KAUFMAN FM 460 (2249-01-008)

Items: 94

County: KAUFMAN
Length: N/A
Highway: FM 460
District: DALLAS
Control Number: 2249-01-008
DBE Goal: N/A
Project: STP 2019(674)
Guaranty: N/A
Time: 124 WORKING DAYS
Engineer's Estimate: $1,543,309.88
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: REHABILITATION OF EXISTING PAVEMENT AND ADD SHLDRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,543,309.88
$1,469,989.63
Over/Under Est: -4.75% -$73,320.25
Over/Under Est: 6.33% $97,721.15
Amt Left: 11.64% $171,041.40
Over/Under Est: 12.71% $196,231.14
Amt Left: 18.34% $269,551.39
Delta: -6.00% -$98,509.99
Over/Under Est: 12.76% $196,887.08
Amt Left: 18.38% $270,207.33
Delta: -0.04% -$655.94
Over/Under Est: 28.51% $440,033.13
Amt Left: 34.92% $513,353.38
Delta: -13.97% -$243,146.05
$2,084,892.42
Over/Under Est: 35.09% $541,582.54
Amt Left: 41.83% $614,902.79
Delta: -5.12% -$101,549.41

Bid Items & Bid Tabulations

94 Total 0 of 94
KAUFMAN  |  FM 460  |  DALLAS  |  2249-01-008  |  03/06/2019  |  $1,543,309.88  |  STP 2019(674)  |  REHAB OF EXIST PAVMT AND ADD SHLDRS  |  124 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
TEXAS MATERIALS GROUP, INC.
ACCELERATED CRITICAL PATH, INC.
A. L. HELMCAMP, INC.
PREPARING ROW
STA 59.500 $525.000 $105.000 $830.000 $1,200.000 $1,900.000 $950.000 $2,590.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 1.000 $1,500.000 $2,100.000 $2,500.000 $1,000.000 $5,000.000 $1,900.000 $2,200.000
REMOVING CONC (RIPRAP)
SY 10.000 $13.000 $52.500 $60.000 $50.000 $25.000 $30.000 $80.000
REMOVING CONC (DRIVEWAYS)
SY 495.000 $20.000 $15.750 $15.000 $20.000 $25.000 $15.000 $26.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 708.000 $6.000 $15.750 $14.000 $20.000 $11.000 $15.000 $20.000
EXCAVATION (ROADWAY)
CY 217.000 $15.000 $42.000 $18.500 $12.000 $28.000 $29.000 $35.000
SUBGRADE WIDENING (ORD COMP)
STA 34.500 $250.000 $353.000 $225.000 $500.000 $373.000 $450.000 $1,600.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,050.000 $17.000 $31.500 $14.000 $25.000 $22.000 $28.000 $26.000
BACKFILL (TY A OR B)
STA 25.000 $250.000 $73.500 $225.000 $400.000 $300.000 $390.000 $550.000
ROAD GRADER WORK (ORD COMP)
STA 57.600 $300.000 $26.250 $175.000 $300.000 $110.000 $790.000 $300.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 33,858.000 $0.100 $0.210 $0.190 $0.130 $0.160 $0.150 $0.150
DRILL SEED (TEMP)(WARM OR COOL)
SY 11,286.000 $0.100 $0.030 $0.190 $0.110 $0.140 $0.150 $0.150
VEGETATIVE WATERING
MG 4,617.000 $1.500 $0.010 $1.000 $7.000 $0.010 $15.000 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,072.000 $0.900 $1.680 $1.200 $3.000 $1.400 $2.080 $2.200
FL BS (CMP IN PLC)(TY-D GR-1-2)(14")
SY 2,593.000 $20.000 $17.500 $20.000 $30.000 $20.000 $55.000 $20.000
PRIME COAT(MC-30 OR AE-P)
GAL 521.000 $4.500 $9.450 $7.500 $8.000 $4.000 $8.000 $11.000
ASPH (CRS-2P)
GAL 5,284.000 $4.000 $3.850 $4.600 $4.500 $3.900 $7.000 $3.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 4,438.000 $4.200 $4.200 $4.750 $4.500 $5.000 $7.200 $4.500
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 205.000 $130.000 $126.000 $150.000 $125.000 $175.000 $280.000 $150.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 2,327.000 $85.000 $88.880 $100.000 $105.000 $85.000 $115.000 $99.440
SUPERPAVE MIXTURES SP-C PG64-22
TON 448.000 $85.000 $136.500 $115.000 $105.000 $105.000 $130.000 $136.240
FLEXIBLE PAVEMENT STRUCTURE REPAIR(19")
SY 3,625.000 $85.000 $71.330 $106.000 $70.000 $85.000 $69.000 $124.000
PLANE ASPH CONC PAV(0" TO 3")
SY 18,827.000 $2.500 $2.530 $2.750 $4.000 $2.350 $3.000 $3.500
CEM STABIL BKFL
CY 86.000 $340.000 $157.500 $245.000 $400.000 $290.000 $175.000 $210.000
CUT & RESTORE ASPH PAVING
SY 98.000 $150.000 $157.500 $115.000 $125.000 $148.000 $170.000 $85.000
