JASPER FM 2799 (0244-09-014)

Items: 61

County: JASPER
Length: 1.7800 MILES
Highway: FM 2799
District: BEAUMONT
Control Number: 0244-09-014
DBE Goal: 0.0%
Project: F 2026(161)
Guaranty: $60,000.00
Time: 42 WORKING DAYS
Engineer's Estimate: $1,483,639.82
Date: 12/02/2025 (6 months ago)
Contract Number: 12253029
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00196657
Contract Type: Federal
Project Description: FM 2799(FM 777, EAST TO US 96) MILL AND OVERLAY WITH SAFETY UPGRADES
Mail/Deliver Bids To: N/A
JIM GRISSOM
BRYCE BROUSSARD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$1,483,639.82
$1,374,925.71
Over/Under Est: -7.33% -$108,714.11
Over/Under Est: 8.71% $129,281.69
Amt Left: 17.31% $237,995.80

Bid Items & Bid Tabulations

61 Total 0 of 61
JASPER  |  FM 2799  |  BEAUMONT  |  0244-09-014  |  12/02/2025  |  $1,483,639.82  |  F 2026(161)  |  SURF/ROADWAY RESTOR  |  42 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
REMOV CONC (MOWSTRIP)
CY 23.000 $100.000 $122.000 $75.000
BACKFILL (TY A OR B)
STA 39.000 $185.000 $756.670 $600.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 5,001.000 $2.700 $0.240 $0.230
VEGETATIVE WATERING
TGL 28.000 $28.790 $302.050 $9.000
SP MIXES SP-C SAC-A PG76-22
TON 5,563.000 $150.000 $152.500 $163.000
TACK COAT
GAL 3,034.000 $5.000 $6.700 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 210.000 $100.000 $182.030 $115.000
PLANE ASPH CONC PAV(0" TO 2")
SY 2,951.000 $4.250 $2.150 $3.250
PLANE ASPH CONC PAV(2")
SY 32,512.000 $2.300 $2.150 $3.250
FULL-DEPTH REPAIR CRCP (8"-10")
SY 100.000 $450.000 $170.800 $450.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 16.000 $250.000 $244.000 $230.000
RIPRAP (MOW STRIP)(4 IN)
CY 22.000 $660.000 $488.000 $700.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 90.000 $45.500 $87.580 $40.000
HEADER TYPE EXPANSION JOINT
LF 138.000 $150.000 $27.320 $100.000
ADJUSTING MANHOLES
EA 11.000 $2,750.000 $1,220.000 $3,500.000
MOBILIZATION
LS 1.000 $100,000.000 $68,746.310 $160,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $1,980.980 $4,000.000
TMA (STATIONARY)
DAY 45.000 $205.000 $135.370 $75.000
TMA (MOBILE OPERATION)
DAY 10.000 $200.000 $365.480 $75.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 52.000 $1.000 $12.200 $15.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 52.000 $1.000 $6.100 $12.000
INTERSECTIONS (ACP)
SY 165.000 $40.000 $22.190 $85.000
DRIVEWAYS (ACP)
SY 1,350.000 $40.000 $24.330 $40.000
DRIVEWAYS (BASE)
SY 324.000 $35.000 $32.370 $40.000
TURNOUTS (ACP)
SY 195.000 $140.000 $78.630 $175.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 7,802.000 $0.250 $0.920 $0.260
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 3,901.000 $0.250 $0.920 $0.260
MTL W-BEAM GD FEN (TIM POST)
LF 300.000 $140.000 $32.330 $27.000
MTL THRIE-BEAM GD FEN (TIM POST)
EA 4.000 $2,240.000 $2,318.000 $2,200.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $3.000 $3.050 $2.750
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $300.000 $305.000 $275.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,450.000 $3,599.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $300.000 $305.000 $275.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 2.000 $700.000 $725.900 $511.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 2.000 $330.000 $305.000 $300.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 22.000 $600.000 $671.000 $583.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $900.000 $780.800 $660.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 6.000 $800.000 $793.000 $603.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $800.000 $793.000 $703.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,100.000 $1,323.700 $975.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,250.000 $1,323.700 $1,050.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,270.000 $1,323.700 $1,020.000
REMOVE SM RD SN SUP&AM
EA 36.000 $110.000 $115.900 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 4.000 $25.000 $18.300 $33.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $35.000 $43.920 $30.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 169.000 $0.300 $9.150 $1.500
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 13.000 $0.500 $9.150 $2.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 465.000 $0.300 $9.150 $1.450
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 396.000 $3.000 $1.030 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,148.000 $3.000 $2.060 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 810.000 $1.000 $1.530 $1.000
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 1,820.000 $0.800 $1.100 $0.850
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 9,361.000 $1.000 $1.100 $0.800
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 180.000 $0.800 $1.100 $0.850
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 20,024.000 $0.800 $1.100 $0.800
PRFB RUMBLE STRIP (BLK)(4')(TRANSVERSE)
LF 80.000 $25.000 $30.500 $12.000
PREFAB PM TY C (W)(24")(SLD)
LF 502.000 $20.000 $9.760 $18.000
PREFAB PM TY C (W)(ARROW)
EA 15.000 $240.000 $244.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $800.000 $292.800 $370.000
REFL PAV MRKR TY I-C
EA 159.000 $6.000 $6.100 $7.000
REFL PAV MRKR TY II-A-A
EA 1,004.000 $6.000 $6.100 $6.000
Totals: $1,483,639.820 $1,374,925.710 $1,612,921.510