PREPARING ROW
|
STA
|
80.000
|
$1,400.000
|
$15,000.000
|
$52,500.000
|
$27,272.160
|
$20,000.000
|
$25,000.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
10,411.000
|
$10.000
|
$8.000
|
$6.500
|
$25.510
|
$11.500
|
$9.000
|
|
|
EXCAVATION (SPECIAL)
|
CY
|
1,895.000
|
$20.000
|
$20.000
|
$7.500
|
$22.900
|
$18.250
|
$20.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
39,203.000
|
$9.250
|
$35.000
|
$10.000
|
$22.670
|
$13.500
|
$28.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
23,102.000
|
$1.000
|
$3.000
|
$1.000
|
$4.640
|
$2.500
|
$1.500
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
10,878.000
|
$0.800
|
$0.630
|
$1.000
|
$0.950
|
$1.050
|
$1.000
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
10,877.000
|
$0.800
|
$0.630
|
$1.000
|
$0.940
|
$1.050
|
$1.000
|
|
|
BOND FBR MTRX SEED(PERM)(RURAL)(CLAY)
|
AC
|
0.500
|
$30,000.000
|
$3,328.000
|
$10,000.000
|
$9,441.180
|
$10,500.000
|
$8,000.000
|
|
|
VEGETATIVE WATERING
|
MG
|
478.890
|
$10.000
|
$25.000
|
$50.000
|
$47.220
|
$4.000
|
$15.000
|
|
|
LIME (HYDRATED LIME (DRY))
|
TON
|
324.000
|
$175.000
|
$180.000
|
$200.000
|
$225.990
|
$220.000
|
$225.000
|
|
|
CEMENT
|
TON
|
324.000
|
$150.000
|
$150.000
|
$130.000
|
$176.430
|
$190.000
|
$165.000
|
|
|
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
|
GAL
|
22,855.000
|
$3.000
|
$4.500
|
$4.000
|
$5.530
|
$4.500
|
$5.000
|
|
|
AGGR (TY-PD GR-3 OR TY-PL GR-3)
|
CY
|
544.000
|
$135.000
|
$170.000
|
$120.000
|
$218.330
|
$200.000
|
$145.000
|
|
|
SUPERPAVE MIXTURES SP-C PG64-22
|
TON
|
10,771.000
|
$95.000
|
$85.000
|
$100.000
|
$96.320
|
$122.000
|
$100.000
|
|
|
SUPERPAVE MIXTURES SP-D SAC-A PG70-22
|
TON
|
4,480.000
|
$98.000
|
$90.000
|
$100.000
|
$98.140
|
$110.000
|
$105.000
|
|
|
SUPERPAVE MIXTURES SP-D PG64-22(LEV-UP)
|
TON
|
3,005.000
|
$84.000
|
$91.000
|
$100.000
|
$83.530
|
$110.000
|
$125.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (9")
|
SY
|
10,185.000
|
$50.000
|
$75.000
|
$60.000
|
$87.450
|
$98.000
|
$88.000
|
|
|
CEM STABIL BKFL
|
CY
|
202.900
|
$200.000
|
$160.000
|
$112.000
|
$201.720
|
$250.000
|
$250.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
11,960.000
|
$30.000
|
$24.000
|
$35.000
|
$20.310
|
$40.000
|
$45.000
|
|
|
SHEET PILING (PZ - 27)
|
SF
|
222,403.500
|
$50.000
|
$42.000
|
$39.250
|
$40.650
|
$41.000
|
$60.000
|
|
|
SHEET PILING (PZC - 39)
|
SF
|
15,812.400
|
$50.000
|
$50.000
|
$40.000
|
$95.730
|
$65.000
|
$130.000
|
|
|
DRILL SHAFT (30 IN)
|
LF
|
840.000
|
$160.000
|
$150.000
|
$155.000
|
$235.920
|
$175.000
|
$200.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
3,783.000
|
$250.000
|
$500.000
|
$207.990
|
$517.310
|
$595.000
|
$600.000
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
7,815.000
|
$350.000
|
$600.000
|
$560.000
|
$579.790
|
$675.000
|
$750.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
72.200
|
$1,000.000
|
$1,200.000
|
$850.000
|
$1,035.170
|
$1,050.000
|
$1,200.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
853.500
|
$1,100.000
|
$1,200.000
|
$1,150.000
|
$1,330.690
|
$1,300.000
|
$1,200.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
235.000
|
$1,100.000
|
$1,200.000
|
$1,100.000
|
$1,473.670
|
$1,725.000
|
$1,200.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
244.600
|
$600.000
|
$400.000
|
$400.000
|
$580.640
|
$615.000
|
$800.000
|
|
|
CL C CONC(COPING)(HPC)
|
LF
|
4,458.000
|
$310.000
|
$115.000
|
$150.000
|
$160.550
|
$150.000
|
$150.000
|
|
|
REINF CONC SLAB
|
SF
|
195,286.000
|
$22.000
|
$17.000
|
$20.000
|
$21.660
|
$21.750
|
$20.000
|
|
|
APPROACH SLAB
|
CY
|
124.000
|
$840.000
|
$500.000
|
$452.000
