Show Job Controls
Bid Cobra

HIDALGO IH 69C (0255-07-152)

Items: 58

County: HIDALGO
Length: 0.0000 MILES
Highway: IH 69C
District: PHARR
Control Number: 0255-07-152
DBE Goal: 0.0%
Project: C 255-7-152
Guaranty: $100,000.00
Time: 120 WORKING DAYS
Engineer's Estimate: $7,870,654.92
Date: 05/01/2025 (1 year ago)
Contract Number: 5253006
Type: PREVENTIVE MAINTENANCE
Project ID: A00209567
Project Description: OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
HECTOR SILLER
JESUS NORIEGA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$7,870,654.92
$6,414,834.09
Over/Under Est: -18.5% -$1,455,820.83
$6,452,440.21
Over/Under Est: -18.02% -$1,418,214.71
Amt Left: 0.59% $37,606.12
Over/Under Est: -5.24% -$412,429.73
Amt Left: 16.27% $1,043,391.10
Delta: -15.59% -$1,005,784.98
$8,662,911.75
Over/Under Est: 10.07% $792,256.83
Amt Left: 35.04% $2,248,077.66
Delta: -16.15% -$1,204,686.56
Subcontractor Percentage Amount
HIGHWAY BARRICADES AND SERVICES, LLC 3.64% $235,683.96
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 1.27% $82,230.39
D&G ENERGY CORPORATION 1.23% $79,640.46
SOIL TECH ADVANCE INC. 0.12% $7,769.80
Total: 6.26% $405,324.61

