Bid Cobra

HIDALGO FM 1423 (1427-02-008)

Items: 84

County: HIDALGO
Length: 1.3900 MILES
Highway: FM 1423
District: PHARR
Control Number: 1427-02-008
DBE Goal: 0.0%
Project: C 1427-2-8
Guaranty: $71,000.00
Time: 128 WORKING DAYS
Engineer's Estimate: $4,068,431.47
Date: 07/01/2025 (11 months ago)
Contract Number: 7253014
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00199763
Project Description: PROVIDE ADDITIONAL PAVED SURFACE WIDTH TO 28', MILLED EDGELINE MARKINGS, MILLED CENTERLINE MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESUS NORIEGA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$4,068,431.47
$3,406,133.00
Over/Under Est: -16.28% -$662,298.47
$3,546,656.63
Over/Under Est: -12.82% -$521,774.84
Amt Left: 4.13% $140,523.63
$3,642,334.40
Over/Under Est: -10.47% -$426,097.07
Amt Left: 6.93% $236,201.40
Delta: -2.70% -$95,677.77
Over/Under Est: -7.93% -$322,437.17
Amt Left: 9.98% $339,861.30
Delta: -2.85% -$103,659.90
$4,225,052.55
Over/Under Est: 3.85% $156,621.08
Amt Left: 24.04% $818,919.55
Delta: -12.79% -$479,058.25
$4,645,619.70
Over/Under Est: 14.19% $577,188.23
Amt Left: 36.39% $1,239,486.70
Delta: -9.95% -$420,567.15
Subcontractor Percentage Amount
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 1.87% $70,087.81
HIGHWAY BARRICADES AND SERVICES, LLC 1.29% $48,349.35
Total: 3.16% $118,437.16

