KENDALL RM 473 (0142-09-049)
Items: 100
County: KENDALL
Length: 5.9880 MILES
Highway: RM 473
District: SAN ANTONIO
Control Number: 0142-09-049
DBE Goal: 0.0%
Project: C 142-9-49
Guaranty: $81,000.00
Time: 200 WORKING DAYS
Engineer's Estimate: $4,070,599.47
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263012
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00214597
Project Description: WIDEN EXISTING NARROW ROADWAY TO 28' TO ADD SHOULDERS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ANDRES GONZALEZ
ROBERTO MADRIGAL
KENDALL RM 473 (0142-09-049)
Project Name: N/A
Project: C 142-9-49
Length: 5.9880 MILES
Project Type: CONSTRUCTION
Limits From: FM 1376
Limits To: FM 474
Project Description: WIDEN EXISTING NARROW ROADWAY TO 28' TO ADD SHOULDERS
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,070,599.47 | |||
| $4,095,968.43 |
0.62%
$25,368.96
|
|||
| $4,244,813.85 |
4.28%
$174,214.38
|
3.63%
$148,845.42
|
||
| $4,250,503.37 |
4.42%
$179,903.90
|
3.77%
$154,534.94
|
-0.13%
-$5,689.52
|
|
| $4,427,014.69 |
8.76%
$356,415.22
|
8.08%
$331,046.26
|
-4.15%
-$176,511.32
|
|
| $4,724,931.52 |
16.07%
$654,332.05
|
15.36%
$628,963.09
|
-6.73%
-$297,916.83
|
|
| $4,728,410.38 |
16.16%
$657,810.91
|
15.44%
$632,441.95
|
-0.07%
-$3,478.86
|
|
| $6,085,395.77 |
49.5%
$2,014,796.30
|
48.57%
$1,989,427.34
|
-28.70%
-$1,356,985.39
|
E
Engineer's Estimate
$4,070,599.47
1
Awarded
$4,095,968.43
Over/Under Est:
0.62%
$25,368.96
$4,244,813.85
Over/Under Est:
4.28%
$174,214.38
Amt Left:
3.63%
$148,845.42
$4,250,503.37
Over/Under Est:
4.42%
$179,903.90
Amt Left:
3.77%
$154,534.94
Delta:
-0.13%
-$5,689.52
$4,427,014.69
Over/Under Est:
8.76%
$356,415.22
Amt Left:
8.08%
$331,046.26
Delta:
-4.15%
-$176,511.32
$4,724,931.52
Over/Under Est:
16.07%
$654,332.05
Amt Left:
15.36%
$628,963.09
Delta:
-6.73%
-$297,916.83
$4,728,410.38
Over/Under Est:
16.16%
$657,810.91
Amt Left:
15.44%
$632,441.95
Delta:
-0.07%
-$3,478.86
$6,085,395.77
Over/Under Est:
49.5%
$2,014,796.30
Amt Left:
48.57%
$1,989,427.34
Delta:
-28.70%
-$1,356,985.39
Bid Items & Bid Tabulations
100
Total
0 of 100
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $50,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $15,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $15,000.00 |
| Total: | $80,000.00 |