KAUFMAN US 175 (0197-03-075)

Items: 24

County: KAUFMAN
Length: N/A
Highway: US 175
District: DALLAS
Control Number: 0197-03-075
DBE Goal: N/A
Project: NH 2017(922)
Guaranty: N/A
Time: 76 WORKING DAYS
Engineer's Estimate: $5,833,573.16
Date: 04/05/2017 (9 years ago)
Contract Number: N/A
Type: MILL, OVERLAY, BRIDGE JOINT REPAIR AND PVMT MRKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$5,833,573.16
$4,046,960.20
Over/Under Est: -30.63% -$1,786,612.96
Over/Under Est: -23.07% -$1,345,772.96
Amt Left: 10.89% $440,840.00
Over/Under Est: -22.22% -$1,296,231.61
Amt Left: 12.12% $490,381.35
Delta: -1.10% -$49,541.35
Over/Under Est: -20.22% -$1,179,433.38
Amt Left: 15% $607,179.58
Delta: -2.57% -$116,798.23
Over/Under Est: -18.2% -$1,061,502.16
Amt Left: 17.92% $725,110.80
Delta: -2.53% -$117,931.22
$5,663,073.00
Over/Under Est: -2.92% -$170,500.16
Amt Left: 39.93% $1,616,112.80
Delta: -18.67% -$891,002.00

Bid Items & Bid Tabulations

24 Total 0 of 24
KAUFMAN  |  US 175  |  DALLAS  |  0197-03-075  |  04/05/2017  |  $5,833,573.16  |  NH 2017(922)  |  MILL, OVERLAY, BRIDGE JOINT REPAIR A...  |  76 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
BIG CREEK CONSTRUCTION, LTD.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
OLDCASTLE MATERIALS TEXAS, INC.
PEACHTREE CONSTRUCTION, LTD.
FNH CONSTRUCTION, LLC
FOG SEAL (SS-1H OR CSS-1H)
GAL 14,947.000 $2.500 $2.700 $3.000 $2.400 $5.200 $5.200 $5.500
SUPERPAVE MIXTURES SP-D SAC-A PG70-22
TON 38,360.000 $81.400 $66.100 $80.000 $70.000 $84.000 $84.500 $82.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 1,000.000 $65.000 $101.700 $80.000 $68.000 $68.350 $105.000 $68.000
PLAN & TEXT ASPH CONC PAV (2")
SY 348,724.000 $3.350 $1.150 $1.500 $2.000 $1.500 $1.550 $3.000
PAV JT UNDERSEAL (24")
LF 5,548.000 $60.000 $23.150 $28.000 $35.000 $23.200 $12.500 $20.000
FULL - DEPTH REPAIR CPCD (9")
SY 110.000 $225.000 $434.500 $500.000 $375.000 $434.500 $650.000 $250.000
RESIZING AND SEALING JOINTS
LF 4,772.000 $32.000 $18.700 $25.000 $15.000 $18.700 $15.000 $28.000
MOBILIZATION
LS 1.000 $580,000.000 $400,000.000 $150,000.000 $356,388.250 $157,920.000 $280,000.000 $560,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $4,950.000 $5,000.000 $12,000.000 $17,500.000 $4,500.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,000.000 $2.700 $0.010 $3.000 $1.850 $1.960 $1.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,000.000 $0.650 $0.010 $0.500 $0.850 $0.660 $0.100 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,200.000 $3.900 $2.500 $5.000 $3.380 $2.540 $4.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,200.000 $1.500 $0.010 $1.000 $1.430 $0.400 $1.100 $8.000
RUMBLE STRIPS (SHOULDER)
LF 192,180.000 $0.450 $0.150 $0.200 $0.120 $0.150 $0.150 $0.250
CABLE BARRIER SYSTEM (TL-4) (20 '-0")
LF 4,800.000 $6.000 $18.500 $20.000 $30.000 $20.500 $20.000 $25.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 2.000 $2,200.000 $2,600.000 $3,000.000 $4,000.000 $2,880.000 $2,900.000 $2,850.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,004.000 $0.250 $0.400 $2.000 $1.000 $1.060 $2.000 $5.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 104,090.000 $0.460 $0.350 $0.260 $0.390 $0.280 $0.300 $0.450
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 111,090.000 $0.350 $0.300 $0.260 $0.340 $0.280 $0.300 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 105,090.000 $0.350 $0.300 $0.260 $0.340 $0.280 $0.300 $0.450
REFL PAV MRKR TY I-C
EA 1,301.000 $2.740 $3.500 $2.500 $3.100 $2.590 $3.200 $5.000
REFL PAV MRKR TY II-A-A
EA 3,004.000 $3.000 $3.500 $2.500 $3.100 $2.590 $3.000 $5.000
REFL PAV MRKR TY II-C-R
EA 1,301.000 $3.120 $3.500 $2.500 $3.100 $2.590 $3.200 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $16,500.000 $17,500.000 $5,000.000 $8,005.000 $8,660.000 $18,000.000 $16,500.000
Totals: $5,833,573.160 $4,046,960.200 $4,487,800.200 $4,537,341.550 $4,654,139.780 $4,772,071.000 $5,663,073.000