Show Job Controls
Bid Cobra

HOUSTON FM 2076 (2068-01-006)

Items: 121

County: HOUSTON
Length: 5.9690 MILES
Highway: FM 2076
District: LUFKIN
Control Number: 2068-01-006
DBE Goal: 0.0%
Project: C 2068-1-6
Guaranty: $100,000.00
Time: 207 WORKING DAYS
Engineer's Estimate: $11,385,716.50
Date: 08/08/2025 (10 months ago)
Contract Number: 8253206
Type: HIGHWAY IMPROVEMENT
Project ID: A00064662
Project Description: RESTORATION AND WIDEN PAVEMENT TO 26'
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESSE SISCO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$11,385,716.50
Over/Under Est: -13.05% -$1,485,518.12
Over/Under Est: -11.4% -$1,297,888.68
Amt Left: 1.9% $187,629.44
Over/Under Est: -10.24% -$1,166,198.73
Amt Left: 3.23% $319,319.39
Delta: -1.31% -$131,689.95
Over/Under Est: -5.88% -$669,237.91
Amt Left: 8.25% $816,280.21
Delta: -4.86% -$496,960.82
$10,982,554.73
Over/Under Est: -3.54% -$403,161.77
Amt Left: 10.93% $1,082,356.35
Delta: -2.48% -$266,076.14
Over/Under Est: -0.76% -$86,621.31
Amt Left: 14.13% $1,398,896.81
Delta: -2.88% -$316,540.46

Bid Items & Bid Tabulations

121 Total 0 of 121
HOUSTON  |  FM 2076  |  LUFKIN  |  2068-01-006  |  08/08/2025  |  $11,385,716.50  |  C 2068-1-6  |  HWY IMPRV  |  207 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DREWERY CONSTRUCTION COMPANY, INCORPORATED
BIG CREEK CONSTRUCTION, LTD.
PINTO CONSTRUCTION CO., INC.
L. S. EQUIPMENT CO., INC.
A. L. HELMCAMP, INC.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
PREPARING ROW
STA 315.900 $2,500.000 $1,450.000 $2,500.000 $1,500.000 $1,800.000 $2,300.000 $2,175.000
REMOV CONC (DRIVEWAYS)
SY 878.000 $35.000 $31.000 $20.000 $29.400 $24.000 $15.000 $35.000
REMOV CONC (CURB)
LF 256.000 $10.000 $19.000 $20.000 $18.900 $24.000 $15.000 $12.000
SUBGR WIDEN (OC)
STA 315.900 $500.000 $363.000 $750.000 $533.470 $1,000.000 $600.000 $485.160
EMBANK (VEH)(OC)(TY B)
CY 15,130.000 $20.000 $26.000 $30.000 $24.570 $21.500 $36.000 $23.820
BLADING
STA 315.900 $200.000 $300.000 $500.000 $393.480 $250.000 $200.000 $472.440
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 149.000 $175.000 $255.000 $100.000 $131.250 $100.000 $300.000 $250.000
BLOCK SODDING
SY 4,935.000 $6.000 $7.000 $7.000 $6.590 $8.000 $6.000 $5.990
BROADCAST SEED (TEMP_WARM)
SY 122,766.000 $0.500 $0.110 $0.160 $0.140 $0.180 $0.140 $0.130
BROADCAST SEED (TEMP_COOL)
SY 122,766.000 $0.500 $0.130 $0.160 $0.140 $0.180 $0.140 $0.130
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 245,532.000 $1.000 $0.630 $0.600 $0.580 $0.650 $0.550 $0.530
VEGETATIVE WATERING
TGL 9,930.100 $20.000 $0.010 $10.000 $0.010 $0.010 $1.000 $15.480
SPRINKLING (DUST CONTROL)
TGL 913.000 $50.000 $0.010 $50.000 $0.010 $0.010 $5.000 $38.620
FL BS (RDWY DEL) (TY D GR 1-2 OR GR 5)
TON 36,627.000 $60.000 $55.000 $50.000 $53.610 $54.500 $58.000 $66.290
GEOGRID BASE REINFORCEMENT (TYPE 1)
SY 4,810.000 $4.000 $10.200 $5.000 $15.080 $9.500 $5.000 $4.860
REWORK BS MTL (TY B)(6")(ORD COMP)
