Show Job Controls
Bid Cobra

KARNES FM1354 (6311-81-001)

Items: 73

County: KARNES
Length: N/A
Highway: FM1354
District: CORPUS CHRISTI
Control Number: 6311-81-001
DBE Goal: N/A
Project: RMC - 631181001
Guaranty: N/A
Time: 112 W
Engineer's Estimate: $1,577,929.41
Date: 06/04/2019 (7 years ago)
Contract Number: N/A
Type: REHABILITATION OF AN EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,577,929.41
$1,657,477.60
Over/Under Est: 5.04% $79,548.19
Over/Under Est: 18.5% $291,948.07
Amt Left: 12.81% $212,399.88
Over/Under Est: 31.32% $494,258.87
Amt Left: 25.02% $414,710.68
Delta: -10.82% -$202,310.80
$2,090,649.23
Over/Under Est: 32.49% $512,719.82
Amt Left: 26.13% $433,171.63
Delta: -0.89% -$18,460.95
Over/Under Est: 40.98% $646,663.27
Amt Left: 34.22% $567,115.08
Delta: -6.41% -$133,943.45

Bid Items & Bid Tabulations

73 Total 0 of 73
KARNES  |  FM1354  |  CORPUS CHRISTI  |  6311-81-001  |  06/04/2019  |  $1,577,929.41  |  RMC - 631181001  |  REHAB OF AN EXIST ROADWAY  |  112 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TIERRA LEASE SERVICE, LLC
HUNTER INDUSTRIES, LTD.
DEAN WORD COMPANY, LTD.
RAY FARIS, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREPARING ROW
STA 113.000 $300.000 $100.000 $369.630 $611.421 $480.000 $255.380
EXCAVATION (ROADWAY)
CY 711.120 $11.500 $20.000 $18.930 $15.360 $15.750 $19.440
SUBGRADE WIDENING (ORD COMP)
STA 105.000 $350.000 $200.000 $875.790 $505.506 $933.870 $696.350
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 1,086.000 $11.000 $15.000 $16.650 $15.614 $13.500 $12.230
BACKFILL (TY A OR B)
STA 113.000 $350.000 $110.000 $379.620 $370.853 $146.250 $274.200
BLADING
HR 10.000 $100.000 $140.000 $91.200 $109.128 $90.000 $146.280
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 60,267.000 $0.300 $0.300 $0.350 $0.270 $0.320 $0.400
CELL FBR MLCH SEED(TEMP)(WARM)
SY 15,067.000 $0.250 $0.250 $0.300 $0.218 $0.290 $0.360
CELL FBR MLCH SEED(TEMP)(COOL)
SY 15,067.000 $0.250 $0.250 $0.300 $0.218 $0.290 $0.360
VEGETATIVE WATERING
MG 623.000 $15.000 $18.000 $23.310 $21.888 $12.000 $64.400
PROOF ROLLING
HR 10.000 $96.000 $80.000 $79.800 $65.800 $78.750 $72.920
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 1,357.000 $60.000 $67.500 $58.830 $63.553 $59.450 $69.580
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 5,605.000 $20.000 $25.750 $30.180 $32.454 $23.700 $33.590
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
CY 3,500.000 $55.000 $55.000 $58.840 $62.918 $61.700 $64.050
CEMENT
TON 444.000 $150.000 $160.000 $155.840 $147.290 $150.000 $174.820
CEM TRT (MX EXST MTL & NW BS)(DC)(6")
SY 37,334.000 $1.600 $1.250 $1.940 $2.173 $1.620 $2.400
ASPH (MULTI OPTION)
GAL 27,875.000 $3.200 $3.000 $3.800 $3.462 $3.560 $4.270
ASPH (RC-250)
GAL 7,535.000 $4.000 $3.750 $5.110 $4.222 $5.940 $4.450
AGGR(TY-B GR-5 SAC-B)
CY 280.000 $94.000 $115.000 $109.590 $87.232 $83.900 $140.160
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 378.000 $86.000 $94.000 $99.420 $90.334 $84.860 $123.050
AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B)
CY 444.000 $100.000 $88.500 $99.530 $93.326 $83.130 $148.130
CEM STABIL BKFL
CY 152.000 $80.000 $90.000 $180.000 $156.000 $150.000 $121.070
CUT & RESTORING PAV
SY 155.000 $65.000 $20.000 $80.000 $182.000 $175.000 $98.920
TRENCH EXCAVATION PROTECTION
LF 80.000 $12.000 $40.000 $10.000 $20.800 $20.000 $34.020
TEMPORARY SPL SHORING
SF 304.000 $15.000 $30.000 $5.000 $104.000 $100.000 $60.250
RIPRAP (CONC)(5 IN)
CY 9.100 $450.000 $600.000 $400.000 $624.000 $600.000 $654.020
CONC BOX CULV (5 FT X 3 FT)
LF 80.000 $235.000 $425.000 $340.000 $520.000 $500.000 $587.920
CONC BOX CULV (5 FT X 5 FT)
LF 120.000 $250.000 $475.000 $370.000 $676.000 $650.000 $646.410
CONC BOX CULV (6 FT X 3 FT)
LF 40.000 $285.000 $625.000 $440.000 $624.000 $600.000 $880.220
RC PIPE (CL III)(18 IN)
LF 475.000 $60.000 $84.000 $48.000 $58.240 $56.000 $73.990
RC PIPE (CL III)(24 IN)
LF 240.000 $70.000 $93.000 $84.000 $114.400 $110.000 $170.430
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 4.000 $6,250.000 $8,500.000 $3,800.000 $6,240.000 $6,000.000 $6,507.530
SET (TY I)(S= 5 FT)(HW= 6 FT)(3:1) (C)
