Show Job Controls
Bid Cobra

KERR SH 27 (0142-04-052)

Items: 101

County: KERR
Length: 0.6090 MILES
Highway: SH 27
District: SAN ANTONIO
Control Number: 0142-04-052
DBE Goal: 0.0%
Project: C 142-4-52
Guaranty: $50,000.00
Time: 118 WORKING DAYS
Engineer's Estimate: $2,512,371.39
Date: 04/03/2025 (1 year ago)
Contract Number: 4253028
Type: INSTALL/UPGRADE DRAINAGE STRUCTURE(S)
Project ID: A00139936
Project Description: REPLACE EXISTING CMP WITH BOX CULVERT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RICARDO GONZALEZ
ANDRES GONZALEZ
ROBERTO MADRIGAL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,512,371.39
$1,403,742.29
Over/Under Est: -44.13% -$1,108,629.10
$1,730,872.44
Over/Under Est: -31.11% -$781,498.95
Amt Left: 23.3% $327,130.15
$1,877,364.22
Over/Under Est: -25.28% -$635,007.17
Amt Left: 33.74% $473,621.93
Delta: -8.46% -$146,491.78
Over/Under Est: -13% -$326,492.24
Amt Left: 55.72% $782,136.86
Delta: -16.43% -$308,514.93
Over/Under Est: -8.28% -$208,063.15
Amt Left: 64.15% $900,565.95
Delta: -5.42% -$118,429.09
$2,421,453.00
Over/Under Est: -3.62% -$90,918.39
Amt Left: 72.5% $1,017,710.71
Delta: -5.08% -$117,144.76
$2,672,864.20
Over/Under Est: 6.39% $160,492.81
Amt Left: 90.41% $1,269,121.91
Delta: -10.38% -$251,411.20
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 4.18% $58,676.43
FLASHER EQUIPMENT COMPANY 1.51% $21,196.51
CK NEWBERRY, LLC 0.80% $11,229.94
Total: 6.49% $91,102.88

Bid Items & Bid Tabulations

101 Total 0 of 101
KERR  |  SH 27  |  SAN ANTONIO  |  0142-04-052  |  04/03/2025  |  $2,512,371.39  |  C 142-4-52  |  INSTL/UPGRADE DRAINAGE STRUCT(S)  |  118 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACEE CONSTRUCTION LLC.
MPB, INC.
DAN WILLIAMS COMPANY
ACME BRIDGE COMPANY, INC.
HUNTER INDUSTRIES, LTD.
STX CIVIL
ICOS MANAGEMENT, LLC
PREPARING ROW
AC 0.490 $10,000.000 $5,500.000 $6,500.000 $200,000.000 $20,617.630 $21,100.000 $20,000.000 $11,000.000
REMOV CONC (RIPRAP)
SY 320.000 $12.000 $12.500 $10.000 $20.000 $36.900 $42.000 $30.000 $132.000
REMOVING STAB BASE AND ASPH PAV(0"-16")
SY 79.000 $10.000 $20.000 $55.000 $50.000 $106.000 $38.500 $25.000 $220.000
EXCAV (ROADWAY)
CY 27.000 $13.740 $50.000 $85.000 $50.000 $134.000 $77.000 $40.000 $220.000
EXCAV (CHANNEL)
CY 783.000 $12.000 $25.000 $18.000 $40.000 $46.900 $77.000 $40.000 $110.000
EMBANK (FNL)(OC)(TY C)
CY 28.000 $30.000 $55.000 $165.000 $55.000 $238.000 $77.000 $50.000 $110.000
BLADING
HR 10.000 $150.000 $65.850 $180.000 $65.000 $43.400 $144.000 $100.000 $1,100.000
STRAW/HAY MLCH SEED(PERM_RURAL_CLAY)
SY 3,096.000 $0.350 $1.500 $1.000 $5.000 $1.400 $1.360 $6.000 $1.000
VEGETATIVE WATERING
TGL 49.000 $25.000 $35.700 $300.000 $15.000 $143.000 $31.500 $50.000 $1.000
SOIL RET BLKT(CHAN_TEMP_4 PSF)
SY 526.000 $3.500 $4.750 $5.250 $8.000 $4.800 $4.640 $10.000 $11.000
ASPH (AC-15P OR CRS-2P)
GAL 1,070.000 $5.750 $7.500 $6.300 $22.000 $9.400 $9.200 $25.000 $22.000
AGGR (TY-PB, GR-4)(SAC-B)
CY 31.000 $125.000 $241.000 $735.000 $450.000 $652.000 $553.550 $900.000 $440.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 195.000 $133.000 $205.000 $315.000 $210.000 $338.000 $220.000 $200.000 $330.000
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
TON 112.000 $190.790 $205.000 $331.000 $235.000 $355.000 $225.500 $400.000 $330.000
PLANE ASPH CONC PAV(0" TO 2")
