HARRIS VARIOUS (0912-72-801)

Items: 8

County: HARRIS
Length: 0.0000 MILES
Highway: VARIOUS
District: HOUSTON
Control Number: 0912-72-801
DBE Goal: 0.0%
Project: C 912-72-801
Guaranty: $94,000.00
Time: 298 WORKING DAYS
Engineer's Estimate: $4,715,636.00
Date: 11/07/2024 (1 year ago)
Contract Number: 11243213
Type: REHABILITATE BRIDGE
Project ID: A00209446
Project Description: CLEAN AND SEAL BRIDGE JOINTS
Mail/Deliver Bids To: N/A
PHILLIP GARLIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (10)
E
Engineer's Estimate
$4,715,636.00
$3,348,460.00
Over/Under Est: -28.99% -$1,367,176.00
$3,489,769.20
Over/Under Est: -26% -$1,225,866.80
Amt Left: 4.22% $141,309.20
Over/Under Est: -22.09% -$1,041,806.40
Amt Left: 9.72% $325,369.60
Delta: -5.27% -$184,060.40
Over/Under Est: -16.55% -$780,507.60
Amt Left: 17.52% $586,668.40
Delta: -7.11% -$261,298.80
$4,192,785.60
Over/Under Est: -11.09% -$522,850.40
Amt Left: 25.22% $844,325.60
Delta: -6.55% -$257,657.20
Over/Under Est: -6.39% -$301,300.00
Amt Left: 31.83% $1,065,876.00
Delta: -5.28% -$221,550.40
Over/Under Est: 3.62% $170,940.00
Amt Left: 45.94% $1,538,116.00
Delta: -10.70% -$472,240.00
Over/Under Est: 3.93% $185,300.80
Amt Left: 46.36% $1,552,476.80
Delta: -0.29% -$14,360.80
Over/Under Est: 5.17% $243,772.00
Amt Left: 48.11% $1,610,948.00
Delta: -1.19% -$58,471.20
Over/Under Est: 36.52% $1,721,990.80
Amt Left: 92.26% $3,089,166.80
Delta: -29.81% -$1,478,218.80

Bid Items & Bid Tabulations

8 Total 0 of 8
HARRIS  |  VARIOUS  |  HOUSTON  |  0912-72-801  |  11/07/2024  |  $4,715,636.00  |  C 912-72-801  |  REHAB BRIDGE  |  298 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
ISI CONTRACTING, INC.
SCR CIVIL CONSTRUCTION, LLC
SELECT MAINTENANCE, L.L.C.
MC2 CIVIL, LLC
B & MS CONSTRUCTION, INC.
ROY JORGENSEN ASSOCIATES, INC.
STRUCTURAL INTEGRITY GROUP LLC
MB WESTERN INDUSTRIAL CONTRACTING CO.
SOUTHERN ROAD & BRIDGE, LLC
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,200.000 $230.000 $180.000 $147.000 $300.000 $123.500 $200.000 $270.000 $285.000 $130.000 $225.000 $678.000
MOBILIZATION
LS 1.000 $400,000.000 $400,000.000 $260,000.000 $170,000.000 $625,000.000 $400,000.000 $225,000.000 $480,000.000 $225,000.000 $450,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $20,000.000 $5,000.000 $8,990.000 $2,400.000 $55,000.000 $2,500.000 $3,800.000 $22,000.000 $57,000.000 $10,000.000 $18,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 2,044.000 $130.000 $100.000 $202.000 $50.000 $65.000 $30.000 $150.000 $100.000 $85.000 $100.000 $60.000
TMA (STATIONARY)
DAY 1,192.000 $200.000 $300.000 $75.000 $225.000 $75.000 $250.000 $100.000 $250.000 $230.000 $250.000 $150.000
JT CLEANING AND SEALING(TRANS CNTR JTS)
LF 23,744.000 $43.000 $30.000 $28.000 $32.000 $29.000 $39.000 $36.000 $27.500 $44.000 $25.000 $58.000
JT CLEANING AND SEALING (EXPANSION JTS)
LF 52,925.600 $40.000 $25.000 $32.000 $36.000 $29.000 $41.000 $45.000 $47.500 $43.000 $55.000 $58.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 750.000 $210.000 $100.000 $113.000 $106.000 $75.000 $90.000 $210.000 $175.000 $90.000 $150.000 $205.000
Totals: $4,715,636.000 $3,348,460.000 $3,489,769.200 $3,673,829.600 $3,935,128.400 $4,192,785.600 $4,414,336.000 $4,886,576.000 $4,900,936.800 $4,959,408.000 $6,437,626.800