SY 4,810.000 $5.000 $14.500 $15.000 $14.980 $7.500 $6.000 $8.400
CEMENT
TON 1,665.000 $225.000 $270.000 $250.000 $185.000 $240.000 $225.000 $215.000
CEMENT TRT (EXIST MATL & NEW BASE)(12")
SY 86,450.000 $5.000 $4.250 $3.000 $5.070 $4.250 $7.500 $5.960
CEMENT TRT (NEW BASE)(12")
SY 4,810.000 $5.000 $4.700 $15.000 $5.070 $7.500 $9.000 $16.750
EMULS ASPH (EROSN CONT)(SS-1)
GAL 4,214.000 $7.000 $3.400 $6.000 $7.030 $6.500 $4.500 $4.330
ASPH (RC-250)
TON 98.900 $1,100.000 $1,150.000 $1,200.000 $1,358.360 $1,470.000 $1,100.000 $1,225.020
ASPH (AC-15P OR CRS-2P)
TON 167.000 $1,100.000 $900.000 $1,000.000 $988.780 $1,298.000 $1,050.000 $926.470
AGGR (TY E OR L, GR-5)
CY 651.000 $180.000 $195.000 $250.000 $190.010 $190.000 $250.000 $420.520
AGGR (TY E OR L, PE OR PL GR 4)
CY 676.000 $190.000 $185.000 $150.000 $195.620 $196.000 $260.000 $418.650
SP MIXES SP-C SAC-A PG70-22
TON 10,040.000 $180.000 $171.000 $130.000 $159.600 $164.000 $150.000 $136.240
CEM STABIL BKFL
CY 54.000 $250.000 $253.000 $400.000 $317.100 $400.000 $360.000 $200.000
FLOWABLE BACKFILL
CY 33.000 $250.000 $393.000 $400.000 $341.250 $400.000 $360.000 $350.000
TRENCH EXCAVATION PROTECTION
LF 11.000 $50.000 $17.000 $25.000 $31.500 $60.000 $16.000 $10.000
TEMPORARY SPL SHORING
SF 3,731.000 $55.000 $51.000 $35.000 $52.500 $50.000 $48.000 $40.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 16.000 $700.000 $466.000 $200.000 $190.100 $265.500 $435.000 $172.820
CL A CONC (COLLAR)
EA 10.000 $1,700.000 $1,350.000 $1,000.000 $1,908.900 $2,200.000 $790.000 $1,200.000
CL C CONC (WINGWALLS)
CY 3.000 $1,500.000 $3,370.000 $3,000.000 $4,200.000 $5,500.000 $2,600.000 $2,500.000
RIPRAP (CONC)(5 IN)
CY 6.000 $800.000 $1,125.000 $800.000 $806.400 $3,000.000 $761.000 $850.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 346.000 $325.000 $280.000 $150.000 $327.600 $250.000 $262.000 $250.000
MISC NON-BRIDGE (NBIS)
LB 56.000 $50.000 $17.000 $25.000 $11.000 $275.000 $26.000 $200.000
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 59.000 $1,000.000 $785.000 $1,000.000 $945.000 $800.000 $998.000 $650.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 20.000 $1,100.000 $840.000 $1,150.000 $997.500 $767.000 $1,105.000 $700.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 11.000 $1,500.000 $900.000 $1,300.000 $1,260.000 $900.000 $1,260.000 $800.000
CONC BOX CULV (7 FT X 7 FT)(EXTEND)
LF 14.000 $2,000.000 $1,000.000 $1,500.000 $1,538.250 $1,200.000 $1,470.000 $900.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 20.000 $1,500.000 $1,350.000 $1,600.000 $1,305.150 $1,400.000 $1,575.000 $1,000.000
CONC BOX CULV (10 FT X 10 FT)(EXTEND)
LF 3.000 $4,000.000 $3,400.000 $4,000.000 $3,839.850 $3,600.000 $3,150.000 $3,000.000
CONC BOX CULV (4 FT X 5 FT) (EXTEND)
LF 4.000 $1,300.000 $1,000.000 $1,300.000 $1,601.250 $1,200.000 $1,260.000 $900.000
CONC BOX CULV (5 FT X 9 FT) (EXTEND)
LF 4.000 $2,000.000 $1,125.000 $1,400.000 $1,634.850 $1,500.000 $1,365.000 $1,000.000
RC PIPE (CL III)(18 IN)