SY 973.000 $2.600 $4.500 $10.500 $14.000 $11.300 $9.040 $25.000 $12.000
CUT & RESTORE ASPH PAVING
SY 150.000 $160.000 $107.500 $140.000 $185.000 $128.000 $239.660 $350.000 $330.000
CEM STABIL BKFL
CY 154.000 $161.760 $142.500 $95.000 $250.000 $390.000 $324.000 $250.000 $440.000
FLOWABLE BACKFILL
CY 40.000 $250.000 $145.000 $150.000 $265.000 $225.000 $324.000 $300.000 $440.000
TRENCH EXCAVATION PROTECTION
LF 220.000 $5.000 $8.500 $17.000 $1.000 $156.000 $34.560 $20.000 $1.000
TEMPORARY SPL SHORING
SF 1,430.000 $25.000 $20.000 $106.000 $25.000 $56.400 $70.200 $75.000 $10.000
CL C CONC (CAP)
CY 1.000 $1,075.000 $850.000 $650.000 $1,200.000 $4,270.000 $1,943.990 $5,000.000 $4,400.000
RIPRAP (CONC)(4 IN)
CY 21.000 $350.000 $495.000 $645.000 $625.000 $1,060.000 $674.990 $900.000 $550.000
RIPRAP (CONC)(5 IN)
CY 105.100 $479.000 $505.000 $460.000 $600.000 $932.000 $669.590 $1,000.000 $660.000
RAIL (TY C1W)
LF 91.720 $227.240 $532.000 $550.000 $400.000 $741.000 $430.920 $600.000 $660.000
GABION MATTRESSES (GALV)(9 IN)
SY 100.000 $150.000 $120.000 $168.000 $200.000 $121.000 $136.000 $100.000 $275.000
GABION (1.5' X 3')(GALV)
CY 18.000 $300.000 $120.000 $265.000 $300.000 $480.000 $650.000 $200.000 $330.000
CONC BOX CULV (6 FT X 5 FT)
LF 73.000 $654.590 $785.000 $1,650.000 $1,000.000 $1,160.000 $944.450 $1,100.000 $1,980.000
CONC BOX CULV (7 FT X 3 FT)
LF 210.000 $800.000 $615.000 $450.000 $900.000 $1,170.000 $1,037.490 $1,300.000 $2,200.000
CONC BOX CULV (12 FT X 5 FT)
LF 73.000 $1,586.980 $3,250.000 $2,700.000 $2,000.000 $2,660.000 $3,197.860 $2,500.000 $3,300.000
RC PIPE (CL III)(36 IN)
LF 82.000 $188.740 $151.500 $165.000 $165.000 $232.000 $118.800 $300.000 $385.000
WINGWALL (PW - 1) (HW=9 FT)
EA 2.000 $45,871.840 $38,500.000 $40,000.000 $50,000.000 $54,300.000 $38,121.140 $60,000.000 $22,000.000
SET (TY I)(S= 7 FT)(HW= 4 FT)(4:1)(C)
EA 10.000 $12,500.000 $9,750.000 $5,425.000 $7,500.000 $8,340.000 $11,311.530 $20,000.000 $22,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $4,963.330 $4,499.950 $5,200.000 $6,000.000 $9,130.000 $6,543.670 $10,000.000 $16,500.000
REMOV STR (MANHOLE)
EA 1.000 $1,360.430 $500.000 $500.000 $1,800.000 $1,050.000 $782.190 $1,000.000 $2,200.000
REMOV STR (SET)
EA 2.000 $607.890 $350.000 $250.000 $650.000 $409.000 $669.590 $250.000 $550.000
REMOV STR (WINGWALL)
EA 2.000 $1,838.720 $330.750 $500.000 $1,850.000 $843.000 $1,564.390 $2,500.000 $1,320.000
REMOV STR (PIPE)
LF 643.000 $26.000 $21.800 $9.250 $25.000 $17.900 $59.400 $20.000 $11.000
REMOVE STR (RAIL)
LF 60.000 $15.000 $15.200 $5.750 $12.000 $22.300 $12.500 $50.000 $220.000
MOBILIZATION
LS 1.000 $1,256,475.360 $137,500.000 $150,000.000 $180,000.000 $195,000.000 $230,366.920 $220,000.000 $170,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $5,000.000 $5,500.000 $5,000.000 $20,000.000 $6,470.000 $20,270.000 $10,000.000 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 70.000 $89.010 $80.000 $75.000 $150.000 $358.000 $169.170 $60.000 $1.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 228.000 $35.000 $47.900 $47.250 $45.000 $55.600 $53.790 $70.000 $5.000
ROCK FILTER DAMS (REMOVE)