|
$666.800
|
$595.000
|
$500.000
|
|
|
RETAINING WALL (SPECIAL)
|
SF
|
1,240.000
|
$90.000
|
$85.000
|
$100.000
|
$91.230
|
$300.000
|
$200.000
|
|
|
PRESTR CONC GIRDER (TX34)
|
LF
|
4,770.030
|
$146.000
|
$125.000
|
$134.000
|
$159.970
|
$155.000
|
$175.000
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
19,530.030
|
$140.000
|
$125.000
|
$140.000
|
$168.630
|
$155.000
|
$175.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
13.900
|
$400.000
|
$650.000
|
$350.000
|
$714.880
|
$600.000
|
$600.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(8 IN)
|
CY
|
30.000
|
$125.000
|
$155.000
|
$140.000
|
$226.440
|
$275.000
|
$140.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
9,829.000
|
$90.000
|
$140.000
|
$105.000
|
$134.240
|
$200.000
|
$140.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
163.600
|
$525.000
|
$550.000
|
$450.000
|
$790.360
|
$560.000
|
$500.000
|
|
|
RAIL (TY T1F)
|
LF
|
13,234.300
|
$135.000
|
$135.000
|
$122.000
|
$162.300
|
$135.000
|
$215.000
|
|
|
RAIL (TY SSTR)
|
LF
|
2,097.000
|
$60.000
|
$55.000
|
$45.000
|
$65.300
|
$90.000
|
$90.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
694.000
|
$120.000
|
$135.000
|
$75.000
|
$96.590
|
$78.000
|
$85.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
2,017.000
|
$50.000
|
$60.000
|
$50.000
|
$65.250
|
$46.000
|
$40.000
|
|
|
JCTBOX(COMPL)(PJB)(3FTX5FT)
|
EA
|
1.000
|
$5,000.000
|
$3,800.000
|
$4,000.000
|
$3,556.180
|
$5,000.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(TY C)
|
EA
|
4.000
|
$6,000.000
|
$4,200.000
|
$4,500.000
|
$4,703.930
|
$6,500.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(3FT)(NONE)
|
EA
|
1.000
|
$3,800.000
|
$3,700.000
|
$4,500.000
|
$3,556.180
|
$6,500.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(3FT)(LEFT)
|
EA
|
3.000
|
$3,000.000
|
$4,300.000
|
$4,300.000
|
$3,557.350
|
$7,500.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(3FT)(RIGHT)
|
EA
|
4.000
|
$3,000.000
|
$4,300.000
|
$4,500.000
|
$3,557.060
|
$7,500.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(3FT)(BOTH)
|
EA
|
1.000
|
$4,500.000
|
$5,200.000
|
$6,500.000
|
$3,556.180
|
$10,000.000
|
$5,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$800.000
|
$1,200.000
|
$890.000
|
$1,769.480
|
$750.000
|
$500.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (P)
|
EA
|
18.000
|
$1,140.000
|
$1,400.000
|
$946.000
|
$1,837.320
|
$750.000
|
$500.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
1.000
|
$650.000
|
$1,600.000
|
$1,000.000
|
$1,905.190
|
$800.000
|
$600.000
|
|
|
PIPE (PVC) (SCH 80) (4 IN)
|
LF
|
952.400
|
$50.000
|
$25.000
|
$111.000
|
$32.350
|
$40.000
|
$20.000
|
|
|
REMOV STR (INLET)
|
EA
|
4.000
|
$1,550.000
|
$750.000
|
$610.000
|
$913.420
|
$1,500.000
|
$1,000.000
|
|
|
REMOV STR (SET)
|
EA
|
24.000
|
$400.000
|
$450.000
|
$500.000
|
$913.420
|
$350.000
|
$500.000
|
|
|
REMOV STR (PIPE)
|
EA
|
21.000
|
$450.000
|
$850.000
|
$770.000
|
$569.120
|
$275.000
|
$500.000
|
|
|
REMOVE STR (PILING)
|
EA
|
1.000
|
$200.000
|
$13,500.000
|
$5,000.000
|
$7,307.390
|
$14,000.000
|
$30,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$3,492,998.960
|
$4,500,000.000
|
$4,255,000.000
|
$4,500,000.000
|
$5,000,000.000
|
$5,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
17.000
|
$6,500.000
|
$25,000.000
|
$9,000.000
|
$18,561.240
|
$3,600.000
|
$150,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
255.000
|
$30.000
|
$34.000
|
$35.000
|
$33.960
|
$38.000
|
$40.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
255.000
|
$7.000
|
$10.000
|
$18.000
|
$17.530
|
$19.250
|
$8.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