TRENCH EXCAVATION PROTECTION
LF 100.000 $13.500 $10.500 $25.000 $20.000 $26.000 $2.000 $12.000
TEMPORARY SPL SHORING
SF 724.000 $65.000 $10.500 $42.000 $45.000 $58.000 $70.000 $59.000
RIPRAP (CONC)(4 IN)
CY 1.400 $500.000 $735.000 $1,100.000 $800.000 $1,000.000 $1,500.000 $1,600.000
RIPRAP (CONC)(5 IN)
CY 3.500 $550.000 $735.000 $900.000 $500.000 $1,000.000 $950.000 $1,300.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 31.500 $130.000 $210.000 $195.000 $180.000 $140.000 $200.000 $185.000
RIPRAP (MOW STRIP)(4 IN)
CY 10.500 $525.000 $735.000 $550.000 $500.000 $1,000.000 $900.000 $930.000
CONC BOX CULV (5 FT X 3 FT)
LF 78.000 $260.000 $525.000 $350.000 $550.000 $465.000 $310.000 $350.000
RC PIPE (CL III)(18 IN)
LF 448.000 $50.000 $63.000 $44.000 $40.000 $45.000 $70.000 $70.000
RC PIPE (CL III)(24 IN)
LF 56.000 $75.000 $94.500 $70.000 $55.000 $58.000 $95.000 $180.000
RC PIPE (CL III)(36 IN)
LF 44.000 $115.000 $367.500 $115.000 $110.000 $93.000 $290.000 $260.000
RC PIPE (CL III)(42 IN)
LF 16.000 $130.000 $525.000 $155.000 $175.000 $128.000 $290.000 $280.000
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 1.000 $7,000.000 $9,450.000 $8,000.000 $7,000.000 $6,000.000 $12,000.000 $17,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $12,000.000 $17,850.000 $7,500.000 $7,000.000 $13,000.000 $10,000.000 $17,000.000
SET (TY I) (36 IN) (3: 1) (C)
EA 4.000 $4,200.000 $7,350.000 $6,000.000 $3,000.000 $3,900.000 $4,500.000 $3,000.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 1.000 $8,000.000 $11,550.000 $9,000.000 $7,000.000 $6,750.000 $13,500.000 $14,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 20.000 $720.000 $945.000 $620.000 $575.000 $800.000 $900.000 $1,300.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $880.000 $1,470.000 $950.000 $900.000 $1,050.000 $1,400.000 $1,700.000
CLEAN EXIST CULVERTS
EA 2.000 $1,600.000 $2,100.000 $4,000.000 $1,500.000 $2,650.000 $1,500.000 $2,000.000
REMOV STR (SET)
EA 8.000 $250.000 $525.000 $160.000 $500.000 $215.000 $250.000 $750.000
REMOV STR (HEADWALL)
EA 5.000 $950.000 $1,050.000 $1,200.000 $1,000.000 $430.000 $900.000 $1,400.000
REMOV STR (PIPE)
LF 525.000 $13.000 $21.000 $14.000 $15.000 $5.450 $9.000 $25.000
MOBILIZATION
LS 1.000 $132,119.080 $138,967.000 $130,000.000 $150,000.000 $172,472.000 $195,000.000 $190,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $15,000.000 $12,600.000 $3,200.000 $7,000.000 $14,491.330 $19,000.000 $12,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 164.000 $17.500 $18.700 $22.000 $28.000 $25.000 $45.000 $15.000
CONSTRUCTION EXITS (REMOVE)
SY 164.000 $7.000 $8.800 $8.800 $13.000 $10.000 $10.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,857.000 $3.000 $2.100 $1.900 $3.000 $2.200 $5.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,857.000 $0.800 $0.500 $0.550 $1.000 $1.000 $1.000 $1.250
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 415.000 $5.500 $3.850 $4.350 $6.000 $3.800 $7.000 $7.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 415.000 $1.000 $0.500 $0.850 $1.000 $1.000 $1.000 $1.250
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 180.000 $50.000 $10.000 $90.000 $90.000 $100.000 $15.000 $45.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 180.000 $10.000 $10.000 $20.000 $20.000 $45.000 $12.000 $15.000
DRIVEWAYS (ACP)
SY 232.000 $45.000 $36.330 $54.000 $60.000 $60.000 $49.000 $55.000
DRIVEWAYS (BASE)
SY 430.000 $27.000 $15.750 $30.000 $20.000 $30.000 $19.000 $21.000
DRIVEWAYS (CONC) (HES)
SY 753.000 $100.000 $115.500 $86.000 $100.000 $145.000 $69.000 $105.000
RUMBLE STRIPS (SHOULDER)
LF 10,158.000 $0.150 $0.300 $1.150 $0.750 $0.600 $0.300 $0.450
RUMBLE STRIPS (CENTERLINE)
LF 3,740.000 $0.170 $0.300 $0.400 $0.750 $0.600 $0.300 $0.600
