Bid Cobra

JACKSON SH 35 (0179-09-041)

Items: 76

County: JACKSON
Project: BR 2026(242)
Highway: SH 35
District: YOAKUM
Date: 12/02/2025 (6 months ago)
Time: 319 WORKING DAYS
Engineer's Estimate: $17,962,824.25
Type: BRIDGE REPLACEMENT
Control Number: 0179-09-041
Sequence Number: 3009
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$17,962,824.25
1
Rejected
$21,288,201.98
Over/Under Est: 18.51% $3,325,377.73
Over/Under Est: 32.2% $5,783,592.30
Amt Left: 11.55% $2,458,214.57
$26,862,178.12
Over/Under Est: 49.54% $8,899,353.87
Amt Left: 26.18% $5,573,976.14
Delta: -13.12% -$3,115,761.57
$27,298,997.91
Over/Under Est: 51.97% $9,336,173.66
Amt Left: 28.24% $6,010,795.93
Delta: -1.63% -$436,819.79
$33,412,147.18
Over/Under Est: 86.01% $15,449,322.93
Amt Left: 56.95% $12,123,945.20
Delta: -22.39% -$6,113,149.27
$34,823,497.97
Over/Under Est: 93.86% $16,860,673.72
Amt Left: 63.58% $13,535,295.99
Delta: -4.22% -$1,411,350.79