LF 1,443.000 $75.000 $70.000 $70.000 $73.500 $83.500 $63.000 $58.000
RC PIPE (CL III)(24 IN)
LF 244.000 $150.000 $157.000 $105.000 $110.250 $97.250 $100.000 $130.000
RC PIPE (CL III)(30 IN)
LF 10.000 $250.000 $336.890 $200.000 $231.000 $145.000 $131.000 $300.000
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $6,800.000 $6,200.000 $8,500.000 $6,825.000 $7,500.000 $7,875.000 $5,500.000
HEADWALL (CH - FW - 0) (DIA= 42 IN)
EA 1.000 $18,000.000 $6,700.000 $13,000.000 $11,550.000 $8,000.000 $12,600.000 $8,500.000
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 2.000 $9,000.000 $3,400.000 $9,000.000 $8,400.000 $4,500.000 $8,400.000 $4,000.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 1.000 $9,550.000 $4,500.000 $10,000.000 $9,660.000 $5,000.000 $9,450.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $12,000.000 $6,200.000 $11,000.000 $15,750.000 $6,250.000 $10,500.000 $6,500.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 1.000 $15,000.000 $15,000.000 $16,000.000 $18,375.000 $14,000.000 $15,750.000 $15,000.000
HEADWALL (CH - PW - 0) (DIA= 66 IN)
EA 1.000 $17,000.000 $30,000.000 $21,000.000 $26,250.000 $30,000.000 $21,000.000 $26,000.000
HEADWALL (CH - PW - 0) (DIA= 72 IN)
EA 2.000 $20,000.000 $34,000.000 $23,000.000 $28,350.000 $36,000.000 $23,100.000 $30,000.000
HEADWALL (CH - PW - S) (DIA= 30 IN)
EA 1.000 $11,000.000 $6,700.000 $12,000.000 $16,432.500 $8,000.000 $11,025.000 $7,000.000
HEADWALL (CH - PW - S) (DIA= 33 IN)
EA 1.000 $13,000.000 $7,800.000 $13,000.000 $18,270.000 $8,500.000 $12,600.000 $8,000.000
HEADWALL (CH - PW - S) (DIA= 60 IN)
EA 1.000 $23,000.000 $26,000.000 $17,000.000 $29,400.000 $27,000.000 $16,800.000 $23,000.000
HEADWALL (CH - PW - S) (DIA= 66 IN)
EA 1.000 $25,000.000 $30,000.000 $19,000.000 $30,450.000 $32,000.000 $18,900.000 $27,000.000
WINGWALL (FW - 0) (HW=3 FT)
EA 1.000 $9,000.000 $3,400.000 $9,000.000 $14,175.000 $4,000.000 $8,400.000 $3,000.000
WINGWALL (FW - 0) (HW=4 FT)
EA 1.000 $10,000.000 $6,200.000 $10,000.000 $15,750.000 $7,500.000 $9,450.000 $5,500.000
WINGWALL (FW - S) (HW=7 FT)
EA 0.500 $20,000.000 $11,000.000 $15,000.000 $31,500.000 $12,500.000 $12,600.000 $9,500.000
WINGWALL (PW - 2) (HW=4 FT)
EA 4.000 $22,000.000 $6,200.000 $15,000.000 $16,590.000 $7,500.000 $14,700.000 $5,500.000
WINGWALL (PW - 2) (HW=5 FT)
EA 1.000 $25,000.000 $7,900.000 $21,000.000 $22,050.000 $7,500.000 $21,000.000 $7,000.000
WINGWALL (PW - 2) (HW=8 FT)
EA 2.500 $26,000.000 $28,000.000 $41,000.000 $39,900.000 $27,000.000 $42,000.000 $25,000.000
WINGWALL (PW - 2) (HW=9 FT)
EA 1.000 $28,000.000 $29,000.000 $43,000.000 $60,585.000 $29,500.000 $44,100.000 $26,000.000
WINGWALL (PW - 2) (HW=10 FT)
EA 1.000 $30,000.000 $39,300.000 $51,000.000 $65,625.000 $41,500.000 $52,500.000 $35,000.000
WINGWALL (PW - 2) (HW=14 FT)
EA 1.000 $35,000.000 $90,000.000 $80,000.000 $89,250.000 $87,500.000 $78,750.000 $80,000.000
WINGWALL (PW - 2) (HW=15 FT)
