $250.000 $312.500 $275.000 $358.000
WIRE FENCE (TY A)
LF 25.000 $15.000 $111.000 $25.490 $96.000 $100.000 $34.930 $85.000 $85.000
IN RD IL (TY SA) 50T-12 (400W EQ) LED
EA 3.000 $3,828.320 $5,050.500 $5,660.000 $6,750.000 $6,000.000 $5,197.850 $5,000.000 $4,800.000
IN RD IL (TY SA) 50T-12-12(400W EQ)LED
EA 6.000 $5,064.300 $6,160.500 $6,925.000 $7,676.000 $7,000.000 $7,546.550 $6,200.000 $7,000.000
CONDT (PVC) (SCH 40) (2")
LF 2,377.000 $10.850 $12.770 $13.750 $16.000 $15.000 $11.370 $20.000 $10.750
CONDT (PVC) (SCH 80) (2") (BORE)
LF 175.000 $25.000 $20.260 $32.000 $24.000 $32.000 $37.530 $43.000 $34.650
ELEC CONDR (NO.8) BARE
LF 2,810.000 $1.400 $2.550 $1.600 $2.000 $1.500 $1.760 $1.800 $1.630
ELEC CONDR (NO.8) INSULATED
LF 5,592.000 $1.450 $2.780 $1.850 $2.000 $2.000 $2.100 $1.900 $1.940
GROUND BOX TY D (162922)W/APRON
EA 5.000 $850.000 $1,060.050 $1,256.000 $930.000 $1,500.000 $1,649.210 $1,500.000 $1,522.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 25.000 $540.000 $865.800 $649.210 $620.000 $850.000 $612.150 $550.000 $935.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $700.000 $999.000 $749.210 $800.000 $1,200.000 $779.100 $700.000 $1,320.000
REMOVE SM RD SN SUP&AM
EA 18.000 $80.000 $111.000 $95.490 $70.000 $75.000 $69.010 $62.000 $93.500
INSTL OM ASSM (OM-2Y)(WC)GND
EA 11.000 $65.000 $61.050 $69.490 $68.000 $80.000 $66.780 $60.000 $60.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 40.000 $20.000 $22.200 $10.490 $17.000 $20.000 $16.700 $15.000 $22.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 10.000 $95.000 $94.350 $79.490 $96.000 $80.000 $94.610 $85.000 $93.500
INSTL DEL ASSM (D-SW)SZ 1(WFLX)SRF
EA 4.000 $111.000 $138.750 $85.490 $96.000 $100.000 $94.600 $85.000 $135.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GND
EA 9.000 $80.000 $94.350 $79.490 $96.000 $100.000 $94.600 $85.000 $93.500
INSTL DEL ASSM (D-SY)SZ 1(YFLX)SRF
EA 3.000 $46.270 $138.750 $85.490 $96.000 $100.000 $94.610 $85.000 $135.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 30,920.000 $0.210 $0.280 $0.220 $0.300 $0.250 $0.260 $0.250 $0.270
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 20.000 $2.520 $5.550 $10.000 $6.000 $5.000 $5.250 $5.000 $5.500
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 3,100.000 $0.200 $0.310 $0.220 $0.300 $0.280 $0.290 $0.280 $0.310
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 17,420.000 $0.190 $0.290 $0.220 $0.300 $0.260 $0.270 $0.260 $0.290
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 438.000 $3.510 $5.550 $4.000 $6.000 $5.000 $5.250 $5.000 $5.500
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 256.000 $0.520 $0.670 $1.500 $0.700 $0.600 $0.630 $0.600 $0.660
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,800.000 $0.750 $0.670 $0.650 $0.700 $0.600 $0.630 $0.600 $0.660
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 57.000 $8.700 $19.980 $12.000 $21.000 $18.000 $18.900 $18.000 $19.800
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 15.000 $38.000 $33.300 $64.000 $34.000 $30.000 $31.500 $30.000 $33.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 33,400.000 $0.330 $0.580 $0.440 $0.600 $0.550 $0.550 $0.520 $0.570
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,450.000 $0.320 $0.610 $0.500 $0.600 $0.600 $0.580 $0.550 $0.610
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 19,024.000 $0.330 $0.580 $0.440 $0.600 $0.600 $0.550 $0.520 $0.570
REFL PAV MRKR TY II-A-A
EA 365.000 $2.950 $5.550 $6.000 $6.000 $5.000 $5.250 $5.000 $5.500
ELIM EXT PAV MRK & MRKS (4")
LF 704.000 $0.350 $1.670 $2.500 $2.000 $1.500 $1.580 $1.500 $1.650
SP MIXES SP-C SAC-A PG76-22
TON 6,374.000 $80.000 $116.000 $102.950 $98.000 $128.000 $106.610 $116.000 $122.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,000.000 $19,980.000 $20,017.860 $14,240.000 $15,000.000 $8,000.000 $7,500.000 $5,940.000
TMA (STATIONARY)
DAY 8.000 $126.000 $555.000 $200.000 $163.000 $275.000 $225.000 $325.000 $1,650.000
TMA (MOBILE OPERATION)
HR 48.000 $50.000 $222.000 $30.000 $45.000 $50.000 $145.000 $100.000 $199.000
Totals: $4,596,123.763 $4,380,301.840 $4,388,970.790 $4,705,181.860 $5,344,404.400 $5,499,616.403 $5,655,264.040 $6,039,418.370