HARRISON IH 20 (0495-08-121)

Items: 63

County: HARRISON
Length: N/A
Highway: IH 20
District: ATLANTA
Control Number: 0495-08-121
DBE Goal: N/A
Project: BR 2021(433)
Guaranty: N/A
Time: 146 WORKING DAYS
Engineer's Estimate: $699,253.60
Date: 05/06/2021 (5 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$699,253.60
$692,721.00
Over/Under Est: -0.93% -$6,532.60
Over/Under Est: -0.76% -$5,297.60
Amt Left: 0.18% $1,235.00
Over/Under Est: 1.06% $7,411.50
Amt Left: 2.01% $13,944.10
Delta: -1.83% -$12,709.10
Over/Under Est: 9.35% $65,366.40
Amt Left: 10.38% $71,899.00
Delta: -8.20% -$57,954.90
Over/Under Est: 50.35% $352,102.40
Amt Left: 51.77% $358,635.00
Delta: -37.50% -$286,736.00
Over/Under Est: 51.58% $360,692.80
Amt Left: 53.01% $367,225.40
Delta: -0.82% -$8,590.40
Over/Under Est: 80.58% $563,448.40
Amt Left: 82.28% $569,981.00
Delta: -19.13% -$202,755.60

Bid Items & Bid Tabulations

63 Total 0 of 63
HARRISON  |  IH 20  |  ATLANTA  |  0495-08-121  |  05/06/2021  |  $699,253.60  |  BR 2021(433)  |  BRIDGE MAINT  |  146 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
R & G CONSTRUCTION, LLC
HIGHWAY 19 CONSTRUCTION LLC
GHB EQUIPMENT COMPANY, L.L.C.
SCR CIVIL CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
REMOVING CONC (RIPRAP)
SY 22.000 $20.000 $29.000 $50.000 $16.000 $25.000 $100.000 $300.000 $50.000
REMOVE CONC (MISC)
EA 2.000 $1,000.000 $1,000.000 $1,500.000 $350.000 $1,000.000 $100.000 $9,000.000 $5,000.000
REMOVING STAB BASE & ASPH PAV(13"-18")
SY 166.000 $12.000 $100.000 $25.000 $20.000 $20.000 $100.000 $186.000 $50.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 467.000 $18.000 $30.000 $50.000 $22.000 $30.000 $60.000 $61.000 $50.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 1,423.000 $1.000 $2.000 $2.000 $1.200 $1.000 $3.000 $1.150 $2.000
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 1,423.000 $0.200 $2.000 $2.000 $1.000 $1.000 $3.000 $1.150 $2.000
VEGETATIVE WATERING
MG 46.000 $20.000 $400.000 $100.000 $4.000 $10.000 $300.000 $100.000 $10.000
CEM STABIL BKFL
CY 28.000 $155.000 $100.000 $250.000 $220.000 $180.000 $300.000 $635.000 $400.000
FLOWABLE BACKFILL
CY 11.000 $245.000 $225.000 $250.000 $250.000 $250.000 $300.000 $635.000 $600.000
APPROACH SLAB (HPC)
CY 62.000 $640.000 $600.000 $650.000 $1,050.000 $650.000 $700.000 $1,100.000 $700.000
EPOXY WATERPROOF FINISH
SF 630.000 $8.000 $8.000 $50.000 $30.000 $35.000 $42.000 $25.000 $25.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 1,199.000 $50.000 $20.000 $21.000 $35.000 $35.000 $60.000 $25.000 $25.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 3.000 $1,000.000 $160.000 $500.000 $700.000 $1,000.000 $2,000.000 $1,500.000 $1,500.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 169.000 $220.000 $149.000 $120.000 $400.000 $350.000 $120.000 $340.000 $300.000
CONC STR REPAIR (PAN GIRDER HOLE REPR)
EA 32.000 $200.000 $150.000 $400.000 $60.000 $200.000 $200.000 $100.000 $100.000
RIPRAP (CONC)(5 IN)
CY 22.000 $450.000 $400.000 $450.000 $625.000 $600.000 $500.000 $1,150.000 $500.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 50.000 $150.000 $190.000 $90.000 $150.000 $250.000 $300.000 $390.000 $400.000
BEDDING MATERIAL (6 IN)
CY 13.000 $200.000 $115.000 $90.000 $130.000 $250.000 $200.000 $586.000 $400.000
RIPRAP (MOW STRIP)(4 IN)
CY 48.000 $450.000 $450.000 $500.000 $500.000 $450.000 $500.000 $960.000 $600.000
CLEANING AND SEALING EXISTING JOINTS
LF 373.000 $30.000 $30.000 $35.000 $32.000 $35.000 $40.000 $35.000 $50.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 610.000 $40.000 $40.000 $25.000 $20.000 $55.000 $40.000 $30.000 $50.000
CLEANING EXISTING JOINTS
LF 533.000 $25.000 $15.000 $20.000 $15.000 $55.000 $40.000 $20.000 $26.000
RETROFIT RAIL (TY T131RC)
LF 357.000 $190.000 $200.000 $200.000 $270.000 $190.000 $250.000 $455.000 $350.000
ARMOR JOINT
LF 51.000 $80.000 $100.000 $200.000 $100.000 $180.000 $200.000 $200.000 $300.000
HEADER TYPE EXPANSION JOINT
CF 157.000 $460.000 $400.000 $400.000 $320.000 $250.000 $250.000 $470.000 $700.000
JOINT SEALANT
LF 773.000 $20.000 $20.000 $25.000 $15.500 $35.000 $40.000 $10.000 $20.000
MOBILIZATION