MTL W-BEAM GD FEN (TIM POST)
LF 87.500 $20.000 $20.200 $27.500 $27.000 $25.000 $22.000 $20.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 1.000 $625.000 $1,039.970 $1,200.000 $1,300.000 $1,100.000 $1,200.000 $1,100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,550.000 $2,681.170 $3,000.000 $3,000.000 $2,900.000 $2,500.000 $2,700.000
CRASH CUSH ATTEN (INSTL)
EA 2.000 $8,000.000 $3,150.000 $10,250.000 $10,000.000 $9,000.000 $14,000.000 $10,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $800.000 $315.000 $1,100.000 $2,000.000 $850.000 $850.000 $1,000.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 1.000 $215.000 $243.740 $415.000 $500.000 $255.000 $250.000 $240.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 11.000 $460.000 $498.320 $620.000 $600.000 $500.000 $400.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $570.000 $628.310 $740.000 $800.000 $625.000 $500.000 $620.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $760.000 $785.390 $880.000 $900.000 $800.000 $550.000 $770.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 1.000 $900.000 $785.390 $880.000 $900.000 $800.000 $550.000 $770.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $815.000 $937.050 $1,050.000 $1,100.000 $965.000 $600.000 $920.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $880.000 $893.720 $990.000 $1,000.000 $920.000 $650.000 $880.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $1,000.000 $1,191.630 $1,265.000 $1,300.000 $1,200.000 $700.000 $1,200.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 6.000 $65.000 $61.750 $50.000 $60.000 $70.000 $80.000 $65.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 4.000 $30.000 $24.920 $27.500 $40.000 $32.000 $11.000 $35.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 624.000 $0.700 $1.030 $1.350 $1.350 $1.000 $1.000 $1.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 66.000 $6.000 $4.330 $8.250 $8.250 $4.250 $4.500 $4.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 12,957.000 $0.300 $0.430 $1.100 $1.100 $0.430 $0.450 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 64.000 $1.500 $2.250 $1.450 $2.000 $1.050 $2.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 650.000 $2.300 $2.350 $1.450 $2.000 $1.050 $2.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 624.000 $1.500 $1.350 $1.100 $1.100 $1.350 $1.500 $1.300
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 66.000 $7.250 $8.670 $6.600 $6.600 $8.550 $9.000 $8.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 6.000 $145.000 $146.250 $160.000 $160.000 $150.000 $150.000 $143.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $180.000 $167.910 $200.000 $200.000 $175.000 $170.000 $165.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 11,829.000 $0.500 $0.490 $0.720 $0.720 $0.480 $0.500 $0.470
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 12,957.000 $0.500 $0.490 $0.720 $0.720 $0.480 $0.500 $0.470
REFL PAV MRKR TY I-C
EA 30.000 $5.500 $5.420 $5.500 $5.500 $5.500 $6.000 $5.500
REFL PAV MRKR TY II-A-A
EA 341.000 $5.500 $5.420 $5.500 $5.500 $5.500 $6.000 $5.500
FULL - WIDTH MOWING
CYC 3.000 $2,500.000 $525.000 $8,500.000 $3,000.000 $3,300.000 $1,900.000 $1,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 7.000 $100.000 $157.500 $100.000 $300.000 $125.000 $75.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $15,000.000 $3,150.000 $7,500.000 $15,000.000 $6,300.000 $11,000.000 $10,000.000
TMA (STATIONARY)
EA 1.000 $12,000.000 $3,150.000 $7,500.000 $30,000.000 $18,000.000 $7,500.000 $25,000.000
TMA (MOBILE OPERATION)
HR 64.000 $70.000 $63.000 $22.000 $50.000 $25.000 $85.000 $50.000
Totals: $1,543,309.880 $1,469,989.630 $1,641,031.030 $1,739,541.020 $1,740,196.960 $1,983,343.010 $2,084,892.420