Show Job Controls
Bid Cobra

KAUFMAN CR (0918-11-091)

Items: 42

County: KAUFMAN
Length: N/A
Highway: CR
District: DALLAS
Control Number: 0918-11-091
DBE Goal: N/A
Project: BR 1602(004)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $759,083.29
Date: 04/04/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BR AND APPRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$759,083.29
$696,776.52
Over/Under Est: -8.21% -$62,306.77
Over/Under Est: -5.4% -$40,977.19
Amt Left: 3.06% $21,329.58
$720,000.00
Over/Under Est: -5.15% -$39,083.29
Amt Left: 3.33% $23,223.48
Delta: -0.26% -$1,893.90
Over/Under Est: 7.21% $54,742.21
Amt Left: 16.8% $117,048.98
Delta: -13.03% -$93,825.50
Over/Under Est: 7.71% $58,489.21
Amt Left: 17.34% $120,795.98
Delta: -0.46% -$3,747.00
Over/Under Est: 10.55% $80,082.91
Amt Left: 20.44% $142,389.68
Delta: -2.64% -$21,593.70
Over/Under Est: 13% $98,651.88
Amt Left: 23.1% $160,958.65
Delta: -2.21% -$18,568.97
Over/Under Est: 17.9% $135,846.74
Amt Left: 28.44% $198,153.51
Delta: -4.34% -$37,194.86
Over/Under Est: 21.71% $164,802.21
Amt Left: 32.59% $227,108.98
Delta: -3.24% -$28,955.47
Over/Under Est: 33.64% $255,338.96
Amt Left: 45.59% $317,645.73
Delta: -9.80% -$90,536.75

