JOHNSON IH0035W (6399-85-001)

Items: 40

County: JOHNSON
Length: N/A
Highway: IH0035W
District: FORT WORTH
Control Number: 6399-85-001
DBE Goal: N/A
Project: RMC - 639985001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $2,027,287.44
Date: 06/29/2022 (3 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
JANET CRAWFORD
PETER D ROSS
BRYAN ANDERSON
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$2,027,287.44
$1,798,404.00
Over/Under Est: -11.29% -$228,883.44
$2,781,819.00
Over/Under Est: 37.22% $754,531.56
Amt Left: 54.68% $983,415.00
Over/Under Est: 59.64% $1,209,147.56
Amt Left: 79.96% $1,438,031.00
Delta: -16.34% -$454,616.00
$3,817,450.60
Over/Under Est: 88.3% $1,790,163.16
Amt Left: 112.27% $2,019,046.60
Delta: -17.95% -$581,015.60
Subcontractor Percentage Amount
JUNIOR CONSTRUCTION COMPANY, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

40 Total 0 of 40
JOHNSON  |  IH0035W  |  FORT WORTH  |  6399-85-001  |  06/29/2022  |  $2,027,287.44  |  RMC - 639985001  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SHORT-LINE CORPORATION
DIGG COMMERCIAL, LLC
SYNERGY SIGNS & SERVICES LLC
VANN/ELLI, INC.
RIPRAP (MOW STRIP)(4 IN)
CY 10.000 $476.040 $1,500.000 $1,200.000 $650.000 $890.000
MOBILIZATION (CALLOUT)
EA 24.000 $260.210 $1.000 $1.000 $1,500.000 $1,700.000
MOBILIZATION (EMERGENCY)
EA 6.000 $655.670 $1.000 $1.000 $3,000.000 $2,500.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,000.000 $23.450 $75.000 $40.000 $25.000 $36.000
TERMINAL ANCHOR SECTION
EA 4.000 $50.000 $1.000 $500.000 $1,600.000 $1,000.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 40.000 $1,800.000 $1,700.000 $100.000 $2,100.000 $2,500.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 1,000.000 $9.040 $25.000 $1.000 $12.500 $36.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 90.000 $1,000.000 $1,000.000 $945.000 $1,400.000 $1,534.000
REMOVE METAL BEAM GUARD FENCE
LF 14,000.000 $3.290 $1.000 $1.000 $2.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 20.000 $208.800 $500.000 $1.000 $200.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,055.560 $1,500.000 $2,355.000 $3,400.000 $3,900.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 10.000 $101.830 $1,000.000 $1.000 $500.000 $2,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $162.910 $1,000.000 $1.000 $200.000 $250.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 20,000.000 $11.640 $18.000 $15.000 $20.000 $25.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 30.000 $41.190 $40.000 $200.000 $60.000 $90.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 650.000 $36.360 $40.000 $37.000 $60.000 $76.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 1,000.000 $25.010 $25.000 $1.000 $50.000 $30.000
RAISE RAIL ELEMENT
LF 400.000 $7.000 $10.000 $75.000 $5.000 $20.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 3,200.000 $30.160 $30.000 $73.000 $45.000 $51.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 46.000 $44.790 $75.000 $300.000 $100.000 $153.600
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $119.570 $300.000 $600.000 $600.000 $450.000
REMOVE & REPLACE BLOCKOUT
EA 3,200.000 $24.770 $5.000 $0.500 $24.000 $35.000
REPLACE STL BLOCKOUTS W /WOOD BLOCKOUTS
EA 40.000 $1.000 $20.000 $100.000 $24.000 $35.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 600.000 $11.250 $20.000 $23.000 $35.000 $50.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 50.000 $49.220 $200.000 $200.000 $75.000 $96.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 200.000 $3,128.950 $2,600.000 $2,355.000 $3,500.000 $4,407.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 4.000 $228.570 $1,500.000 $3,000.000 $1,600.000 $1,300.000
REM & RESET SGT IMPACT HEAD
EA 40.000 $107.690 $50.000 $1.000 $250.000 $400.000
REPLACE POSTS (TL-4)
EA 2,400.000 $180.490 $100.000 $170.000 $350.000 $350.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 25.000 $221.390 $100.000 $1.000 $35.000 $475.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 20.000 $50.000 $1.000 $500.000 $150.000 $175.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 30.000 $1,636.360 $100.000 $2,390.000 $5,000.000 $5,685.000
REPLACE CABLE (TL-4)
LF 600.000 $2.770 $0.500 $9.000 $5.000 $38.000
CHECK / RE-TENSION CABLE
EA 30.000 $100.000 $500.000 $1.000 $500.000 $500.000
REPLACE POST HARDWARE (TL-4)
EA 2,400.000 $21.880 $25.000 $1.000 $75.000 $75.000
POST AND CABLE FENCE (REPAIR)
LF 25.000 $8.870 $100.000 $200.000 $50.000 $60.000
REMOVE AND REPLACE (TRACC)
EA 4.000 $5,000.000 $5,000.000 $10,000.000 $30,000.000 $27,500.000
REPAIR (TRACC)
EA 4.000 $5,000.000 $100.000 $1,500.000 $5,000.000 $13,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $49.170 $2,000.000 $1,000.000 $200.000 $150.000
TMA (STATIONARY)
DAY 200.000 $185.650 $1.000 $4,500.000 $200.000 $350.000
Totals: $2,027,287.440 $1,798,404.000 $2,781,819.000 $3,236,435.000 $3,817,450.600