Bid Items & Bid Tabulations

76 Total 0 of 76
JACKSON  |  SH 35  |  YOAKUM  |  0179-09-041  |  12/02/2025  |  $17,962,824.25  |  BR 2026(242)  |  BRIDGE REPL  |  319 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COPASA INC
RAGLE CONSTRUCTION, INC.
HUNTER INDUSTRIES, LTD.
ORION CONSTRUCTION, LLC
MCMILLEN, INC.
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 66.400 $4,000.000 $32,059.367 $50,000.000 $40,163.540 $40,000.000 $25,000.000 $51,920.916
REMOV CONC (RIPRAP)
SY 1,832.000 $25.000 $30.000 $10.000 $29.700 $12.000 $75.000 $24.811
REMOV CONC (DRIVEWAYS)
SY 137.000 $20.000 $24.000 $25.000 $29.700 $12.000 $60.000 $24.811
OBLITERATING ABANDONED ROAD
SY 11,045.000 $15.000 $8.940 $6.800 $12.100 $1.900 $9.000 $47.334
EXCAV (ROADWAY)
CY 21,426.000 $18.000 $12.910 $18.000 $27.500 $11.000 $15.000 $30.494
EMBANK (FNL)(OC)(TY C)
CY 17,402.000 $23.000 $14.210 $85.000 $33.000 $8.000 $40.000 $50.509
BLADING
HR 28.000 $120.000 $500.000 $130.000 $132.000 $550.000 $220.000 $126.988
BROADCAST SEED (PERM_RURAL_CLAY)
SY 46,925.000 $0.750 $0.210 $0.450 $0.230 $0.240 $0.300 $0.211
BROADCAST SEED (TEMP_WARM)
SY 11,731.000 $0.750 $0.360 $0.350 $0.400 $0.380 $0.520 $0.362
BROADCAST SEED (TEMP_COOL)
SY 11,731.000 $0.750 $0.370 $0.350 $0.410 $0.380 $0.530 $0.372
VEGETATIVE WATERING
TGL 396.000 $50.000 $47.680 $30.000 $25.300 $48.000 $68.680 $48.050
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 3,404.000 $125.000 $132.090 $135.000 $106.420 $135.000 $149.510 $57.079
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 292.000 $330.000 $360.000 $360.000 $346.500 $375.000 $565.430 $361.726
LIME TRT (EXIST MATL & NEW BASE)(8")
SY 16,231.000 $4.000 $8.000 $3.900 $2.910 $3.250 $6.810 $12.294
ASPH (RC-250)
GAL 3,063.000 $5.000 $6.000 $5.200 $5.170 $7.000 $20.000 $5.744
AGGR (TY-E, GR-5)(SAC-B)
CY 109.000 $725.000 $590.000 $280.000 $173.600 $210.000 $400.000 $302.329
AGGR (TY-PE, GR-4)(SAC-B)
CY 181.000 $725.000 $350.000 $280.000 $174.240 $140.000 $400.000 $256.979
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 6,127.000 $5.000 $8.000 $8.000 $3.910 $5.000 $20.000 $5.290
D-GR HMA TY-B PG64-22
TON 2,426.000 $115.000 $130.000 $195.000 $119.900 $220.000 $250.000 $149.058
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 81.000 $150.000 $158.000 $245.000 $145.200 $325.000 $350.000 $100.524
D-GR HMA TY-D SAC-B PG76-22
TON 2,865.000 $120.000 $160.000 $225.000 $132.000 $250.000 $250.000 $141.721
TACK COAT
GAL 2,910.000 $3.500 $4.750 $5.200 $3.080 $8.000 $15.000 $3.325
CEM STABIL BKFL
CY 252.000 $215.000 $198.000 $175.000 $200.000 $400.000 $300.000 $169.566
TEMPORARY SPL SHORING
SF 3,378.000 $30.000 $60.000 $60.000 $66.000 $1.000 $78.530 $51.960
PRESTR CONC PIL (18 IN SQ)
LF 176.000 $200.000 $199.010 $150.000 $350.000 $280.000 $600.000 $276.550
PRESTR CONC PIL (24 IN SQ)
LF 14,492.000 $245.000 $262.910 $175.000 $360.000 $290.000 $454.260 $673.377
CL B CONC (FLUME)
CY 11.600 $1,100.000 $1,996.820 $715.000 $900.000 $1,750.000 $1,000.000 $342.770
CL C CONC (ABUT)
CY 56.800 $1,600.000 $1,639.920 $1,200.000 $3,000.000 $2,250.000 $2,500.000 $11,119.953
CL C CONC (CAP)
CY 644.800 $1,500.000 $2,307.190 $1,100.000 $3,000.000 $2,250.000 $3,500.000 $1,768.060
REINF CONC SLAB
SF 117,760.000 $20.000 $23.750 $24.000 $36.000 $33.000 $48.000 $52.907
APPROACH SLAB
CY 70.600 $875.000 $1,086.500 $625.000 $1,000.000 $1,050.000 $1,000.000 $3,024.267
PRESTR CONC GIRDER (TX34)
LF 15,264.000 $205.000 $175.150 $192.000 $247.000 $353.500 $325.000 $188.824
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,988.000 $120.000 $200.000 $225.000 $320.000 $235.000 $225.000 $277.961
RAIL (TY SSTR)
LF 5,172.000 $140.000 $72.980 $63.000 $120.000 $80.000 $92.000 $112.446
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 516.000 $250.000 $237.500 $205.000 $250.000 $400.000 $265.230 $172.327
RC PIPE (CL III)(18 IN)
LF 310.000 $125.000 $90.000 $80.000 $74.710 $125.000 $183.340 $453.483
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 12.000 $1,500.000 $2,500.000 $1,380.000 $3,923.540 $3,200.000 $1,679.510 $1,726.752
REMOV STR (BRIDGE 1000 FT OR GREATER)
EA 1.000 $1,500,000.000 $1,733,054.280 $1,100,000.000 $600,000.000 $2,000,000.000 $300,000.000 $1,201,829.089
REMOV STR (SMALL)
