JACKSON SH 111 (0346-02-016)

Items: 29

County: JACKSON
Length: N/A
Highway: SH 111
District: YOAKUM
Control Number: 0346-02-016
DBE Goal: N/A
Project: STP 1902(023)HES
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $1,212,240.50
Date: 06/05/2019 (7 years ago)
Contract Number: N/A
Type: INCREASE SUPERELEVATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,212,240.50
$1,235,556.27
Over/Under Est: 1.92% $23,315.77
Over/Under Est: 12.78% $154,912.75
Amt Left: 10.65% $131,596.98
Over/Under Est: 47.76% $578,907.81
Amt Left: 44.97% $555,592.04
Delta: -31.01% -$423,995.06

Bid Items & Bid Tabulations

29 Total 0 of 29
JACKSON  |  SH 111  |  YOAKUM  |  0346-02-016  |  06/05/2019  |  $1,212,240.50  |  STP 1902(023)HES  |  INCREASE SUPERELEVATION  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
JAMES CONSTRUCTION GROUP, L.L.C.
REXCO CONSTRUCTION SERVICES, INC.
BACKFILL (TY B)
STA 158.400 $125.000 $117.450 $200.000 $470.200
BLADING
HR 20.000 $100.000 $108.300 $100.000 $100.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 160.000 $90.000 $135.190 $340.000 $174.350
AGGR(TY-PE GR-4 SAC-B)
CY 554.000 $100.000 $100.840 $180.000 $199.310
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 24,443.000 $3.500 $3.950 $3.250 $6.260
D-GR HMA TY-D SAC-B PG64-22
TON 845.000 $87.500 $97.200 $108.000 $136.920
D-GR HMA TY-D SAC-B PG70-22
TON 6,040.000 $87.500 $92.280 $96.750 $116.700
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,000.000 $75.000 $61.320 $71.000 $53.480
PLANE ASPH CONC PAV(0" TO 3")
SY 30,819.000 $2.500 $1.570 $2.500 $2.440
CLEANING AND SEALING EXISTING JOINTS
LF 336.000 $15.000 $39.480 $8.000 $55.680
RETROFIT RAIL (TY T631)
LF 418.000 $77.000 $70.000 $70.000 $103.680
MOBILIZATION
LS 1.000 $100,000.000 $136,960.230 $120,000.000 $222,766.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $1,174.240 $1,900.000 $3,620.000
RUMBLE STRIPS (SHOULDER)
LF 31,680.000 $0.500 $0.160 $0.340 $0.330
RUMBLE STRIPS (CENTERLINE)
LF 15,840.000 $0.500 $0.200 $0.410 $0.560
MTL W-BEAM GD FEN (TIM POST)
LF 1,407.000 $25.000 $22.000 $22.000 $32.450
REMOVE METAL BEAM GUARD FENCE
LF 1,400.000 $2.000 $2.000 $2.000 $5.400
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $175.000 $200.000 $200.000 $216.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,500.000 $2,400.000 $2,400.000 $3,234.600
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $200.500 $200.000 $200.000 $432.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 44.000 $25.000 $10.000 $10.000 $50.220
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 31,680.000 $0.250 $0.180 $0.180 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 3,960.000 $0.250 $0.200 $0.200 $0.270
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 792.000 $2.000 $1.760 $0.450 $5.200
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 31,680.000 $0.400 $0.420 $0.420 $0.490
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 3,960.000 $0.400 $0.450 $0.450 $0.540
REFL PAV MRKR TY II-A-A
EA 198.000 $4.000 $5.000 $5.000 $5.400
TMA (STATIONARY)
EA 2.000 $8,000.000 $7,615.900 $7,000.000 $12,000.000
TMA (MOBILE OPERATION)
DAY 20.000 $500.000 $304.640 $470.000 $1,000.000
Totals: $1,212,240.500 $1,235,556.270 $1,367,153.250 $1,791,148.310