KAUFMAN SH 243 (0522-01-023)

Items: 69

County: KAUFMAN
Length: N/A
Highway: SH 243
District: DALLAS
Control Number: 0522-01-023
DBE Goal: N/A
Project: CC 522-1-23
Guaranty: N/A
Time: 168 WORKING DAYS
Engineer's Estimate: $1,295,144.78
Date: 12/03/2019 (6 years ago)
Contract Number: N/A
Type: GRADE,STRS,ASPALT PVMT, PVMT MRKS & SIGNS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$1,295,144.78
$1,271,679.25
Over/Under Est: -1.81% -$23,465.53
Over/Under Est: 9.19% $119,061.63
Amt Left: 11.21% $142,527.16
Over/Under Est: 11.68% $151,266.67
Amt Left: 13.74% $174,732.20
Delta: -2.28% -$32,205.04
Over/Under Est: 19.38% $250,943.35
Amt Left: 21.58% $274,408.88
Delta: -6.89% -$99,676.68
$1,568,705.99
Over/Under Est: 21.12% $273,561.21
Amt Left: 23.36% $297,026.74
Delta: -1.46% -$22,617.86
Over/Under Est: 24.14% $312,682.62
Amt Left: 26.43% $336,148.15
Delta: -2.49% -$39,121.41
$1,849,979.46
Over/Under Est: 42.84% $554,834.68
Amt Left: 45.48% $578,300.21
Delta: -15.06% -$242,152.06
$1,993,111.64
Over/Under Est: 53.89% $697,966.86
Amt Left: 56.73% $721,432.39
Delta: -7.74% -$143,132.18

Bid Items & Bid Tabulations

69 Total 0 of 69
KAUFMAN  |  SH 243  |  DALLAS  |  0522-01-023  |  12/03/2019  |  $1,295,144.78  |  CC 522-1-23  |  GRADE,STRS,ASPALT PVMT, PVMT MRKS &...  |  168 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FRITCHER CONSTRUCTION SERVICES
ED BELL CONSTRUCTION COMPANY
ACCELERATED CRITICAL PATH, INC.
TEXAS MATERIALS GROUP, INC.
ALTUS CONSTRUCTION LLC
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
A. L. HELMCAMP, INC.
PREPARING ROW
STA 31.260 $1,250.000 $350.000 $1,155.000 $900.000 $1,500.000 $1,697.410 $1,500.000 $3,800.000 $2,000.000
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 2.000 $640.000 $1,000.000 $525.000 $1,400.000 $2,200.000 $1,539.420 $400.000 $5,000.000 $2,000.000
REMOVING CONC (MEDIANS)
SY 44.000 $20.000 $20.000 $21.000 $85.000 $350.000 $13.810 $25.000 $20.000 $60.000
REMOVING CONC (DRIVEWAYS)
SY 1,000.000 $13.000 $15.000 $15.750 $15.000 $38.000 $13.890 $15.000 $20.000 $35.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 909.000 $5.500 $15.000 $15.750 $9.000 $15.000 $17.650 $15.000 $20.000 $24.000
EXCAVATION (ROADWAY)
CY 520.880 $9.000 $15.000 $31.500 $15.000 $32.000 $10.010 $15.000 $20.000 $35.000
SUBGRADE WIDENING (DENS CONT)
STA 37.330 $365.000 $350.000 $1,575.000 $1,900.000 $500.000 $814.760 $800.000 $650.000 $3,000.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,331.330 $16.000 $20.000 $21.000 $15.000 $22.500 $20.370 $25.000 $30.000 $25.000
ROAD GRADER WORK (ORD COMP)
STA 37.330 $375.000 $350.000 $525.000 $350.000 $250.000 $237.640 $300.000 $450.000 $1,100.000
COMPOST MANUF TOPSOIL (4")
SY 4,817.830 $3.000 $3.250 $2.100 $0.930 $1.400 $1.360 $3.000 $6.000 $5.000
BLOCK SODDING
SY 4,817.830 $5.000 $4.500 $4.000 $3.000 $4.000 $5.800 $4.000 $6.000 $4.700
DRILL SEED (TEMP)(WARM OR COOL)
SY 1,589.920 $0.150 $1.000 $0.060 $0.600 $1.600 $1.100 $2.000 $2.000 $0.900
VEGETATIVE WATERING
MG 175.960 $5.000 $20.000 $33.000 $49.000 $28.000 $24.010 $15.000 $50.000 $30.000
FL BS (CMP IN PLACE) (TY D GR 1-2)(10")
SY 5,877.730 $20.000 $13.000 $21.000 $23.400 $18.000 $10.230 $30.000 $22.000 $24.000
SUPERPAVE MIXTURES SP-B PG64-22
TON 3,197.000 $89.000 $102.000 $88.000 $85.000 $81.000 $112.710 $110.000 $105.000 $119.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 606.250 $93.000 $121.000 $108.000 $135.000 $135.000 $122.210 $110.000 $110.000 $152.000
