HAYS IH 35 (0016-03-124)

Items: 38

County: HAYS
Length: N/A
Highway: IH 35
District: AUSTIN
Control Number: 0016-03-124
DBE Goal: N/A
Project: F 2023(880)
Guaranty: N/A
Time: 29 WORKING DAYS
Engineer's Estimate: $1,065,373.17
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
SHANE SWIMM
MARK BAUMANN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,065,373.17
$1,002,855.18
Over/Under Est: -5.87% -$62,517.99
Over/Under Est: -3.4% -$36,207.34
Amt Left: 2.62% $26,310.65
Over/Under Est: 8.4% $89,488.19
Amt Left: 15.16% $152,006.18
Delta: -12.21% -$125,695.53
Over/Under Est: 10.6% $112,934.54
Amt Left: 17.5% $175,452.53
Delta: -2.03% -$23,446.35
Subcontractor Percentage Amount
D. I. J. CONSTRUCTION, INC. 0.00% $0.00
ENVIRONMENTAL SAFETY SERVICES, INC. 0.00% $0.00
MURRAY CONSTRUCTION 0.00% $0.00
TRP CONSTRUCTION GROUP, LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

38 Total 0 of 38
HAYS  |  IH 35  |  AUSTIN  |  0016-03-124  |  06/01/2023  |  $1,065,373.17  |  F 2023(880)  |  RESURF ROADWAY  |  29 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
CLARK CONSTRUCTION OF TEXAS, INC.
LONE STAR PAVING COMPANY
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A)
STA 209.160 $170.000 $184.000 $179.710 $180.000 $100.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 2,500.000 $40.000 $35.380 $47.430 $42.000 $39.000
PLANE ASPH CONC PAV (1")
SY 34,050.000 $1.300 $1.340 $1.730 $2.200 $1.750
MOBILIZATION
LS 1.000 $85,134.790 $71,311.140 $27,700.000 $67,900.000 $98,875.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $8,000.000 $15,905.000 $1,800.000 $2,000.000 $3,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 50.000 $3.500 $11.880 $13.000 $10.000 $8.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 50.000 $1.000 $11.880 $4.000 $10.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 50.000 $10.000 $11.880 $12.000 $10.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 50.000 $1.000 $11.880 $2.000 $10.000 $1.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)SRF
EA 120.000 $100.000 $129.570 $37.500 $180.000 $160.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 5,621.000 $0.400 $1.030 $0.400 $0.360 $0.950
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 24,272.000 $0.470 $0.620 $0.400 $0.360 $0.570
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 5,338.000 $0.400 $1.460 $0.800 $0.360 $1.350
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 300.000 $1.500 $3.890 $1.500 $5.500 $3.600
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 5.000 $75.000 $86.380 $150.000 $81.000 $80.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 5.000 $80.000 $97.170 $150.000 $81.000 $90.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 16,285.000 $0.300 $0.620 $0.400 $0.360 $0.570
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,587.000 $1.750 $1.770 $1.070 $2.600 $1.650
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,964.000 $1.750 $1.730 $1.500 $0.800 $1.600
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 300.000 $3.250 $11.010 $3.000 $4.500 $10.200
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 5.000 $160.000 $237.540 $200.000 $260.000 $220.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 5.000 $185.000 $253.730 $200.000 $260.000 $235.000
REFL PAV MRK TY I (W)(BIKE ARW)(100MIL)
EA 5.000 $110.000 $156.560 $150.000 $260.000 $145.000
REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
EA 5.000 $190.000 $199.750 $250.000 $260.000 $185.000
REFL PAV MRK TY I (W)(BIKE DOT)(100MIL)
EA 92.000 $0.600 $4.750 $5.000 $1.100 $4.400
REFL PAV MRK TY II (W) (BIKE ARROW)
EA 5.000 $40.000 $43.190 $75.000 $80.000 $40.000
REFL PAV MRK TY II (W) (BIKE SYMBOL)
EA 5.000 $55.000 $59.380 $85.000 $80.000 $55.000
REFL PAV MRK TY II (W) (BIKE DOT)
EA 92.000 $3.250 $2.750 $2.500 $1.100 $2.550
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 5,229.000 $0.770 $1.060 $0.850 $1.600 $0.980
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 22,578.000 $0.770 $1.080 $1.750 $1.600 $1.000
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 15,148.000 $0.800 $1.080 $1.750 $1.600 $1.000
REFL PAV MRKR TY II-C-R
EA 262.000 $4.000 $11.980 $5.000 $8.000 $11.100
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 197.000 $180.000 $154.000 $179.170 $140.000 $180.000
TOM-C PG76-22 SAC-B
TON 4,029.000 $140.000 $120.800 $133.880 $155.000 $163.000
UNDERSEAL COURSE
GAL 14,262.000 $4.000 $4.000 $4.070 $4.000 $3.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $2,921.980 $2,000.000 $4,000.000 $6,000.000
TMA (STATIONARY)
DAY 40.000 $240.000 $321.420 $200.000 $300.000 $250.000
TMA (MOBILE OPERATION)
HR 100.000 $125.000 $60.780 $200.000 $52.000 $90.000
Totals: $1,065,373.170 $1,002,855.180 $1,029,165.834 $1,154,861.360 $1,178,307.710