EA 1.000 $40,000.000 $112,000.000 $90,000.000 $98,280.000 $115,000.000 $84,000.000 $100,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 3.000 $1,150.000 $1,000.000 $900.000 $1,050.000 $950.000 $866.000 $900.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 2.000 $1,300.000 $1,100.000 $1,000.000 $1,050.000 $950.000 $971.000 $1,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 105.000 $1,300.000 $1,100.000 $1,000.000 $1,050.000 $950.000 $971.000 $900.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 14.000 $2,000.000 $2,800.000 $1,700.000 $1,995.000 $1,150.000 $1,680.000 $2,500.000
CLEAN EXIST CULVERTS
EA 4.000 $4,000.000 $1,700.000 $2,000.000 $2,782.500 $2,000.000 $1,575.000 $1,500.000
REMOV STR (PIPE)
EA 61.000 $1,000.000 $67.000 $500.000 $525.000 $30.000 $289.000 $850.000
MOBILIZATION
LS 1.000 $1,100,000.000 $750,000.000 $1,000,000.000 $1,000,000.000 $990,000.000 $900,000.000 $1,290,245.210
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $3,500.000 $3,560.000 $5,000.000 $2,500.000 $9,500.000 $8,000.000 $14,462.920
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $7,500.000 $8,250.000 $20,000.000 $10,000.000 $15,000.000 $15,000.000
TMA (STATIONARY)
DAY 207.000 $350.000 $100.000 $400.000 $250.000 $300.000 $250.000 $192.000
TMA (MOBILE OPERATION)
DAY 30.000 $350.000 $100.000 $800.000 $50.000 $350.000 $250.000 $192.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,150.000 $45.000 $46.000 $45.000 $44.100 $52.500 $44.000 $42.000
ROCK FILTER DAMS (REMOVE)
LF 1,150.000 $15.000 $13.500 $5.000 $10.500 $10.500 $10.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 445.000 $40.000 $66.000 $30.000 $1.000 $42.000 $40.000 $39.000
CONSTRUCTION EXITS (REMOVE)
SY 445.000 $15.000 $20.000 $5.000 $1.000 $10.000 $10.000 $10.000
CONSTRUCTION PERIMETER FENCE
LF 435.000 $8.000 $5.000 $5.000 $5.250 $6.500 $5.000 $43.080
TEMP SEDMT CONT FENCE (INSTALL)
LF 15,470.000 $5.000 $4.500 $4.300 $4.390 $5.000 $4.200 $3.990
TEMP SEDMT CONT FENCE (REMOVE)
LF 15,470.000 $1.000 $0.700 $1.000 $0.420 $1.000 $0.400 $0.380
DRIVEWAYS (CONC)
SY 771.000 $150.000 $280.000 $130.000 $196.350 $275.000 $115.000 $200.000
DRIVEWAYS (ACP)
SY 5,810.000 $75.000 $55.000 $45.000 $54.120 $60.000 $103.000 $44.870
TURNOUTS (ACP)
SY 457.000 $100.000 $80.000 $65.000 $87.540 $90.000 $132.000 $95.160
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 31,590.000 $1.000 $0.400 $0.500 $0.400 $0.750 $0.550 $0.080
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $30.000 $32.000 $35.000 $30.800 $32.000 $25.000 $28.500
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $2,500.000 $1,700.000 $1,500.000 $1,375.000 $2,000.000 $1,312.000 $1,450.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,200.000 $3,425.000 $3,500.000 $3,190.000 $4,000.000 $3,045.000 $3,355.000
WIRE FENCE (TY A)
LF 250.000 $30.000 $28.000 $25.000 $40.000 $45.000 $30.000 $28.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 4.000 $650.000 $780.000 $700.000 $690.800 $695.000 $660.000 $620.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 10.000 $300.000 $275.000 $300.000 $278.300 $280.500 $266.000 $180.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 3.000 $350.000 $300.000 $400.000 $327.800 $327.500 $313.000 $230.000