TACK COAT
GAL 1,028.150 $5.000 $1.500 $5.500 $6.000 $3.350 $4.070 $3.000 $8.000 $6.000
TRENCH EXCAVATION PROTECTION
LF 8.000 $3.000 $21.000 $150.000 $10.000 $22.000 $135.790 $5.000 $10.000 $25.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 14.000 $200.000 $180.000 $262.500 $190.000 $132.000 $203.690 $125.000 $285.000 $130.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 48.000 $900.000 $1,250.000 $735.000 $1,200.000 $775.000 $718.670 $700.000 $1,000.000 $800.000
RC PIPE (CL III)(18 IN)
LF 440.000 $60.000 $48.000 $52.500 $80.000 $60.000 $68.020 $50.000 $85.000 $60.000
RC PIPE (CL III)(24 IN)
LF 206.000 $65.000 $72.000 $73.500 $120.000 $120.000 $98.250 $65.000 $100.000 $122.000
RC PIPE (CL III)(30 IN)
LF 24.000 $115.000 $105.000 $105.000 $150.000 $160.000 $134.000 $85.000 $125.000 $160.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 6.000 $6,000.000 $9,500.000 $7,350.000 $5,900.000 $8,250.000 $10,521.810 $2,500.000 $12,500.000 $8,300.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 26.000 $750.000 $700.000 $400.000 $1,100.000 $1,000.000 $1,058.060 $600.000 $1,650.000 $1,000.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 4.000 $850.000 $718.000 $400.000 $1,000.000 $1,000.000 $1,597.480 $650.000 $2,000.000 $1,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 22.000 $1,000.000 $885.000 $425.000 $1,200.000 $1,100.000 $1,810.010 $1,000.000 $2,500.000 $1,200.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $1,960.000 $1,680.000 $1,500.000 $1,900.000 $2,750.000 $3,115.700 $1,500.000 $3,000.000 $2,800.000
CLEAN EXIST CULVERTS
EA 2.000 $2,685.000 $1,500.000 $4,725.000 $1,900.000 $2,200.000 $3,394.820 $1,000.000 $1,500.000 $2,500.000
REMOV STR (WINGWALL)
EA 2.000 $1,500.000 $1,800.000 $2,100.000 $1,900.000 $1,650.000 $1,318.880 $1,000.000 $2,500.000 $1,700.000
REMOV STR (HEADWALL)
EA 2.000 $965.000 $1,800.000 $1,050.000 $1,700.000 $1,650.000 $1,102.150 $1,000.000 $5,000.000 $1,700.000
REMOV STR (PIPE)
LF 514.000 $15.000 $20.000 $21.000 $15.000 $33.000 $14.770 $15.000 $30.000 $35.000
MOBILIZATION
LS 1.000 $119,799.000 $88,000.000 $142,800.000 $140,000.000 $150,000.000 $162,951.520 $150,000.000 $170,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $10,000.000 $5,500.000 $17,850.000 $14,500.000 $21,500.000 $10,554.490 $20,000.000 $8,500.000 $20,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 48.000 $30.000 $55.000 $31.500 $39.000 $28.000 $39.350 $50.000 $30.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 48.000 $10.000 $20.000 $17.500 $12.000 $12.000 $11.870 $15.000 $15.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 235.000 $20.000 $21.750 $21.000 $34.000 $23.000 $28.960 $30.000 $40.000 $21.000
CONSTRUCTION EXITS (REMOVE)
SY 235.000 $10.000 $10.000 $10.500 $9.000 $11.000 $10.650 $2.000 $20.000 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,216.000 $2.000 $2.250 $2.000 $3.000 $2.200 $3.310 $3.000 $4.000 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,216.000 $0.500 $1.000 $0.250 $1.000 $0.880 $0.980 $1.000 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 378.000 $3.250 $3.750 $5.000 $5.000 $4.000 $5.490 $8.000 $18.000 $4.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 378.000 $0.650 $1.000 $1.250 $1.000 $1.150 $1.470 $1.000 $12.000 $1.200
DRIVEWAYS (ACP)