Bid Items & Bid Tabulations

84 Total 0 of 84
HIDALGO  |  FM 1423  |  PHARR  |  1427-02-008  |  07/01/2025  |  $4,068,431.47  |  C 1427-2-8  |  HAZARD ELIM & SAFETY  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS CORDIA CONSTRUCTION, LLC
ROVAN TEXAS, L.L.C.
IOC COMPANY, LLC
P & C OIL FIELD SERVICE LLC
EARTHWORKS ENTERPRISE
FOREMOST PAVING, INC.
PREPARING ROW
STA 72.000 $2,500.000 $1,500.000 $3,831.730 $3,250.000 $1,000.000 $1,396.490 $4,700.000
REMOV CONC (DRIVEWAYS)
SY 248.000 $15.000 $10.000 $27.640 $50.970 $50.000 $16.640 $51.150
RMV (4") TRT/UNTRT BASE & ASPH PAV
SY 4,891.000 $15.000 $12.000 $4.240 $6.500 $23.000 $23.140 $4.150
EXCAV (ROADWAY)
CY 4,816.000 $9.000 $52.000 $27.560 $25.000 $15.250 $23.920 $39.950
EMBANK (FNL)(DC)(TY C)
CY 140.000 $10.000 $20.000 $22.160 $25.000 $85.250 $20.170 $114.970
BACKFILL (TY A)
STA 72.000 $250.000 $470.000 $551.570 $500.000 $625.000 $877.430 $348.580
COMPOST MANUF TOPSOIL (4")
SY 23,349.000 $2.500 $2.000 $7.830 $0.750 $12.250 $10.650 $7.810
HYDRO MULCH SEED (PERM_RURAL_CLAY)
SY 23,349.000 $0.500 $1.000 $0.680 $0.500 $0.700 $0.780 $0.510
HYDRO MULCH SEED (TEMP_WARM)
SY 20,510.000 $0.400 $1.000 $0.620 $0.360 $0.600 $0.720 $0.370
VEGETATIVE WATERING
TGL 824.000 $12.000 $46.000 $69.840 $37.020 $48.000 $11.090 $48.430
FL BS (RDWY DEL)(TY E GR 4)(FNL POS)
CY 3,379.000 $27.500 $55.000 $59.400 $41.000 $99.000 $176.590 $48.740
LIME (COM OR QK)(SLURRY)
TON 337.000 $245.000 $350.000 $374.060 $270.000 $340.000 $424.760 $466.560
LIME TRT (EXIST MATL)(12")
SY 13,626.000 $3.000 $7.000 $5.710 $7.000 $10.250 $20.200 $12.530
CEMENT
TON 114.000 $200.000 $200.000 $220.380 $200.000 $215.000 $248.320 $272.080
CEMENT TRT (NEW BASE)(10")
SY 12,162.000 $7.200 $7.000 $6.400 $5.000 $11.500 $0.840 $11.810
SALV,HAUL & STKPL RCL ASPH PV (1 TO 3")
SY 4,891.000 $3.000 $9.000 $5.850 $6.500 $5.000 $6.950 $9.050
PRIME COAT (MC-30)
GAL 2,447.000 $4.750 $7.000 $6.500 $6.000 $7.600 $5.530 $8.770
ASPH (TIER II)
GAL 3,670.000 $4.000 $6.000 $4.690 $6.000 $7.250 $4.220 $19.270
AGGR (TY-B GR-4P SAC-B)
CY 98.000 $75.000 $300.000 $377.050 $230.000 $240.000 $328.280 $109.390
SP MIXES SP-D SAC-A PG76-22
TON 3,462.000 $130.000 $130.000 $140.340 $145.000 $155.000 $164.660 $179.750
PLANE & TEXT ASPH CONC PAV(1.5")
SY 2,918.000 $5.000 $6.000 $9.040 $10.000 $5.000 $4.160 $12.850
STRUCT EXCAV (SPECIAL)
CY 530.000 $75.000 $125.000 $97.130 $75.000 $98.000 $58.810 $71.400
CEM STABIL BKFL
CY 320.000 $113.000 $115.000 $90.940 $75.000 $150.000 $150.300 $173.400
TRENCH EXCAVATION PROTECTION
LF 826.000 $1.750 $8.000 $4.770 $0.100 $3.000 $4.570 $0.110
CL A CONC (COLLAR)
EA 1.000 $1,410.000 $5,000.000 $3,003.840 $2,500.000 $2,800.000 $2,940.660 $2,040.000
RIPRAP (CONC)(5 IN)
CY 283.000 $389.000 $550.000 $484.380 $650.000 $407.000 $643.680 $816.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 36.000 $175.000 $200.000 $330.660 $500.000 $320.000 $379.870 $224.400
CMP (GAL STL 12 IN)
LF 56.000 $80.000 $140.000 $90.760 $250.000 $67.000 $70.580 $122.400
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 26.000 $350.000 $1,390.000 $550.850 $1,500.000 $590.000 $1,045.570 $1,632.000
RC PIPE (CL III)(18 IN)
LF 672.000 $101.000 $130.000 $93.280 $150.000 $97.000 $182.980 $137.700
RC PIPE (CL IV)(18 IN)
LF 130.000 $84.000 $140.000 $101.900 $175.000 $110.000 $193.430 $142.800
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 2.000 $13,000.000 $20,360.000 $11,264.620 $10,000.000 $7,765.000 $3,920.900 $15,300.000
WINGWALL (PW - 1) (HW=4 FT)
EA 2.000 $15,700.000 $21,620.000 $13,517.550 $15,000.000 $13,000.000 $3,920.900 $15,300.000
SET (TY I)(S= 3 FT)(HW= 2 FT)(3:1)(C)
EA 1.000 $1,500.000 $1,080.000 $6,518.330 $15,000.000 $10,250.000 $3,071.360 $13,260.000
SET (TY I)(S= 3 FT)(HW= 2 FT)(4:1)(C)
EA 1.000 $8.000 $1,120.000 $7,420.370 $15,000.000 $10,250.000 $3,398.110 $13,260.000
SET (TY II) (12 IN) (CMP) (6: 1) (P)
EA 2.000 $975.000 $2,110.000 $1,888.030 $1,500.000 $15,500.000 $2,091.140 $1,428.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 58.000 $1,150.000 $1,650.000 $1,552.640 $1,500.000 $1,200.000 $2,352.540 $1,428.000
CLEAN EXIST CULVERTS
EA 3.000 $5,000.000 $5,910.000 $1,144.160 $2,000.000 $1,500.000 $1,960.450 $3,060.000
REMOV STR (SET)
EA 11.000 $350.000 $500.000 $1,011.200 $500.000 $425.000 $980.220 $612.000
REMOV STR (WINGWALL)
EA 6.000 $4,500.000 $3,170.000 $1,348.260 $2,000.000 $3,500.000 $1,633.710 $3,060.000
REMOV STR (PIPE)
LF 1,045.000 $18.000 $11.000 $26.980 $30.000 $26.000 $52.280 $35.700
MOBILIZATION
LS 1.000 $368,161.170 $200,000.000 $153,596.130 $350,000.000 $155,000.000 $51,026.940 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $8,000.000 $1,000.000 $12,179.250 $5,000.000 $1,050.000 $4,607.050 $6,400.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $10,520.000 $160.000 $2,137.460 $16,500.000 $6,800.000 $15,095.440 $4,104.920