Bid Items & Bid Tabulations

58 Total 0 of 58
HIDALGO  |  IH 69C  |  PHARR  |  0255-07-152  |  05/01/2025  |  $7,870,654.92  |  C 255-7-152  |  PREVENT MAINT  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOREMOST PAVING, INC.
IOC COMPANY, LLC
PULICE CONSTRUCTION, INC.
EARTHWORKS ENTERPRISE
REMOV CONC (MOWSTRIP)
LF 100.000 $15.000 $36.780 $62.480 $17.430 $21.500
SP MIXES SP-D SAC-A PG76-22
TON 12,956.000 $140.000 $114.750 $108.050 $105.090 $132.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 27,873.000 $140.000 $129.050 $123.850 $135.650 $169.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 6,933.000 $25.000 $23.960 $30.000 $41.200 $31.000
PLANE ASPH CONC PAV(2")
SY 358,137.000 $2.500 $1.330 $1.500 $1.610 $2.500
RIPRAP (MOW STRIP)(4 IN)
CY 104.000 $500.000 $377.780 $973.570 $401.160 $393.250
MOBILIZATION
LS 1.000 $350,000.000 $100,000.000 $240,000.000 $743,927.290 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $6,750.000 $2,000.000 $11,438.540 $2,882.000
TMA (STATIONARY)
DAY 120.000 $100.000 $116.380 $1.000 $327.780 $394.000
TMA (MOBILE OPERATION)
DAY 120.000 $150.000 $0.010 $0.100 $144.680 $281.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,130.000 $7.000 $5.530 $4.790 $11.180 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,130.000 $1.000 $1.510 $1.360 $2.540 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 925.000 $30.000 $26.440 $27.180 $28.660 $44.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $2,250.000 $2,175.830 $2,120.000 $2,359.590 $3,258.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,500.000 $1,226.100 $1,635.000 $1,329.650 $3,258.000
CONNECTOR PLATE FOR THRIE BEAM
EA 3.000 $1,300.000 $1,125.600 $1,103.000 $1,220.670 $3,258.000
REMOVE METAL BEAM GUARD FENCE
LF 886.000 $3.000 $3.020 $3.750 $3.270 $10.250
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $250.000 $221.100 $325.000 $239.780 $1,012.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $250.000 $231.150 $325.000 $250.680 $1,012.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $350.000 $261.300 $325.000 $283.370 $1,012.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,400.000 $2,989.880 $3,454.000 $3,242.390 $5,505.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $250.000 $331.650 $325.000 $359.660 $1,012.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 28.000 $35.000 $28.650 $100.170 $31.060 $57.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 6,456.000 $1.000 $1.110 $1.250 $2.260 $0.750
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,733.000 $1.000 $1.110 $1.330 $2.280 $0.750
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 38.000 $0.650 $1.110 $1.100 $1.120 $4.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 11,090.000 $1.250 $0.890 $0.880 $0.890 $1.500
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 1,420.000 $4.000 $1.110 $1.100 $1.120 $5.250
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 2,227.000 $4.000 $1.110 $1.100 $1.120 $5.250
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 8,248.000 $9.000 $3.520 $3.500 $3.560 $4.500
RE PM TY II (W) 6" (BRK)
LF 8,525.000 $0.350 $0.390 $0.380 $0.390 $0.750
RE PM TY II (W) 8" (SLD)
LF 2,526.000 $0.600 $0.490 $0.480 $0.490 $1.000
RE PM TY II (W) 12" (LNDP)
LF 355.000 $2.000 $1.110 $1.100 $1.120 $2.750
RE PM TY II (Y) 6" (BRK)
LF 2,483.000 $0.350 $0.390 $0.380 $0.390 $0.750
RE PM TY II (Y) 6" (SLD)
LF 9,341.000 $0.450 $0.390 $0.380 $0.390 $0.750
RE PM TY III (W)(6")(SLD)
LF 627.000 $2.500 $6.540 $6.500 $6.610 $4.500
RE PM TY III (W)(6")(BRK)
LF 157.000 $3.000 $6.540 $6.500 $6.610 $4.750
RE PM TY III (Y)(6")(SLD)
LF 627.000 $2.500 $6.540 $6.500 $6.610 $4.250
RE PM TY III (Y)(6")(BRK)
LF 40.000 $3.000 $6.540 $6.500 $6.610 $4.750
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 19,081.000 $0.650 $0.750 $0.740 $0.750 $1.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 75,126.000 $0.650 $0.630 $0.620 $0.630 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 5,517.000 $0.650 $0.790 $0.780 $0.790 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 72,363.000 $0.650 $0.630 $0.620 $0.630 $1.000
PREFAB PM TY B (W)(6")(BRK)CONTRAST
LF 157.000 $8.810 $20.100 $20.000 $20.330 $11.000
PREFAB PM TY C (W)(ARROW)
EA 57.000 $250.000 $135.680 $135.000 $137.260 $264.000
PREFAB PM TY C (W)(DBL ARROW)
EA 4.000 $370.000 $326.630 $325.000 $330.440 $517.000
PREFAB PM TY C (W)(NUMBER)
EA 4.000 $250.000 $95.480 $95.000 $96.590 $236.000
PREFAB PM TY C (W)(WORD)
EA 47.000 $270.000 $226.130 $225.000 $228.760 $264.000
PREFAB PM TY C (W)(RR XING)
EA 2.000 $700.000 $653.250 $650.000 $660.880 $764.000
PREFAB PM TY C (W)(BIKE ARROW)
EA 30.000 $200.000 $90.450 $90.000 $91.510 $147.000
PREFAB PM TY C (W)(BIKE SYMBOL)
EA 30.000 $200.000 $180.900 $180.000 $183.010 $209.000
REFL PAV MRKR TY I-C
EA 599.000 $4.000 $7.540 $7.500 $7.630 $5.000
REFL PAV MRKR TY II-A-A
EA 1,395.000 $4.000 $7.540 $7.500 $7.630 $4.500
REFL PAV MRKR TY II-C-R
EA 1,263.000 $3.000 $7.540 $7.500 $7.630 $4.500
ELIM EXT PM & MRKS (4")
LF 1,451.000 $0.650 $0.260 $0.250 $0.250 $1.250
ELIM EXT PM & MRKS (24")
LF 3,589.000 $6.000 $2.010 $2.000 $2.030 $2.500
VEH LP DETECT (SAWCUT)
LF 6,139.000 $16.000 $13.070 $13.000 $13.220 $18.000
BONDING COURSE
GAL 25,071.000 $4.500 $3.050 $3.000 $3.910 $5.000
Totals: $7,870,654.920 $6,414,834.090 $6,452,440.210 $7,458,225.190 $8,662,911.750
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $25,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $15,000.00
Total: $40,000.00