Show Job Controls
Bid Cobra

JACKSON SH 172 (0420-01-047)

Items: 80

County: JACKSON
Length: N/A
Highway: SH 172
District: YOAKUM
Control Number: 0420-01-047
DBE Goal: N/A
Project: F 2024(117)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $11,854,606.45
Date: 10/06/2023 (2 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
CLAYTON HARRIS
JAMES JANAK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$11,854,606.45
$12,691,410.84
Over/Under Est: 7.06% $836,804.39
Over/Under Est: 11.85% $1,404,881.42
Amt Left: 4.48% $568,077.03
Subcontractor Percentage Amount
INTERSTATE BARRICADES & MARKINGS, INC. 4.03% $523,623.98
JB PINNACLE GROUP, LLC 1.82% $236,475.35
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 1.10% $142,924.66
HIGHWAY BARRICADES AND SERVICES, LLC 0.45% $58,469.18
MURRAY CONSTRUCTION 0.35% $45,476.03
PROFESSIONAL TRAFFIC CONTROL LLC 0.33% $42,877.40
A K FUQUAY CONSTRUCTION 0.15% $19,489.73
Total: 8.23% $1,069,336.33

Bid Items & Bid Tabulations

80 Total 0 of 80
JACKSON  |  SH 172  |  YOAKUM  |  0420-01-047  |  10/06/2023  |  $11,854,606.45  |  F 2024(117)  |  SURF/ROADWAY RESTOR  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
JAMES CONSTRUCTION GROUP, LLC
REMOVING CONC (PAV)
SY 3,067.000 $18.500 $14.000 $22.500
EXCAVATION (ROADWAY)
CY 2,652.000 $9.250 $14.000 $44.000
BACKFILL (TY B)
STA 752.360 $250.000 $156.400 $290.000
BLADING
HR 50.000 $150.000 $120.000 $110.000
FL BS (CMP IN PLC)(TY E GR 5)(FNL POS)
CY 1,547.000 $100.000 $117.610 $210.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 37.000 $275.000 $275.000 $391.000
LIME TRT (EXST MATL)(8")
SY 3,834.000 $4.000 $4.800 $20.000
CEMENT
TON 47.000 $300.000 $275.000 $268.000
CEMENT TREAT(EXIST MATL)(8")
SY 3,834.000 $4.000 $4.800 $9.750
PRIME COAT (MC-30)
GAL 1,533.000 $6.000 $7.900 $6.550
AGGR(TY-PE GR-3 SAC-B)
CY 90.000 $150.000 $213.330 $731.000
AGGR(TY-PE GR-4 SAC-B)
CY 3,765.000 $120.000 $146.160 $145.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 169,502.000 $4.900 $4.410 $4.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 3,000.000 $75.000 $66.440 $75.000
PLANE ASPH CONC PAV(0" TO 2")
SY 153,960.000 $2.100 $2.130 $1.850
PLANE ASPH CONC PAV (2" TO 6")
SY 7,667.000 $3.500 $4.330 $9.150
RETROFIT RAIL (TY SSTR)
LF 1,246.000 $300.000 $225.000 $164.000
MOBILIZATION
LS 1.000 $985,000.000 $1,263,898.190 $783,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $3,000.000 $3,930.810 $12,000.000
CONSTRUCTION PERIMETER FENCE
LF 2,000.000 $5.000 $5.500 $5.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $5.000 $4.500 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $1.250 $0.500 $0.500
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 500.000 $6.000 $6.250 $6.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $3.000 $1.000 $1.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 1,200.000 $35.000 $20.000 $37.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 740.000 $35.000 $25.000 $41.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $30.000 $90.000 $116.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 1,200.000 $10.000 $20.000 $2.500
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 2,120.000 $6.000 $20.000 $21.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 120.000 $6.000 $90.000 $169.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 1,200.000 $10.000 $12.000 $19.250
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 740.000 $15.000 $15.000 $12.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $15.000 $75.000 $57.000
RUMBLE STRIPS (SHOULDER)
LF 217,628.000 $0.300 $0.140 $0.370
RUMBLE STRIPS (CENTERLINE)
LF 108,814.000 $0.300 $0.180 $0.300
MTL W-BEAM GD FEN (TIM POST)
LF 1,684.340 $30.000 $28.840 $24.150
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,750.000 $2,670.750 $1,755.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 215.660 $90.000 $78.640 $75.000
REMOVE METAL BEAM GUARD FENCE
LF 1,350.000 $2.500 $3.150 $2.200
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $300.000 $262.150 $180.000
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $3,300.000 $3,360.720 $3,125.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $300.000 $486.540 $200.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $3,000.000 $1,677.740 $2,800.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $550.000 $823.140 $2,100.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $9,000.000 $8,776.670 $11,350.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 106.000 $25.000 $22.090 $21.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 58.000 $35.000 $33.140 $25.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 540,268.000 $0.500 $0.250 $0.250
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 1,384.000 $0.700 $0.350 $0.350
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 5,424.000 $0.700 $0.350 $0.350
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 320.000 $5.000 $2.500 $2.500
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 62,573.000 $0.500 $0.250 $0.250
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 76,349.000 $0.500 $0.250 $0.250
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 17,200.000 $0.500 $1.750 $1.750
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 26,290.000 $0.500 $1.750 $1.750
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,792.000 $1.500 $1.630 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 19,570.000 $1.500 $1.630 $1.500
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 457.000 $1.900 $1.500 $1.500
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,712.000 $1.350 $0.950 $0.950
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 160.000 $7.000 $4.000 $4.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 518.000 $17.000 $8.000 $8.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $230.000 $200.000 $200.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $275.000 $250.000 $250.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 3.000 $800.000 $550.000 $550.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 20.000 $50.000 $25.000 $25.000
PREFAB PAV MRK TY C (Y) (12") (SLD)
LF 254.000 $10.000 $4.000 $4.000
REFL PAV MRKR TY I-C
EA 146.000 $6.500 $5.000 $5.000
REFL PAV MRKR TY II-A-A
EA 1,954.000 $6.500 $5.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 16,270.000 $0.500 $1.500 $1.500
D-GR HMA TY-B SAC-B PG64-22
TON 2,427.000 $130.000 $121.400 $127.000
D-GR HMA TY-D SAC-B PG70-22
TON 59,664.000 $110.000 $124.100 $131.000
TACK COAT
GAL 1,533.000 $3.750 $4.090 $2.400
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $9,000.000 $7,682.700 $12,000.000
LONG CHANNEL MOUNT CURB SYS (INSTALL)
LF 600.000 $80.000 $75.310 $75.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 240.000 $15.000 $25.000 $25.000
TMA (STATIONARY)
DAY 20.000 $250.000 $512.180 $657.000
TMA (MOBILE OPERATION)
DAY 20.000 $325.000 $1,024.360 $3,000.000
HPPM-RIB W/RET REQ TYI(W)6"(SLD)090MIL
LF 233,952.000 $0.850 $0.750 $0.750
HPPM-RIB W/RET REQ TYI(Y)6"(BRK)090MIL
LF 27,158.000 $0.850 $0.750 $0.750
HPPM-RIB W/RET REQ TYI(Y)6"(SLD)090MIL
LF 31,026.000 $0.850 $0.750 $0.750
Totals: $11,854,606.450 $12,691,410.852 $13,259,487.871