IN RD IL (TY ST) 40T-8 (250W EQ) LED
EA 2.000 $4,650.000 $10,100.000 $8,000.000 $7,756.880 $9,500.000 $9,450.000 $7,051.710
CONDT (PVC) (SCH 80) (2")
LF 215.000 $17.000 $17.400 $25.000 $21.500 $29.500 $16.000 $19.540
CONDT (PVC) (SCH 80) (2") (BORE)
LF 105.000 $25.000 $31.500 $35.000 $30.580 $34.250 $29.000 $27.800
ELEC CONDR (NO.8) BARE
LF 440.000 $2.300 $3.650 $5.000 $3.330 $3.500 $3.400 $3.030
ELEC CONDR (NO.8) INSULATED
LF 760.000 $2.500 $4.300 $5.500 $3.400 $3.750 $4.000 $3.090
GROUND BOX TY D (162922)W/APRON
EA 5.000 $1,700.000 $1,950.000 $2,000.000 $1,654.390 $2,150.000 $1,810.000 $1,503.990
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $9,000.000 $8,450.000 $10,000.000 $8,179.190 $8,500.000 $7,896.000 $7,435.630
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $840.000 $785.000 $750.000 $759.000 $732.500 $725.000 $755.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $850.000 $900.000 $900.000 $884.400 $875.250 $844.000 $950.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,125.000 $1,040.000 $1,100.000 $1,158.300 $1,182.500 $1,106.000 $1,125.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,500.000 $1,350.000 $1,200.000 $1,285.900 $1,307.250 $1,227.000 $1,330.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 35.000 $600.000 $475.000 $500.000 $458.700 $485.000 $438.000 $500.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 1.000 $500.000 $445.000 $400.000 $381.700 $365.000 $364.000 $555.000
REMOVE SM RD SN SUP&AM
EA 40.000 $130.000 $140.000 $125.000 $108.900 $103.000 $104.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 77.000 $35.000 $42.000 $50.000 $34.100 $30.000 $33.000 $30.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 63,180.000 $1.000 $0.250 $0.400 $0.240 $0.300 $0.230 $0.310
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,160.000 $1.000 $2.400 $1.500 $2.500 $1.400 $1.120 $1.270
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 51,400.000 $0.750 $1.000 $0.900 $0.990 $1.000 $0.950 $0.810
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 11,100.000 $0.750 $0.800 $0.770 $0.770 $0.800 $0.740 $0.720
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 3,350.000 $0.750 $1.150 $0.770 $1.100 $1.100 $1.050 $0.720
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 46,300.000 $0.750 $0.800 $0.770 $0.770 $0.800 $0.740 $0.720
REFL PAV MRKR TY II-A-A
EA 759.000 $7.000 $6.750 $7.000 $6.600 $6.400 $6.300 $5.800
TEMP TRAF SIGNALS
EA 2.000 $12,000.000 $3,500.000 $10,000.000 $5,000.000 $75,000.000 $15,000.000 $12,116.060
BONDING COURSE
GAL 4,561.000 $6.000 $6.000 $5.000 $6.040 $8.500 $4.250 $7.360
Totals: $11,385,716.500 $9,900,198.381 $10,087,827.820 $10,219,517.780 $10,716,478.591 $10,982,554.730 $11,299,095.186
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,500.00
Total: $3,000.00