LF 228.000 $14.830 $5.300 $5.250 $5.000 $12.400 $12.000 $10.000 $2.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 314.000 $25.000 $29.800 $29.500 $28.000 $31.300 $30.300 $60.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 314.000 $7.970 $2.650 $2.650 $2.500 $10.000 $9.700 $22.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 920.000 $4.250 $4.750 $4.750 $4.450 $5.100 $4.900 $7.000 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 920.000 $1.000 $0.950 $1.000 $1.000 $1.700 $1.650 $2.500 $1.000
CONSTRUCTING DETOURS
SY 392.000 $90.000 $56.600 $205.000 $100.000 $166.000 $253.000 $200.000 $44.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 3.000 $6,000.000 $5,000.000 $4,850.000 $3,500.000 $5,200.000 $11,588.250 $7,500.000 $11,000.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 210.000 $50.000 $26.500 $140.000 $45.000 $152.000 $115.000 $160.000 $110.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 360.000 $200.000 $26.800 $110.000 $30.000 $40.300 $75.000 $100.000 $110.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $140.000 $25.050 $105.000 $30.000 $53.400 $85.000 $100.000 $110.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 210.000 $10.000 $10.000 $40.000 $15.000 $17.800 $70.000 $30.000 $44.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 220.000 $10.000 $10.000 $28.000 $15.000 $13.800 $80.000 $30.000 $44.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 40.000 $20.000 $10.000 $40.000 $15.000 $28.100 $125.000 $30.000 $44.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 210.000 $11.000 $12.500 $62.000 $35.000 $48.800 $95.000 $105.000 $44.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 360.000 $30.000 $12.500 $31.000 $25.000 $30.500 $55.000 $30.000 $44.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 80.000 $23.920 $12.500 $20.000 $25.000 $51.300 $65.000 $30.000 $44.000
CONC CURB (TY I)
LF 179.000 $20.000 $12.150 $41.000 $30.000 $45.700 $34.560 $100.000 $88.000
DRIVEWAYS (CONC)
SY 67.000 $101.210 $99.650 $157.000 $110.000 $205.000 $128.520 $150.000 $275.000
DRIVEWAYS (ACP)
SY 12.000 $50.430 $325.800 $350.000 $165.000 $372.000 $101.200 $110.000 $440.000
CONC SIDEWALKS (4")
SY 101.000 $70.140 $62.500 $130.000 $85.000 $143.000 $97.200 $100.000 $88.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,750.000 $750.000 $1,500.000 $2,000.000 $2,900.000 $875.000 $1,500.000 $5,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,250.000 $650.000 $650.000 $2,000.000 $1,010.000 $800.000 $1,000.000 $5,500.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL2)
EA 1.000 $20,233.000 $20,000.000 $30,000.000 $30,000.000 $30,900.000 $25,750.000 $20,000.000 $13,200.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL2)
EA 2.000 $8,000.000 $6,750.000 $8,750.000 $8,500.000 $11,100.000 $7,700.000 $9,000.000 $13,200.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 2.000 $150.000 $182.900 $100.000 $200.000 $84.600 $97.580 $100.000 $550.000
WK ZN PAV MRK REMOV (W)4"(DOT)
LF 144.000 $1.660 $3.700 $3.680 $3.500 $2.550 $2.400 $4.500 $5.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 4,424.000 $0.500 $2.050 $2.050 $1.950 $2.550 $2.400 $2.500 $4.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $12.000 $15.750 $15.750 $15.000 $11.300 $10.650 $18.000 $5.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 7,860.000 $0.460 $2.050 $2.050 $1.950 $2.550 $2.400 $2.500 $4.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 24.000 $1.640 $3.550 $5.000 $2.260 $2.200 $1.690 $2.500 $20.