HAYS SH 21 (0471-02-079)

Items: 38

County: HAYS
Length: N/A
Highway: SH 21
District: AUSTIN
Control Number: 0471-02-079
DBE Goal: N/A
Project: F 2023(175)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $3,022,330.95
Date: 11/02/2022 (3 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
MARK BAUMANN
SHANE SWIMM
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$3,022,330.95
$2,808,195.50
Over/Under Est: -7.09% -$214,135.45
Over/Under Est: -2.61% -$78,921.76
Amt Left: 4.81% $135,213.69
Over/Under Est: 1.37% $41,333.61
Amt Left: 9.1% $255,469.06
Delta: -4.09% -$120,255.37
Over/Under Est: 21.73% $656,670.86
Amt Left: 31.01% $870,806.31
Delta: -20.09% -$615,337.25

Bid Items & Bid Tabulations

38 Total 0 of 38
HAYS  |  SH 21  |  AUSTIN  |  0471-02-079  |  11/02/2022  |  $3,022,330.95  |  F 2023(175)  |  PREVENT MAINT  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONE STAR PAVING COMPANY
TEXAS MATERIALS GROUP, INC.
HUNTER INDUSTRIES, LTD.
CLARK CONSTRUCTION OF TEXAS, INC.
BACKFILL (TY A)
STA 240.000 $130.000 $145.000 $170.000 $157.500 $263.270
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 17,940.000 $40.000 $44.000 $39.300 $42.440 $56.570
PLANE ASPH CONC PAV (1")
SY 77,533.000 $1.350 $1.830 $1.250 $1.530 $1.360
MOBILIZATION
LS 1.000 $180,000.000 $45,000.000 $83,009.000 $254,000.000 $127,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $1,175.000 $900.000 $4,000.000 $2,100.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,000.000 $5.000 $4.000 $5.000 $8.000 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $1.500 $1.000 $1.000 $2.000 $3.500
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 13,326.000 $0.300 $0.120 $0.140 $0.180 $0.200
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 71,775.000 $0.300 $0.110 $0.120 $0.170 $0.200
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 7,695.000 $0.750 $0.400 $0.420 $0.360 $0.400
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 164.000 $8.000 $8.000 $8.100 $4.000 $5.000
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 4.000 $200.000 $170.000 $172.000 $374.000 $250.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 78,644.000 $0.250 $0.120 $0.120 $0.170 $0.200
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,931.000 $1.050 $1.500 $1.100 $1.490 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 7,048.000 $1.500 $1.500 $1.100 $1.490 $1.000
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 2,525.000 $1.500 $1.500 $1.400 $1.440 $2.500
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 2,525.000 $1.500 $1.500 $1.400 $1.400 $2.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,130.000 $0.800 $0.950 $0.960 $0.860 $0.950
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 935.000 $3.000 $6.500 $6.570 $4.000 $4.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 164.000 $12.000 $10.000 $10.100 $8.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 22.000 $200.000 $500.000 $505.000 $170.000 $200.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 15.000 $240.000 $100.000 $101.000 $255.000 $275.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 2.000 $135.000 $500.000 $505.000 $375.000 $425.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 22.000 $150.000 $100.000 $101.000 $185.000 $250.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 4.000 $540.000 $500.000 $505.000 $695.000 $650.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 8,884.000 $0.450 $0.410 $0.420 $0.430 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 35,534.000 $0.400 $0.400 $0.410 $0.430 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 6,387.000 $0.400 $0.410 $0.410 $0.430 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 52,429.000 $0.450 $0.400 $0.410 $0.430 $0.500
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 12,316.000 $0.400 $1.000 $1.010 $0.940 $1.250
REFL PAV MRKR TY II-A-A
EA 1,939.000 $4.000 $3.000 $3.030 $3.740 $5.000
TRAFFIC BUTTON TY I-C
EA 1,117.000 $4.000 $3.000 $3.030 $3.740 $5.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 2,221.000 $100.000 $112.500 $106.000 $104.220 $132.750
TOM-C PG76-22 SAC-B
TON 10,136.000 $140.000 $119.000 $144.000 $125.280 $162.280
UNDERSEAL COURSE
GAL 38,751.000 $3.150 $3.650 $3.550 $4.550 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 128.000 $100.000 $67.000 $80.000 $100.000 $75.000
TMA (STATIONARY)
DAY 128.000 $200.000 $263.000 $150.000 $200.000 $200.000
TMA (MOBILE OPERATION)
HR 36.000 $65.000 $221.000 $225.000 $80.000 $250.000
Totals: $3,022,330.950 $2,808,195.500 $2,943,409.190 $3,063,664.560 $3,679,001.810