PREPARING ROW
|
STA
|
524.000
|
$2,735.000
|
$2,500.000
|
$1,880.000
|
|
|
REMOVING CONC (MISC)
|
SY
|
156.000
|
$70.000
|
$45.000
|
$68.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
872.000
|
$15.000
|
$25.000
|
$32.000
|
|
|
REMOVING STAB BASE & ASPH PAV (12")
|
SY
|
119,839.000
|
$7.350
|
$4.900
|
$5.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
156,096.600
|
$6.000
|
$3.350
|
$4.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
64,255.400
|
$10.000
|
$7.900
|
$8.500
|
|
|
BACKFILL (TY A)
|
STA
|
524.000
|
$200.000
|
$325.000
|
$350.000
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
548,500.000
|
$0.420
|
$0.500
|
$0.500
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
548,500.000
|
$0.430
|
$0.450
|
$0.480
|
|
|
VEGETATIVE WATERING
|
MG
|
9,520.000
|
$15.000
|
$40.000
|
$30.000
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
2,096.000
|
$9.000
|
$1.000
|
$10.000
|
|
|
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
|
CY
|
37,264.000
|
$33.000
|
$45.000
|
$54.000
|
|
|
RWRK BS MTL(TY B)(12")(DC)(ORG POS)
|
CY
|
46,004.000
|
$3.000
|
$7.000
|
$10.000
|
|
|
RWRK BS MTL (TY B)(14")(DC)(ORG POS)
|
CY
|
27,059.000
|
$5.000
|
$12.000
|
$14.000
|
|
|
CEMENT
|
TON
|
7,107.000
|
$215.000
|
$200.000
|
$230.000
|
|
|
CEMENT TREAT (EXIST MATL)(12")
|
SY
|
340,122.000
|
$1.500
|
$2.850
|
$3.200
|
|
|
CEMENT TREAT (NEW BASE) (16")
|
SY
|
1,445.000
|
$8.000
|
$8.250
|
$9.000
|
|
|
CMT TRT(MX EXST MTL & NW BS)(12")(DC)
|
SY
|
329,548.000
|
$4.000
|
$3.050
|
$3.500
|
|
|
SALV, HAUL & STKPL RCL APH PV (6 TO 8")
|
SY
|
256,457.000
|
$3.800
|
$4.650
|
$5.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
66,204.000
|
$5.040
|
$5.000
|
$5.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
190.000
|
$1.980
|
$85.000
|
$60.000
|
|
|
STRUCT EXCAV
|
CY
|
18.000
|
$53.040
|
$38.000
|
$20.000
|
|
|
CEM STABIL BKFL
|
CY
|
1,384.000
|
$82.000
|
$150.000
|
$180.000
|
|
|
STRUCT EXCAV (SPECIAL)
|
CY
|
846.000
|
$79.500
|
$130.000
|
$100.000
|
|
|
SAND BACKFILL
|
CY
|
1.630
|
$60.000
|
$30.000
|
$200.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
404.000
|
$15.000
|
$18.000
|
$4.000
|
|
|
CL A CONC (COLLAR)
|
EA
|
3.000
|
$1,550.000
|
$1,800.000
|
$800.000
|
|
|
CL C CONC (RAC-R)
|
CY
|
8.000
|
$1,120.000
|
$2,400.000
|
$3,000.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
1,322.000
|
$445.000
|
$600.000
|
$550.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
1.630
|
$600.000
|
$610.000
|
$600.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
56.000
|
$490.000
|
$610.000
|
$550.000
|
|
|
RAIL (TY T223)
|
LF
|
80.000
|
$230.000
|
$375.000
|
$400.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
2,364.000
|
$424.000
|
$485.000
|
$500.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
920.000
|
$100.000
|
$88.000
|
$80.000
|
|
|
RC PIPE (CL IV) (24 IN) (SPL)
|
LF
|
800.000
|
$68.590
|
$155.000
|
$160.000
|
|
|
WINGWALL (FW - 0) (HW=3 FT)
|
EA
|
32.000
|
$12,895.000
|
$9,000.000
|
$6,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
50.000
|
$1,224.220
|
$2,000.000
|
$1,600.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
5.000
|
$1,900.000
|
$2,200.000
|
$2,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (5: 1) (C)
|
EA
|
10.000
|
$2,426.300
|
$2,200.000
|
$2,000.000
|
|
|
REMOV STR (SET)
|
EA
|
2.000
|
$468.200
|
$1,800.000
|
$650.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
32.000
|
$1,820.000
|
$1,500.000
|
$2,500.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
8.000
|
$2,000.000
|
$1,500.000
|
$1,300.000
|
|
|
REMOV STR (PIPE)
|
LF
|
540.000
|
$13.350
|
$20.000
|
$16.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
1,373.000
|
$42.350
|
$55.000
|
$49.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$3,136,339.520
|
$2,540,000.000
|
$3,600,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
74.000
|
$6,500.000
|
$4,500.000
|
$1,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
150.000
|
$70.000
|
$75.000
|
$82.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
150.000
|
$12.500
|
$35.000
|
$38.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 2)
|
SY
|
936.000
|
$26.000
|
$22.000
|
$68.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
936.000
|
$7.980
|
$12.000
|
$16.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
9,240.000
|
$4.100
|
$5.500
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
9,240.000
|
$0.860
|
$1.500
|
$1.400
|
|
|
CONSTRUCTING DETOURS
|
SY
|
70,188.000
|
$45.000
|
$48.000
|
$54.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
1.000
|
$6,150.000
|
$10,500.000
|
$9,500.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
17,310.000
|
$33.500
|
$22.000
|
$26.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
85,540.000
|
$3.500
|
$3.750
|
$4.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
17,310.000
|
$6.750
|
$16.000
|
$17.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