SY 900.440 $45.000 $60.000 $38.550 $59.000 $50.000 $76.380 $55.000 $60.000 $90.000
DRIVEWAYS (CONC) (HES)
SY 804.200 $100.000 $105.000 $115.500 $99.000 $150.000 $135.830 $125.000 $125.000 $150.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 7.000 $200.000 $246.000 $246.750 $250.000 $430.000 $319.110 $500.000 $650.000 $270.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 15.000 $475.000 $495.000 $451.500 $520.000 $600.000 $583.910 $600.000 $650.000 $530.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 15.000 $600.000 $533.000 $603.750 $550.000 $735.000 $780.810 $700.000 $650.000 $580.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 8.000 $800.000 $861.000 $918.750 $890.000 $1,050.000 $1,188.190 $1,000.000 $650.000 $930.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $850.000 $810.000 $813.750 $850.000 $930.000 $1,052.400 $1,000.000 $650.000 $870.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $410.000 $431.000 $367.500 $450.000 $540.000 $475.280 $500.000 $450.000 $460.000
REMOVE SM RD SN SUP&AM
EA 37.000 $100.000 $72.000 $78.750 $75.000 $120.000 $101.840 $150.000 $150.000 $80.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 4.000 $60.000 $62.000 $47.250 $65.000 $65.000 $101.840 $100.000 $100.000 $70.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 283.000 $1.350 $1.250 $3.150 $2.000 $1.150 $1.890 $2.000 $5.000 $5.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,049.000 $4.000 $1.050 $1.420 $1.100 $1.000 $1.240 $1.100 $2.000 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 74.000 $10.000 $6.150 $10.500 $7.000 $7.750 $9.510 $6.600 $8.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 10.000 $200.000 $138.500 $138.600 $150.000 $135.000 $162.950 $150.000 $200.000 $133.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $215.000 $159.000 $164.850 $170.000 $155.000 $190.110 $170.000 $200.000 $155.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 12,610.000 $0.450 $0.410 $0.580 $0.450 $0.450 $0.540 $0.450 $1.000 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 575.000 $0.430 $1.050 $0.580 $1.100 $0.450 $0.540 $1.100 $2.000 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 13,359.000 $0.450 $0.410 $0.580 $0.450 $0.450 $0.540 $0.450 $1.000 $0.450
REFL PAV MRKR TY I-C
EA 104.000 $4.000 $6.150 $4.990 $7.000 $5.500 $6.790 $7.000 $8.000 $6.000
REFL PAV MRKR TY II-A-A
EA 859.000 $4.000 $3.690 $4.990 $4.000 $4.400 $5.430 $4.000 $8.000 $4.500
ELIM EXT PAV MRK & MRKS (4")
LF 19,460.000 $0.550 $0.500 $0.470 $0.500 $0.400 $0.480 $0.550 $1.000 $0.400
ELIM EXT PAV MRK & MRKS (24")
LF 36.000 $3.000 $5.150 $6.300 $5.500 $5.500 $6.790 $6.000 $6.000 $6.000
FULL - WIDTH MOWING
CYC 1.000 $2,900.000 $4,000.000 $315.000 $1,900.000 $1,000.000 $1,222.140 $3,000.000 $3,000.000 $6,000.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 76.000 $10.000 $15.000 $42.500 $19.000 $20.000 $2.400 $30.000 $20.000 $85.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $8,500.000 $6,300.000 $5,500.000 $8,500.000 $11,458.740 $20,000.000 $16,500.000 $14,000.000
TMA (STATIONARY)
DAY 198.000 $200.000 $260.000 $105.000 $60.000 $215.000 $271.590 $300.000 $300.000 $450.000
TMA (MOBILE OPERATION)
HR 240.000 $35.000 $16.000 $10.000 $45.000 $10.000 $67.900 $30.000 $85.000 $5.000
Totals: $1,295,144.778 $1,271,679.268 $1,414,206.425 $1,446,411.456 $1,546,088.142 $1,568,706.058 $1,607,827.400 $1,849,979.460 $1,993,111.649