EA 7.000 $1,600.000 $1,101.530 $620.000 $1,710.700 $2,400.000 $1,460.620 $1,267.413
MOBILIZATION
LS 1.000 $1,620,000.000 $2,128,742.011 $2,300,000.000 $2,670,088.840 $2,700,000.000 $3,348,000.000 $3,464,960.706
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $9,000.000 $15,416.237 $104,000.000 $27,855.000 $20,000.000 $50,000.000 $12,093.160
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $8,500.000 $45,500.000 $11,272.460 $29,715.000 $42,000.000 $18,083.306
TMA (STATIONARY)
DAY 20.000 $500.000 $550.000 $450.000 $394.540 $800.000 $300.000 $122.433
TMA (MOBILE OPERATION)
DAY 20.000 $300.000 $550.000 $750.000 $845.430 $1,300.000 $1,200.000 $113.373
ROCK FILTER DAMS (INSTALL) (TY 1)
CY 13.000 $45.000 $374.620 $45.000 $412.080 $55.000 $500.000 $377.528
SANDBAGS FOR EROSION CONTROL
EA 142.000 $18.000 $21.730 $3.000 $23.900 $8.000 $26.330 $21.898
TEMP SEDMT CONT FENCE (INSTALL)
LF 946.000 $4.000 $6.370 $4.250 $7.010 $8.000 $10.000 $6.419
TEMP SEDMT CONT FENCE (REMOVE)
LF 946.000 $1.500 $1.170 $2.500 $1.290 $2.600 $1.000 $1.179
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,260.000 $50.000 $50.000 $100.000 $75.000 $128.000 $1,200.000 $80.842
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,260.000 $18.000 $20.000 $15.000 $50.000 $32.000 $20.000 $20.618
DRIVEWAYS (CONC)
SY 137.000 $140.000 $120.000 $115.000 $200.000 $119.000 $197.590 $285.076
DRIVEWAYS (SURF TREAT)
SY 968.000 $30.000 $35.490 $65.000 $39.600 $50.000 $35.620 $26.201
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 8,080.000 $0.300 $1.000 $0.500 $0.590 $0.330 $0.930 $0.655
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 4,040.000 $0.300 $1.000 $0.920 $0.790 $0.450 $1.530 $0.806
MTL W-BEAM GD FEN (TIM POST)
LF 300.000 $30.000 $33.500 $33.500 $30.550 $31.000 $46.780 $23.480
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $2,500.000 $1,944.000 $1,944.000 $2,825.890 $2,250.000 $3,118.890 $1,889.556
REMOVE METAL BEAM GUARD FENCE
LF 474.000 $3.000 $4.250 $4.250 $5.500 $10.000 $3.120 $10.077
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,400.000 $3,343.000 $3,343.000 $3,814.780 $3,510.000 $6,000.000 $2,967.863
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $300.000 $380.000 $380.000 $302.500 $350.000 $155.950 $277.134
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,500.000 $4,100.000 $1,350.000 $1,127.490 $2,000.000 $4,000.000 $1,133.733
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $2,500.000 $1,350.000 $1,099.990 $1,000.000 $3,000.000 $944.778
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $10,298.000 $15,000.000 $9,267.450 $15,000.000 $12,787.450 $6,891.086
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $900.000 $890.000 $890.000 $979.000 $725.000 $923.610 $1,158.927
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $800.000 $1,270.000 $1,270.000 $1,396.990 $850.000 $1,378.520 $1,259.704
REMOVE SM RD SN SUP&AM
EA 7.000 $100.000 $95.000 $95.000 $104.500 $100.000 $165.420 $151.164
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 102.000 $29.000 $21.000 $21.000 $23.100 $25.000 $34.460 $35.271
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $35.000 $35.000 $35.000 $38.500 $40.000 $55.140 $45.349
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 7,350.000 $1.500 $0.850 $0.850 $0.460 $0.440 $0.580 $0.423
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 6,990.000 $1.500 $0.850 $0.850 $0.460 $0.440 $0.580 $0.423
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 350.000 $2.000 $1.250 $1.000 $1.830 $7.150 $3.100 $1.360
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 5,200.000 $1.200 $1.550 $1.550 $1.260 $1.200 $2.680 $1.158
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 5,200.000 $1.000 $1.550 $1.550 $1.260 $1.200 $2.680 $1.158
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 8,805.000 $0.500 $0.910 $0.910 $1.080 $1.050 $1.350 $0.987
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 1,755.000 $0.500 $0.950 $0.950 $2.200 $2.150 $2.760 $2.015
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 7,050.000 $0.500 $0.910 $0.910 $1.080 $1.050 $1.350 $0.987
PAV SURF PREP FOR MRK (6")
LF 10,400.000 $0.040 $0.200 $0.200 $0.110 $0.110 $1.000 $0.100
Totals: $17,962,824.250 $21,288,201.984 $23,746,416.550 $26,862,178.116 $27,298,997.910 $33,412,147.180 $34,823,497.972