50.000
|
$90.000
|
$135.000
|
$120.000
|
$66.990
|
$250.000
|
$225.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
5,980.000
|
$3.000
|
$2.000
|
$3.000
|
$3.010
|
$3.300
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
5,980.000
|
$0.750
|
$0.500
|
$1.000
|
$0.570
|
$0.650
|
$1.500
|
|
|
TRACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
50.000
|
$125.000
|
$275.000
|
$300.000
|
$152.890
|
$250.000
|
$225.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
2,430.000
|
$80.000
|
$60.000
|
$71.000
|
$91.880
|
$90.000
|
$100.000
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
2,430.000
|
$11.000
|
$5.000
|
$7.000
|
$11.030
|
$16.000
|
$20.000
|
|
|
CONC CURB (TY II)
|
LF
|
2,153.000
|
$15.000
|
$15.000
|
$20.000
|
$7.910
|
$14.000
|
$15.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
1,513.000
|
$20.000
|
$25.000
|
$30.000
|
$25.170
|
$33.000
|
$30.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,687.000
|
$30.000
|
$45.000
|
$65.000
|
$41.230
|
$46.000
|
$45.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
2,002.000
|
$100.000
|
$100.000
|
$100.000
|
$72.390
|
$125.000
|
$95.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
612.000
|
$60.000
|
$70.000
|
$55.000
|
$54.380
|
$70.000
|
$65.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
29.000
|
$1,600.000
|
$2,000.000
|
$2,000.000
|
$1,980.960
|
$2,800.000
|
$2,200.000
|
|
|
CURB RAMPS (TY 21)
|
EA
|
2.000
|
$2,000.000
|
$2,100.000
|
$2,000.000
|
$2,082.750
|
$3,200.000
|
$4,000.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
5,201.000
|
$22.000
|
$15.500
|
$18.000
|
$20.000
|
$22.000
|
$22.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
11.000
|
$1,700.000
|
$1,364.000
|
$1,390.000
|
$1,548.000
|
$1,500.000
|
$1,800.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
11.000
|
$1,250.000
|
$893.000
|
$975.000
|
$875.000
|
$1,300.000
|
$1,300.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
9,509.000
|
$4.250
|
$1.350
|
$2.000
|
$2.500
|
$2.200
|
$3.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
13.000
|
$260.000
|
$200.000
|
$90.000
|
$225.000
|
$165.000
|
$200.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
9.000
|
$300.000
|
$490.000
|
$100.000
|
$225.000
|
$165.000
|
$200.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
9.000
|
$2,650.000
|
$2,215.000
|
$2,550.000
|
$2,375.000
|
$2,800.000
|
$2,800.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
5.000
|
$300.000
|
$490.000
|
$225.000
|
$225.000
|
$220.000
|
$300.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
9.000
|
$12,300.000
|
$9,000.000
|
$15,000.000
|
$27,700.000
|
$32,000.000
|
$26,000.000
|
|
|
CRASH CUSH ATTEN (STKPL)
|
EA
|
4.000
|
$1,200.000
|
$1,000.000
|
$1,000.000
|
$3,250.000
|
$1,100.000
|
$2,000.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
7.000
|
$300.000
|
$250.000
|
$300.000
|
$250.000
|
$275.000
|
$400.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$700.000
|
$500.000
|
$740.000
|
$500.000
|
$550.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
27.000
|
$400.000
|
$375.000
|
$470.000
|
$375.000
|
$425.000
|
$500.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
15.000
|
$110.000
|
$65.000
|
$126.000
|
$65.000
|
$70.000
|
$125.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
142.000
|
$27.000
|
$20.000
|
$21.000
|
$20.000
|
$16.500
|
$30.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
29.000
|
$60.000
|
$45.000
|
$52.000
|
$45.000
|
$50.000
|
$55.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
5.000
|
$12.000
|
$10.000
|
$10.000
|
$10.000
|
$55.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
