HAYS FM 2001 (1776-02-021)
Items: 44
County: HAYS
Length: 0.0000 MILES
Highway: FM 2001
District: AUSTIN
Control Number: 1776-02-021
DBE Goal: 0.0%
Project: F 2026(422)
Guaranty: $46,000.00
Time: 50 WORKING DAYS
Engineer's Estimate: $2,310,563.58
Date: 03/04/2026 (3 months ago) Changed
Contract Number: 3263203
Type: PREVENTIVE MAINTENANCE
Project ID: A00197378
Contract Type: Federal
Project Description: FDR, LEVEL-UP, BONDING COURSE, AND TOM
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ORLANDO GALLEGOS
IVAN BAKER
HAYS FM 2001 (1776-02-021)
Project Name: N/A
Project: F 2026(422)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: SH 21
Limits To: 0.37 MI N OF SATTERWHITE RD
Project Description: FDR, LEVEL-UP, BONDING COURSE, AND TOM
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,310,563.58 | |||
| $1,788,337.62 |
-22.6%
-$522,225.96
|
|||
| $1,855,947.95 |
-19.68%
-$454,615.63
|
3.78%
$67,610.33
|
||
| $1,897,500.26 |
-17.88%
-$413,063.32
|
6.1%
$109,162.64
|
-2.24%
-$41,552.31
|
|
| $1,981,996.57 |
-14.22%
-$328,567.01
|
10.83%
$193,658.95
|
-4.45%
-$84,496.31
|
|
| $2,299,184.27 |
-0.49%
-$11,379.31
|
28.57%
$510,846.65
|
-16.00%
-$317,187.70
|
|
| $2,316,971.75 |
0.28%
$6,408.17
|
29.56%
$528,634.13
|
-0.77%
-$17,787.48
|
|
| $2,433,434.98 |
5.32%
$122,871.40
|
36.07%
$645,097.36
|
-5.03%
-$116,463.23
|
E
Engineer's Estimate
$2,310,563.58
1
Awarded
$1,788,337.62
Over/Under Est:
-22.6%
-$522,225.96
$1,855,947.95
Over/Under Est:
-19.68%
-$454,615.63
Amt Left:
3.78%
$67,610.33
$1,897,500.26
Over/Under Est:
-17.88%
-$413,063.32
Amt Left:
6.1%
$109,162.64
Delta:
-2.24%
-$41,552.31
$1,981,996.57
Over/Under Est:
-14.22%
-$328,567.01
Amt Left:
10.83%
$193,658.95
Delta:
-4.45%
-$84,496.31
$2,299,184.27
Over/Under Est:
-0.49%
-$11,379.31
Amt Left:
28.57%
$510,846.65
Delta:
-16.00%
-$317,187.70
$2,316,971.75
Over/Under Est:
0.28%
$6,408.17
Amt Left:
29.56%
$528,634.13
Delta:
-0.77%
-$17,787.48
$2,433,434.98
Over/Under Est:
5.32%
$122,871.40
Amt Left:
36.07%
$645,097.36
Delta:
-5.03%
-$116,463.23
Bid Items & Bid Tabulations
44
Total
0 of 44
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $20,000.00 |