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 40.000 $1.380 $2.750 $5.000 $2.260 $2.200 $1.690 $2.500 $20.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 28.000 $2.000 $3.250 $5.000 $2.260 $2.200 $1.690 $3.000 $20.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 237.000 $1.000 $2.150 $2.100 $2.000 $2.800 $2.660 $2.500 $5.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 205.000 $8.900 $13.150 $13.130 $12.500 $11.300 $10.650 $15.000 $5.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $186.090 $262.500 $262.500 $250.000 $225.000 $213.030 $303.000 $2,200.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $232.220 $288.750 $288.750 $275.000 $254.000 $239.660 $333.000 $2,200.000
PAVEMENT SLER 6"
LF 9,134.000 $0.320 $1.000 $1.000 $1.000 $0.560 $0.530 $1.500 $2.000
PAVEMENT SLER 8"
LF 237.000 $0.430 $1.600 $1.580 $1.500 $0.850 $0.800 $2.000 $5.000
PAVEMENT SLER 24"
LF 205.000 $1.820 $5.800 $5.780 $5.500 $3.400 $3.200 $7.000 $8.000
PAVEMENT SLER (ARROW)
EA 2.000 $51.680 $105.000 $105.000 $100.000 $113.000 $106.520 $121.000 $1,100.000
PAVEMENT SLER (WORD)
EA 2.000 $45.710 $105.000 $105.000 $100.000 $113.000 $106.520 $121.000 $1,100.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 970.000 $0.600 $1.600 $1.580 $1.500 $1.400 $1.330 $2.000 $5.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 2,200.000 $0.600 $1.300 $1.320 $1.250 $1.400 $1.330 $1.500 $5.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 1,049.000 $0.480 $1.600 $1.160 $1.500 $1.400 $1.330 $2.000 $5.000
REFL PAV MRK TY I (Y)6"(SLD)(060MIL)
LF 3,815.000 $0.360 $1.150 $1.160 $1.100 $1.300 $1.220 $1.500 $5.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 1,100.000 $0.600 $1.300 $1.320 $1.250 $1.400 $1.330 $1.500 $5.000
REFL PAV MRKR TY II-A-A
EA 28.000 $6.000 $10.500 $10.500 $10.000 $5.600 $5.330 $12.000 $22.000
ELIM EXT PM & MRKS (4")
LF 5,074.000 $0.750 $1.600 $1.580 $1.500 $1.150 $1.070 $2.000 $2.000
UNDERSEAL COURSE
GAL 195.000 $4.380 $4.500 $14.700 $25.000 $15.800 $5.750 $15.000 $55.000
HYDROSTATIC PRESSURE TEST
EA 1.000 $2,500.000 $1,500.000 $1,000.000 $6,000.000 $5,000.000 $3,500.000 $8,000.000 $5,500.000
REMOVE 8" WATER LINE
LF 100.000 $12.000 $15.000 $25.000 $25.000 $33.800 $25.000 $35.000 $242.000
TIE IN (COMPLETE)(8")
EA 2.000 $2,200.000 $2,500.000 $500.000 $4,000.000 $5,000.000 $3,500.000 $5,000.000 $22,000.000
PIPE WTR MAIN (PVC/C-900) (8IN.)
LF 56.000 $95.000 $80.000 $100.000 $325.000 $500.000 $125.000 $120.000 $440.000
DUCTILE IRON FITTINGS
TON 1.800 $6,500.000 $2,500.000 $1,000.000 $7,500.000 $15,000.000 $8,500.000 $9,000.000 $16,500.000
CARRIER PIPE 8" (OPEN CUT TRENCH) (8")
LF 44.000 $115.000 $85.000 $250.000 $185.000 $300.000 $100.000 $130.000 $440.000
TEMPORARY BLOW-OFF COMPLETE (2")
EA 2.000 $1,800.000 $2,850.000 $1,000.000 $5,000.000 $1,000.000 $3,750.000 $5,250.000 $6,600.000
GATE VALVE & BOX (COMPLETE) (8")
EA 2.000 $6,500.000 $2,950.000 $2,250.000 $6,500.000 $5,000.000 $27,500.000 $6,200.000 $11,000.000
24" STEEL CASING
LF 44.000 $155.000 $200.000 $100.000 $325.000 $500.000 $450.000 $400.000 $275.000
TRENCH EXCAVATION PROTECTION
LF 100.000 $5.000 $8.500 $60.000 $1.000 $30.000 $15.000 $20.000 $44.000
Totals: $2,512,371.393 $1,403,742.290 $1,730,872.440 $1,877,364.220 $2,185,879.149 $2,304,308.241 $2,421,453.000 $2,672,864.200
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $3,000.00