79.000
|
$35.000
|
$25.000
|
$44.000
|
$25.000
|
$22.000
|
$30.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
16,189.000
|
$0.160
|
$0.240
|
$0.200
|
$0.250
|
$0.280
|
$0.270
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
44,278.000
|
$0.180
|
$0.240
|
$0.200
|
$0.250
|
$0.280
|
$0.270
|
|
|
WK ZN PAV MRK REMOV (REFL) TY I-C
|
EA
|
445.000
|
$4.250
|
$3.250
|
$1.000
|
$3.000
|
$3.300
|
$3.500
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
1,950.000
|
$3.750
|
$3.250
|
$0.300
|
$3.000
|
$3.300
|
$3.500
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
EA
|
1,332.000
|
$3.250
|
$3.000
|
$0.200
|
$2.600
|
$2.850
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
EA
|
5,332.000
|
$3.250
|
$3.000
|
$1.000
|
$2.600
|
$2.850
|
$3.000
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
4,110.000
|
$0.200
|
$0.250
|
$0.500
|
$0.200
|
$0.220
|
$0.220
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
9,146.000
|
$0.250
|
$0.200
|
$0.200
|
$0.200
|
$0.220
|
$0.220
|
|
REFL PAV MRK TY II (W) (ARROW)
|
EA
|
2.000
|
$60.000
|
$55.000
|
$500.000
|
$100.000
|
$110.000
|
$110.000
|
|
REFL PAV MRK TY II (Y) 4" (BRK)
|
LF
|
1,780.000
|
$0.350
|
$0.250
|
$0.250
|
$0.200
|
$0.220
|
$0.220
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
15,760.000
|
$0.250
|
$0.200
|
$0.200
|
$0.200
|
$0.220
|
$0.220
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
8,320.000
|
$0.550
|
$0.480
|
$0.200
|
$0.450
|
$0.500
|
$0.500
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
19,798.000
|
$0.300
|
$0.450
|
$0.200
|
$0.420
|
$0.460
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
5,600.000
|
$0.550
|
$0.480
|
$0.200
|
$0.450
|
$0.500
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
32,710.000
|
$0.300
|
$0.450
|
$0.200
|
$0.420
|
$0.460
|
$0.450
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
8.000
|
$180.000
|
$267.000
|
$150.000
|
$200.000
|
$220.000
|
$250.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
570.000
|
$3.000
|
$3.750
|
$1.000
|
$3.200
|
$3.500
|
$4.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
402.000
|
$4.000
|
$3.750
|
$3.000
|
$3.200
|
$3.500
|
$4.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
83,638.000
|
$0.450
|
$0.440
|
$0.300
|
$0.320
|
$1.100
|
$0.750
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
1,060.000
|
$1.750
|
$2.000
|
$0.500
|
$1.000
|
$4.000
|
$3.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
30,798.000
|
$0.200
|
$0.140
|
$0.200
|
$0.100
|
$0.110
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
2.000
|
$25.000
|
$55.000
|
$150.000
|
$50.000
|
$55.000
|
$55.000
|
|
|
NO. OF WORKING DAYS
|
$/D
|
4,500.000
|
$400.000
|
$400.000
|
$400.000
|
$400.000
|
$400.000
|
$350.000
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
24.000
|
$10,000.000
|
$1,500.000
|
$3,000.000
|
$2,663.640
|
$12,000.000
|
$5,000.000
|
|
|
TEMP CONSTRUCTION ACCESS
|
LS
|
1.000
|
$300,000.000
|
$250,000.000
|
$350,000.000
|
$57,665.140
|
$2,000,000.000
|
$2,000,000.000
|
|
|
FLOATING TURBIDITY BARRIER(FUR & INST)
|
LF
|
5,050.000
|
$30.000
|
$15.000
|
$25.000
|
$53.360
|
$42.000
|
$60.000
|
|
|
FLOATING TURBIDITY BARRIER (REMOVE)
|
LF
|
5,050.000
|
$10.000
|
$4.000
|
$10.000
|
$3.000
|
$5.500
|
$10.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$14,000.000
|
$7,500.000
|
$16,500.000
|
$13,571.390
|
$18,000.000
|
$20,000.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
12.000
|
$180.000
|
$750.000
|
$90.000
|
$155.960
|
$55.000
|
$500.000
|
|
Totals: |
$40,593,998.570
|
$43,069,729.220
|
$43,293,722.665
|
$47,378,061.610
|
$50,470,615.950
|
$59,385,223.860
|