Bid Items & Bid Tabulations

42 Total 0 of 42
KAUFMAN  |  CR  |  DALLAS  |  0918-11-091  |  04/04/2017  |  $759,083.29  |  BR 1602(004)  |  REPLACE BR AND APPRS  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
PIERCE R & B LLC
COPPELL CONSTRUCTION CO., INC.
EAST TEXAS BRIDGE, INC.
SEMA CONSTRUCTION, INC.
REECE CONSTRUCTION CO., INC.
ED BELL CONSTRUCTION COMPANY
MCMAHON CONTRACTING, L.P.
LONGVIEW BRIDGE AND ROAD, LTD.
PREPARING ROW
STA 6.500 $3,200.000 $1,500.000 $3,600.000 $2,500.000 $1,350.000 $3,500.000 $12,000.000 $4,762.000 $525.000 $7,708.000 $7,000.000
EXCAVATION (ROADWAY)
CY 615.000 $16.000 $20.000 $10.000 $14.000 $22.000 $20.000 $25.000 $37.000 $15.750 $21.130 $25.000
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 548.000 $23.000 $22.000 $16.000 $23.000 $29.000 $30.000 $20.000 $25.000 $31.500 $36.290 $40.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 142.000 $35.000 $22.000 $16.000 $29.000 $73.500 $30.000 $28.000 $25.000 $42.000 $45.220 $50.000
COMPOST MANUF TOPSOIL (4")
SY 1,291.000 $2.750 $3.500 $6.000 $4.500 $5.200 $4.500 $3.000 $2.550 $0.500 $4.790 $6.000
BLOCK SODDING
SY 215.000 $10.000 $5.000 $4.000 $2.140 $7.950 $10.000 $3.000 $7.950 $7.350 $9.220 $7.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 1,076.000 $1.000 $0.500 $1.000 $0.170 $1.850 $4.250 $0.250 $1.850 $7.350 $2.150 $1.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 1,291.000 $1.000 $0.250 $1.000 $0.230 $1.750 $2.000 $0.200 $1.750 $0.250 $2.030 $0.750
VEGETATIVE WATERING
MG 130.700 $30.000 $35.000 $1.000 $70.000 $25.000 $10.000 $24.000 $50.000 $1.000 $25.000 $60.000
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 226.000 $18.500 $25.000 $30.000 $28.000 $31.000 $23.000 $22.000 $25.000 $21.660 $20.190 $51.000
FL BS (CMP IN PLC)(TY D GR1-2)(8")
SY 1,189.000 $25.000 $24.000 $30.000 $20.500 $36.000 $25.000 $24.000 $25.000 $28.880 $22.680 $56.000
PRIME COAT (MC-30)
GAL 64.000 $9.000 $25.000 $50.000 $25.000 $28.950 $25.000 $9.500 $28.000 $52.500 $33.580 $22.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 26.000 $110.000 $800.000 $300.000 $350.000 $577.000 $500.000 $600.000 $455.000 $630.000 $669.320 $270.000
DRILL SHAFT (24 IN)
LF 132.000 $155.000 $185.000 $130.000 $139.000 $187.000 $125.000 $140.000 $99.000 $175.000 $178.420 $205.000
DRILL SHAFT (36 IN)
LF 252.000 $190.000 $185.000 $160.000 $245.000 $212.000 $255.000 $220.000 $216.000 $195.000 $199.890 $220.000
CL C CONC (ABUT)(HPC)
CY 57.900 $1,000.000 $925.000 $900.000 $900.000 $1,200.000 $1,100.000 $850.000 $1,721.000 $1,365.000 $1,217.670 $1,200.000
CL C CONC (RAIL FOUNDATION)
CY 29.000 $850.000 $400.000 $600.000 $500.000 $500.000 $600.000 $550.000 $617.000 $525.000 $603.150 $900.000
REINF CONC SLAB (HPC)
SF 2,860.000 $23.000 $21.500 $20.000 $22.000 $29.500 $21.000 $26.000 $35.300 $39.000 $30.770 $30.000
PRESTR CONC SLAB BEAM (5SB12)
LF 172.500 $175.000 $163.000 $160.000 $171.000 $200.000 $200.000 $200.000 $177.000 $315.000 $169.500 $300.000
PRESTR CONC GIRDER (TX28)
LF 297.690 $168.000 $158.000 $160.000 $135.000 $200.000 $200.000 $180.000 $168.000 $275.000 $159.440 $200.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 308.900 $120.000 $125.000 $140.000 $162.000 $141.000 $140.000 $125.000 $109.000 $150.000 $176.170 $140.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 327.800 $165.000 $125.000 $140.000 $168.000 $142.000 $140.000 $125.000 $109.000 $160.000 $177.600 $150.000
RIPRAP (MOW STRIP)(4 IN)
CY 36.000 $500.000 $400.000 $500.000 $500.000 $500.000 $550.000 $350.000 $552.000 $630.000 $498.850 $570.000
RAIL (TY T223)
LF 184.000 $110.000 $115.000 $110.000 $100.000 $130.000 $110.000 $90.000 $181.000 $126.000 $125.180 $145.000
RAIL (TY T223)(HPC)
LF 284.000 $110.000 $115.000 $110.000 $100.000 $113.000 $120.000 $90.000 $181.000 $126.000 $102.340 $180.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 108.000 $90.000 $78.000 $80.000 $84.000 $100.000 $100.000 $85.000 $122.000 $63.000 $75.910 $100.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $18,000.000 $5,500.000 $12,000.000 $7,700.000 $8,500.000 $15,000.000 $37,056.000 $9,150.000 $9,450.000 $35,035.520 $40,000.000
MOBILIZATION
LS 1.000 $66,962.120 $69,000.000 $72,500.000 $70,000.000 $80,000.000 $80,000.000 $83,000.000 $89,000.000 $78,000.000 $92,052.000 $90,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $2,500.000 $2,800.000 $1,600.000 $2,000.000 $1,375.000 $3,000.000 $1,500.000 $490.000 $2,100.000 $2,408.270 $1,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 160.000 $32.000 $23.000 $40.000 $21.400 $35.000 $40.000 $30.000 $35.000 $35.770 $41.760 $26.000
ROCK FILTER DAMS (REMOVE)
LF 160.000 $12.000 $6.000 $10.000 $5.700 $7.950 $5.000 $7.000 $7.950 $14.600 $11.600 $11.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 312.000 $25.000 $14.500 $26.000 $13.850 $13.500 $16.000 $19.000 $13.500 $27.740 $25.520 $20.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $10.000 $7.500 $10.000 $6.900 $7.750 $5.000 $9.000 $7.750 $14.600 $9.280 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 990.000 $2.500 $1.750 $3.000 $1.510 $2.950 $3.000 $2.000 $2.950 $2.310 $1.970 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 990.000 $0.750 $0.500 $1.000 $0.430 $0.750 $0.500 $0.500 $0.750 $0.730 $0.580 $0.650
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $19.000 $24.000 $22.000 $18.500 $22.000 $19.000 $18.000 $22.000 $25.240 $25.520 $21.000
MTL BEAM GD FEN TRANS (TL2)
EA 8.000 $850.000 $1,050.000 $900.000 $865.000 $950.000 $900.000 $900.000 $950.000 $1,167.980 $1,102.000 $950.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,100.000 $2,300.000 $2,300.000 $2,275.000 $2,050.000 $2,400.000 $2,200.000 $2,050.000 $2,423.770 $2,378.000 $2,200.000
WIRE FENCE (TY C)
LF 1,137.000 $15.000 $8.750 $16.000 $12.000 $7.200 $15.000 $7.500 $7.200 $8.400 $8.350 $7.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $520.000 $300.000 $600.000 $675.000 $650.000 $700.000 $470.000 $407.000 $635.090 $87.000 $425.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 4.000 $59.000 $70.000 $100.000 $79.900 $65.000 $90.000 $80.000 $65.000 $78.840 $75.400 $47.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $32.000 $50.000 $50.000 $45.000 $45.000 $45.000 $50.000 $45.000 $55.480 $52.200 $16.000
Totals: $759,083.290 $696,776.520 $718,106.100 $720,000.000 $813,825.500 $817,572.500 $839,166.200 $857,735.170 $894,930.030 $923,885.510 $1,014,422.250