LS 1.000 $63,180.000 $40,000.000 $75,000.000 $30,000.000 $70,000.000 $120,000.000 $100,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $4,000.000 $4,000.000 $750.000 $2,000.000 $5,000.000 $2,000.000 $3,850.000 $30,000.000
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 468.000 $35.000 $30.000 $65.000 $25.000 $30.000 $70.000 $67.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 468.000 $9.000 $15.000 $25.000 $10.000 $10.000 $20.000 $22.350 $5.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,700.000 $3.000 $5.000 $3.500 $3.100 $2.000 $7.000 $3.350 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,700.000 $2.000 $2.000 $1.200 $1.100 $1.000 $2.000 $1.150 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 3.000 $6,000.000 $3,500.000 $3,500.000 $5,000.000 $6,000.000 $7,000.000 $5,500.000 $10,000.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 220.000 $35.000 $85.000 $70.000 $100.000 $50.000 $90.000 $100.000 $100.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $40.000 $85.000 $75.000 $110.000 $50.000 $90.000 $100.000 $100.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 220.000 $5.000 $10.000 $30.000 $20.000 $10.000 $40.000 $20.000 $15.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 40.000 $10.000 $10.000 $30.000 $20.000 $10.000 $40.000 $20.000 $15.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 220.000 $15.000 $8.000 $25.000 $40.000 $50.000 $60.000 $75.000 $15.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $15.000 $10.000 $25.000 $40.000 $50.000 $60.000 $75.000 $15.000
MTL W-BEAM GD FEN (TIM POST)
LF 700.000 $25.000 $28.000 $25.000 $25.000 $21.000 $30.000 $25.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $1,650.000 $1,600.000 $1,450.000 $1,500.000 $3,000.000 $2,000.000 $2,500.000
REMOVE METAL BEAM GUARD FENCE
LF 800.000 $4.000 $4.000 $4.000 $2.500 $2.000 $10.000 $3.500 $6.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,000.000 $2,600.000 $2,650.000 $2,500.000 $3,000.000 $2,820.000 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $350.000 $183.000 $200.000 $200.000 $250.000 $1,500.000 $280.000 $700.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $22.000 $20.000 $20.000 $35.000 $15.000 $30.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $30.000 $13.000 $35.000 $35.000 $35.000 $15.000 $50.000 $50.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 90.000 $4.000 $7.000 $5.000 $6.000 $8.000 $7.000 $5.600 $6.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 192.000 $4.000 $6.000 $5.000 $6.000 $8.000 $7.000 $5.600 $6.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 270.000 $3.000 $4.000 $5.000 $6.000 $5.000 $7.000 $5.600 $6.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 576.000 $4.000 $4.000 $5.000 $6.000 $5.000 $7.000 $5.600 $6.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $22.000 $20.000 $13.000 $18.000 $15.000 $15.000 $14.600 $16.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 329.000 $1.000 $1.000 $1.000 $3.000 $1.000 $20.000 $4.500 $5.000
PAVEMENT SEALER 4"
LF 3,380.000 $0.500 $2.000 $0.150 $0.300 $0.300 $2.150 $0.450 $0.200
REFL PAV MRKR TY II-A-A
EA 49.000 $3.000 $6.000 $1.000 $6.000 $10.000 $7.000 $5.600 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 2,780.000 $0.500 $3.000 $1.000 $1.300 $1.000 $3.000 $1.150 $2.000
PAV SURF PREP FOR MRK (6")
LF 3,380.000 $0.500 $1.000 $0.400 $0.700 $0.250 $2.400 $0.450 $0.500
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 14.000 $25.000 $55.000 $30.000 $225.000 $65.000 $500.000 $50.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 280.000 $120.000 $50.000 $77.000 $110.000 $100.000 $60.000 $80.000 $200.000
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 600.000 $0.500 $10.000 $1.000 $1.500 $2.000 $3.000 $1.120 $2.000
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 2,010.000 $0.500 $10.000 $1.000 $1.500 $2.000 $3.000 $1.120 $2.000
REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)
LF 770.000 $0.500 $10.000 $1.000 $1.500 $2.000 $3.000 $1.120 $2.000
TMA (STATIONARY)
DAY 58.000 $200.000 $200.000 $77.000 $150.000 $200.000 $1,500.000 $350.000 $300.000
TMA (MOBILE OPERATION)
HR 20.000 $65.000 $100.000 $179.000 $0.100 $50.000 $400.000 $100.000 $30.000
Totals: $699,253.600 $692,721.000 $693,956.000 $706,665.100 $764,620.000 $1,051,356.000 $1,059,946.400 $1,262,702.000