HARRISON FM 1186 (0063-01-094)
Items: 41
County: HARRISON
Length: N/A
Highway: FM 1186
District: ATLANTA
Control Number: 0063-01-094
DBE Goal: N/A
Project: STP 2020(439)HES
Guaranty: N/A
Time: 305 WORKING DAYS
Engineer's Estimate: $2,187,578.20
Date: 03/04/2020 (6 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (12)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,187,578.20 | |||
| $1,847,139.90 |
-15.56%
-$340,438.30
|
|||
| $1,895,353.60 |
-13.36%
-$292,224.60
|
2.61%
$48,213.70
|
||
| $1,899,552.50 |
-13.17%
-$288,025.70
|
2.84%
$52,412.60
|
-0.22%
-$4,198.90
|
|
| $2,002,547.50 |
-8.46%
-$185,030.70
|
8.41%
$155,407.60
|
-5.42%
-$102,995.00
|
|
| $2,017,609.00 |
-7.77%
-$169,969.20
|
9.23%
$170,469.10
|
-0.75%
-$15,061.50
|
|
| $2,038,713.00 |
-6.81%
-$148,865.20
|
10.37%
$191,573.10
|
-1.05%
-$21,104.00
|
|
| $2,045,465.46 |
-6.5%
-$142,112.74
|
10.74%
$198,325.56
|
-0.33%
-$6,752.46
|
|
| $2,182,298.63 |
-0.24%
-$5,279.57
|
18.14%
$335,158.73
|
-6.69%
-$136,833.17
|
|
| $2,298,632.00 |
5.08%
$111,053.80
|
24.44%
$451,492.10
|
-5.33%
-$116,333.37
|
|
| $2,482,721.07 |
13.49%
$295,142.87
|
34.41%
$635,581.17
|
-8.01%
-$184,089.07
|
|
| $2,595,808.00 |
18.66%
$408,229.80
|
40.53%
$748,668.10
|
-4.55%
-$113,086.93
|
|
| $3,870,090.00 |
76.91%
$1,682,511.80
|
109.52%
$2,022,950.10
|
-49.09%
-$1,274,282.00
|
E
Engineer's Estimate
$2,187,578.20
1
Awarded
$1,847,139.90
Over/Under Est:
-15.56%
-$340,438.30
$1,895,353.60
Over/Under Est:
-13.36%
-$292,224.60
Amt Left:
2.61%
$48,213.70
$1,899,552.50
Over/Under Est:
-13.17%
-$288,025.70
Amt Left:
2.84%
$52,412.60
Delta:
-0.22%
-$4,198.90
$2,002,547.50
Over/Under Est:
-8.46%
-$185,030.70
Amt Left:
8.41%
$155,407.60
Delta:
-5.42%
-$102,995.00
$2,017,609.00
Over/Under Est:
-7.77%
-$169,969.20
Amt Left:
9.23%
$170,469.10
Delta:
-0.75%
-$15,061.50
$2,038,713.00
Over/Under Est:
-6.81%
-$148,865.20
Amt Left:
10.37%
$191,573.10
Delta:
-1.05%
-$21,104.00
$2,045,465.46
Over/Under Est:
-6.5%
-$142,112.74
Amt Left:
10.74%
$198,325.56
Delta:
-0.33%
-$6,752.46
$2,182,298.63
Over/Under Est:
-0.24%
-$5,279.57
Amt Left:
18.14%
$335,158.73
Delta:
-6.69%
-$136,833.17
$2,298,632.00
Over/Under Est:
5.08%
$111,053.80
Amt Left:
24.44%
$451,492.10
Delta:
-5.33%
-$116,333.37
$2,482,721.07
Over/Under Est:
13.49%
$295,142.87
Amt Left:
34.41%
$635,581.17
Delta:
-8.01%
-$184,089.07
$2,595,808.00
Over/Under Est:
18.66%
$408,229.80
Amt Left:
40.53%
$748,668.10
Delta:
-4.55%
-$113,086.93
$3,870,090.00
Over/Under Est:
76.91%
$1,682,511.80
Amt Left:
109.52%
$2,022,950.10
Delta:
-49.09%
-$1,274,282.00
Bid Items & Bid Tabulations
41
Total
0 of 41