EA 6.000 $6,500.000 $9,000.000 $5,800.000 $7,800.000 $7,500.000 $7,757.530
SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $6,500.000 $12,000.000 $4,800.000 $8,320.000 $8,000.000 $8,382.530
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 18.000 $700.000 $1,850.000 $1,500.000 $1,040.000 $1,000.000 $945.440
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 12.000 $1,400.000 $2,000.000 $1,550.000 $1,560.000 $1,500.000 $1,146.690
REMOV STR (PIPE)
LF 332.000 $15.000 $10.000 $12.000 $31.200 $30.000 $16.390
REMOVE STR (CONC)
EA 1.000 $4,500.000 $10,000.000 $7,500.000 $5,200.000 $5,000.000 $4,893.440
MOBILIZATION
LS 1.000 $141,720.130 $112,750.000 $166,841.280 $226,560.806 $229,972.340 $208,196.040
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,000.000 $2,500.000 $3,188.600 $6,861.738 $18,437.500 $4,639.510
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 200.000 $31.000 $30.000 $33.800 $35.152 $24.000 $37.690
ROCK FILTER DAMS (REMOVE)
LF 200.000 $8.000 $15.000 $7.240 $7.530 $7.000 $8.470
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $20.000 $25.000 $13.500 $14.040 $13.000 $15.310
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $7.000 $10.000 $5.860 $6.094 $2.000 $6.900
BACKHOE WORK (EROSION & SEDMT CONT)
HR 42.000 $80.000 $85.000 $85.500 $102.472 $60.000 $83.720
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,500.000 $3.100 $4.000 $2.500 $2.600 $3.000 $3.080
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,500.000 $0.550 $2.000 $0.500 $0.520 $1.000 $0.710
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 440.000 $5.000 $6.000 $6.000 $6.240 $5.250 $6.830
BIODEG EROSN CONT LOGS (REMOVE)
LF 440.000 $1.100 $2.000 $1.000 $1.040 $1.500 $1.330
CONSTRUCTING DETOURS
SY 981.000 $45.000 $27.000 $39.420 $29.646 $52.500 $59.710
CONC CURB (MOD) (TYPE I)
LF 258.000 $20.000 $40.000 $25.000 $41.600 $40.000 $28.820
DRIVEWAYS (SURF TREAT)
SY 1,032.000 $25.000 $18.750 $28.560 $24.872 $25.960 $36.180
TURNOUTS (SURF TREAT)
SY 275.000 $20.000 $25.000 $28.560 $24.624 $25.960 $52.620
WIRE FENCE (TY A)
LF 150.000 $15.000 $16.000 $10.000 $27.000 $18.000 $17.180
MAILBOX INSTALL-S (TWG-POST) TY 4
EA 7.000 $220.000 $500.000 $190.000 $197.600 $190.000 $257.670
MAILBOX INSTALL-D (TWG-POST) TY 4
EA 2.000 $300.000 $550.000 $225.000 $234.000 $225.000 $367.670
MAILBOX INSTALL-M (TWG-POST) TY 4
EA 2.000 $350.000 $650.000 $410.000 $426.400 $410.000 $421.960
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 42.000 $485.000 $525.000 $475.000 $494.000 $475.000 $576.190
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 12.000 $605.000 $650.000 $590.000 $613.600 $590.000 $774.670
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $850.000 $850.000 $755.000 $785.200 $755.000 $1,055.170
REMOVE SM RD SN SUP&AM
EA 29.000 $50.000 $55.000 $50.000 $52.000 $180.000 $120.520
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 18.000 $100.000 $75.000 $65.000 $67.600 $65.000 $88.150
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 22,600.000 $0.260 $0.520 $0.300 $0.312 $0.300 $0.680
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 568.000 $0.750 $1.000 $1.760 $1.970 $1.400 $1.510
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 22,600.000 $0.580 $0.750 $0.700 $0.728 $0.700 $0.900
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 22,600.000 $0.600 $0.750 $0.700 $0.728 $0.700 $0.900
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 12.000 $11.500 $30.000 $20.000 $20.800 $20.000 $35.980
REFL PAV MRKR TY II-A-A
EA 284.000 $2.600 $4.400 $4.000 $4.160 $4.000 $5.310
TREE TRIMMING / BRUSH REMOVAL
MI 2.140 $12,000.000 $7,500.000 $23,625.000 $17,327.794 $7,675.000 $8,737.580
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $4,000.000 $7,643.930 $9,720.000 $16,000.000 $11,428.730
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 160.000 $15.000 $30.000 $12.000 $12.480 $12.000 $17.140
TMA (STATIONARY)
EA 2.000 $7,500.000 $10,000.000 $7,643.930 $6,480.000 $18,000.000 $13,911.980
TMA (MOBILE OPERATION)
DAY 30.000 $150.000 $400.000 $356.720 $540.000 $40.000 $541.710
Totals: $1,577,929.410 $1,657,477.600 $1,869,877.482 $2,072,188.367 $2,090,649.230 $2,224,592.686