3,244.000
|
$41.500
|
$45.000
|
$50.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
475.000
|
$29.210
|
$27.000
|
$28.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,200.000
|
$2,300.000
|
$2,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
475.000
|
$3.500
|
$3.000
|
$3.300
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$250.000
|
$196.000
|
$280.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,289.000
|
$3,600.000
|
$3,200.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$278.960
|
$196.000
|
$436.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
84.000
|
$1,200.000
|
$1,525.000
|
$1,800.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
12.000
|
$750.000
|
$550.000
|
$870.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
12.000
|
$9,633.330
|
$9,300.000
|
$8,800.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
106.500
|
$31.600
|
$30.000
|
$25.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
29.000
|
$808.630
|
$700.000
|
$720.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
26.000
|
$850.000
|
$900.000
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
7.000
|
$1,150.000
|
$1,100.000
|
$120.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
37.000
|
$125.000
|
$140.000
|
$110.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
47.000
|
$15.000
|
$140.000
|
$20.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
48.000
|
$89.830
|
$50.000
|
$66.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
110,330.000
|
$0.500
|
$0.520
|
$0.600
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
105,320.000
|
$0.500
|
$0.520
|
$0.600
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
6,856.000
|
$4.500
|
$4.000
|
$4.500
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
169,355.000
|
$0.550
|
$0.300
|
$0.300
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
82.000
|
$1.100
|
$0.500
|
$0.500
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
140.000
|
$10.000
|
$16.000
|
$17.000
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
1.000
|
$150.000
|
$200.000
|
$220.000
|
|
|
WK ZN PAV MRK REMOV (W)(WORD)
|
EA
|
1.000
|
$205.000
|
$300.000
|
$330.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(BRK)
|
LF
|
220.000
|
$0.620
|
$0.360
|
$0.400
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
177,664.000
|
$0.450
|
$0.300
|
$0.400
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
5,403.000
|
$1.000
|
$1.700
|
$2.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
5,345.000
|
$1.000
|
$1.700
|
$2.000
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
685.000
|
$2.500
|
$0.700
|
$0.700
|
|
REFL PAV MRK TY I (W)6"(LNDP)(100MIL)
|
LF
|
1,515.000
|
$1.200
|
$0.700
|
$0.700
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
98.000
|
$1.650
|
$0.900
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
55.000
|
$11.000
|
$20.000
|
$21.000
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
9,070.000
|
$0.680
|
$0.750
|
$0.800
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
5,569.000
|
$0.800
|
$0.750
|
$0.800
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
72,697.000
|
$0.650
|
$0.750
|
$0.800
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
112,848.000
|
$0.790
|
$0.900
|
$1.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
1.000
|
$250.000
|
$200.000
|
$220.000
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
12.000
|
$562.000
|
$450.000
|
$490.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
1.000
|
$274.260
|
$305.000
|
$330.000
|
|
PREFAB PAV MRK TY C(EVAC SYM, BLUE/WHT)
|
EA
|
2.000
|
$850.680
|
$755.000
|
$820.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
458.000
|
$4.500
|
$5.000
|
$5.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,515.000
|
$3.980
|
$5.000
|
$5.500
|
|
TRAFFIC BUTTON TY Y
|
EA
|
14,580.000
|
$2.200
|
$3.000
|
$3.000
|
|
TRAFFIC BUTTON TY B
|
EA
|
8,036.000
|
$2.200
|
$3.000
|
$3.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
143,196.000
|
$0.450
|
$0.600
|
$0.600
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
1,350.000
|
$0.150
|
$0.100
|
$0.100
|
|
|
SP MIXES SP-B SAC-B PG76-22
|
TON
|
45,524.000
|
$140.000
|
$126.000
|
$127.000
|
|
|
SP MIXES SP-C SAC-A PG76-22
|
TON
|
36,419.000
|
$150.000
|
$158.000
|
$156.000
|
|
|
BONDING COURSE
|
GAL
|
22,363.000
|
$4.650
|
$5.500
|
$5.500
|
|
|
BIRD EXCLUSION METHOD
|
SF
|
5,673.000
|
$3.000
|
$14.000
|
$15.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$8,000.000
|
$32,000.000
|
$29,000.000
|
|
MULTIPOLYMER PAV MRK (W)(6")(SLD)
|
LF
|
270.000
|
$2.000
|
$25.000
|
$22.000
|
|
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
|
LF
|
270.000
|
$2.700
|
$25.000
|
$22.000
|
|
|
TMA (STATIONARY)
|
DAY
|
1,140.000
|
$85.000
|
$25.000
|
$170.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
50.000
|
$150.000
|
$600.000
|
$600.000
|
|
Totals: |
$34,499,734.730
|
$34,775,852.970
|
$37,213,248.500
|