HAYS RM 3237 (0805-04-038)
Items: 74
County: HAYS
Length: 0.0000 MILES
Highway: RM 3237
District: AUSTIN
Control Number: 0805-04-038
DBE Goal: 0.0%
Project: STP 2B25(191)HRR
Guaranty: $64,000.00
Time: 95 WORKING DAYS
Engineer's Estimate: $3,180,793.24
Date: 11/06/2025 (7 months ago)
Contract Number: 11253220
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193148
Contract Type: Federal
Project Description: INSTALL CONTINUOUS TURN LANE, CONSTRUCT PAVED SHOULDERS (>= 5FT.)
Mail/Deliver Bids To: N/A
ORLANDO GALLEGOS
IVAN BAKER
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
HAYS RM 3237 (0805-04-038)
Project Name: N/A
Project: STP 2B25(191)HRR
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.305 MI W OF LONE MAN MOUNTAIN RD
Limits To: 0.379 MI E OF LONE MAN MOUNTAIN RD
Project Description: INSTALL CONTINUOUS TURN LANE, CONSTRUCT PAVED SHOULDERS (>= 5FT.)
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,180,793.24 | |||
| $1,989,310.84 |
-37.46%
-$1,191,482.40
|
|||
| $2,153,984.08 |
-32.28%
-$1,026,809.16
|
8.28%
$164,673.24
|
||
| $2,365,247.45 |
-25.64%
-$815,545.79
|
18.9%
$375,936.61
|
-9.81%
-$211,263.37
|
|
| $2,376,778.22 |
-25.28%
-$804,015.02
|
19.48%
$387,467.38
|
-0.49%
-$11,530.77
|
|
| $2,479,932.25 |
-22.03%
-$700,860.99
|
24.66%
$490,621.41
|
-4.34%
-$103,154.03
|
|
| $2,582,225.15 |
-18.82%
-$598,568.09
|
29.81%
$592,914.31
|
-4.12%
-$102,292.90
|
|
| $2,701,682.30 |
-15.06%
-$479,110.94
|
35.81%
$712,371.46
|
-4.63%
-$119,457.15
|
E
Engineer's Estimate
$3,180,793.24
1
Awarded
$1,989,310.84
Over/Under Est:
-37.46%
-$1,191,482.40
$2,153,984.08
Over/Under Est:
-32.28%
-$1,026,809.16
Amt Left:
8.28%
$164,673.24
$2,365,247.45
Over/Under Est:
-25.64%
-$815,545.79
Amt Left:
18.9%
$375,936.61
Delta:
-9.81%
-$211,263.37
$2,376,778.22
Over/Under Est:
-25.28%
-$804,015.02
Amt Left:
19.48%
$387,467.38
Delta:
-0.49%
-$11,530.77
$2,479,932.25
Over/Under Est:
-22.03%
-$700,860.99
Amt Left:
24.66%
$490,621.41
Delta:
-4.34%
-$103,154.03
$2,582,225.15
Over/Under Est:
-18.82%
-$598,568.09
Amt Left:
29.81%
$592,914.31
Delta:
-4.12%
-$102,292.90
$2,701,682.30
Over/Under Est:
-15.06%
-$479,110.94
Amt Left:
35.81%
$712,371.46
Delta:
-4.63%
-$119,457.15
| Subcontractor | Percentage | Amount |
|---|---|---|
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | 3.86% | $79,134.32 |
| LINEAR TRAFFIC MARKINGS LLC | 3.65% | $74,829.08 |
| STRIPE IT UP, LLC | 0.88% | $18,040.98 |
| EGGEMEYER LAND CLEARING, LLC | 0.72% | $14,760.81 |
| ROADWAY TRAFFIC CONTROL LLC | 0.50% | $10,250.56 |
| Total: | 9.61% | $197,015.75 |