TMA (STATIONARY)
DAY 50.000 $150.000 $180.000 $422.420 $150.000 $150.000 $196.040 $169.580
TMA (MOBILE OPERATION)
DAY 50.000 $150.000 $250.000 $738.940 $300.000 $100.000 $634.120 $0.010
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 312.000 $15.000 $30.000 $29.290 $30.000 $34.000 $58.140 $23.210
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $4.000 $11.000 $12.420 $10.000 $12.000 $25.310 $20.460
TEMP SEDMT CONT FENCE (INSTALL)
LF 400.000 $4.100 $10.000 $7.600 $10.000 $7.000 $8.820 $6.630
TEMP SEDMT CONT FENCE (REMOVE)
LF 400.000 $1.200 $2.000 $3.380 $5.000 $3.250 $3.920 $3.060
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 420.000 $5.200 $10.000 $8.620 $5.000 $6.000 $10.000 $7.040
BIODEG EROSN CONT LOGS (REMOVE)
LF 420.000 $1.300 $3.000 $3.380 $1.000 $3.000 $3.920 $3.060
CONSTRUCTING DETOURS (TY2)
SY 7,617.000 $207.000 $39.000 $65.470 $50.000 $66.500 $63.640 $77.580
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 844.000 $40.000 $320.000 $35.170 $115.000 $72.000 $109.520 $235.460
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 180.000 $50.000 $64.000 $102.690 $35.000 $100.000 $59.860 $60.030
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $58.000 $140.000 $114.240 $35.000 $97.000 $51.810 $47.970
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 180.000 $8.000 $28.000 $24.750 $10.000 $12.000 $9.860 $33.030
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $8.000 $100.000 $24.740 $10.000 $12.000 $11.230 $18.090
DRIVEWAYS (CONC)
SY 236.000 $80.000 $110.000 $157.700 $250.000 $120.000 $114.380 $159.990
DRIVEWAYS (ACP)
SY 2,173.000 $50.000 $41.000 $54.180 $130.000 $76.000 $46.070 $88.650
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 14,201.000 $0.170 $0.300 $0.440 $0.290 $0.250 $0.520 $0.880
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 7,139.000 $0.220 $0.400 $0.520 $0.380 $0.300 $0.520 $1.510
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 18.000 $315.000 $630.000 $394.260 $350.000 $350.000 $496.550 $357.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 2.000 $400.000 $790.000 $450.590 $400.000 $400.000 $926.750 $408.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 2.000 $590.000 $1,900.000 $732.200 $650.000 $775.000 $1,958.070 $663.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 8.000 $825.000 $970.000 $929.330 $825.000 $950.000 $1,019.430 $841.500
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $915.000 $1,100.000 $1,098.300 $975.000 $1,400.000 $1,280.820 $994.500
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,160.000 $1,290.000 $1,295.430 $1,150.000 $1,800.000 $1,437.660 $1,173.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 8.000 $73.000 $390.000 $168.970 $150.000 $114.000 $196.050 $153.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 10.000 $11.000 $130.000 $28.160 $25.000 $36.000 $32.670 $25.500
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 2.000 $228.000 $450.000 $506.910 $450.000 $475.000 $758.040 $459.000
WK ZN PAV MRK REMOV (W)6"(DOT)
LF 825.000 $2.500 $1.000 $1.350 $1.200 $1.000 $2.480 $1.230
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 15,104.000 $0.600 $0.500 $0.380 $0.340 $0.500 $1.240 $0.350
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 20.000 $11.500 $16.000 $18.020 $16.000 $16.500 $18.040 $16.320
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 11,924.000 $1.200 $1.000 $0.810 $0.720 $0.750 $1.240 $0.740
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 6,695.000 $0.750 $0.500 $0.470 $0.420 $0.500 $1.240 $0.430
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 14,201.000 $0.500 $1.000 $0.860 $0.760 $0.800 $0.970 $0.780
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 1,510.000 $0.500 $1.000 $1.240 $1.100 $1.200 $1.050 $1.130
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 2,979.000 $0.550 $1.000 $1.240 $1.100 $1.200 $1.050 $1.130
PREFAB PM TY C (W)(RR XING)
EA 1.000 $600.000 $750.000 $844.850 $750.000 $800.000 $836.450 $765.000
REFL PAV MRKR TY II-A-A
EA 572.000 $5.000 $8.000 $8.450 $7.500 $7.750 $6.270 $7.650
ELIM EXT PM & MRKS (4")
LF 5,036.000 $0.400 $0.350 $0.390 $0.350 $0.500 $1.570 $0.360
ELIM EXT PM & MRKS (24")
LF 11.000 $3.000 $4.000 $4.510 $4.000 $4.000 $10.460 $4.080
BONDING COURSE
GAL 1,979.000 $3.400 $7.000 $7.740 $5.000 $8.000 $4.220 $4.000
Totals: $4,068,431.470 $3,406,133.000 $3,546,656.630 $3,642,334.400 $3,745,994.300 $4,225,052.550 $4,645,619.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $180,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $32,000.00
Total: $217,000.00