HARRIS IH 45 (0110-05-132)

Items: 29

County: HARRIS
Length: N/A
Highway: IH 45
District: HOUSTON
Control Number: 0110-05-132
DBE Goal: N/A
Project: NH 1902(176)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $1,708,903.55
Date: 07/10/2019 (6 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,708,903.55
Over/Under Est: 0.85% $14,480.53
Over/Under Est: 4.57% $78,144.70
Amt Left: 3.69% $63,664.17
$2,343,781.75
Over/Under Est: 37.15% $634,878.20
Amt Left: 36% $620,397.67
Delta: -31.15% -$556,733.50

Bid Items & Bid Tabulations

29 Total 0 of 29
HARRIS  |  IH 45  |  HOUSTON  |  0110-05-132  |  07/10/2019  |  $1,708,903.55  |  NH 1902(176)  |  LANDSCAPE DEVELOPMENT  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
APEX LANDSCAPE & IRRIGATION, LLC
TEXAS WALL & LANDSCAPE
PREPARING ROW
AC 0.250 $20,000.000 $80,701.754 $25,000.000 $30,000.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 11.000 $800.000 $398.724 $500.000 $1,000.000
PREP ROW (TREE) (2" TO 12" DIA)
EA 84.000 $250.000 $122.180 $500.000 $1,000.000
FURNISHING AND PLACING TOPSOIL
CY 32.000 $30.000 $47.971 $35.000 $85.000
EROSION CONTROL COMPOST
CY 3,377.500 $27.000 $21.401 $25.000 $40.000
GENERAL USE COMPOST
CY 1,156.000 $29.000 $21.763 $25.000 $50.000
BROADCAST SEED (PERM)(SPECIAL MIX)
SY 1,173.000 $1.100 $0.374 $1.750 $15.000
FERTILIZER
AC 0.250 $900.000 $1,754.386 $900.000 $1,000.000
VEGETATIVE WATERING
MG 30.000 $125.000 $38.012 $1.000 $50.000
WILDFLOWER SEEDING
AC 105.000 $1,250.000 $1,971.596 $1,500.000 $3,150.000
PLANT MATERIAL (3-GAL)
EA 915.000 $12.500 $13.038 $25.000 $40.000
PLANT MATERIAL (5 GAL) (TREE)
EA 2,668.000 $15.000 $13.809 $30.000 $60.000
PLANT MATERIAL (15 GAL) (TREE)
EA 1,499.000 $100.000 $90.119 $135.000 $275.000
PLANT MATERIAL (30 GAL) (TREE)
EA 1,222.000 $350.000 $183.765 $250.000 $355.000
PLANT MATERIAL (3 GAL) (SHRUB)
EA 653.000 $15.000 $20.956 $25.000 $47.000
PLANT BED PREP (TYPE III)
SY 20,764.000 $1.000 $0.507 $3.000 $2.950
PLANT MAINTENANCE
MO 18.000 $9,500.000 $10,830.493 $6,500.000 $4,000.000
PLANT MAINTENANCE
CYC 9.000 $17,500.000 $15,410.331 $22,000.000 $8,000.000
MOBILIZATION
LS 1.000 $155,355.000 $173,245.614 $270,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $3,333.333 $9,500.000 $22,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 500.000 $6.000 $4.211 $2.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $1.000 $0.351 $0.600 $1.000
PRUNING
CYC 1.000 $145,000.000 $147,368.421 $25,000.000 $36,000.000
PRUNING AND TRIMMING TREES AND SHRUBS
CYC 1.000 $52,000.000 $236,842.105 $50,000.000 $54,000.000
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 29,253.000 $0.500 $0.159 $0.350 $0.200
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 29,253.000 $0.500 $0.144 $0.350 $0.100
LANDSCAPE SOIL AMENDMENT (TYPE III)
SY 5,389.000 $1.250 $0.966 $1.900 $3.000
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 26,945.000 $0.500 $0.282 $0.950 $1.250
LANDSCAPE SOIL AMENDMENT (TYPE V)
SY 6,957.000 $0.500 $2.329 $0.650 $0.400
Totals: $1,708,903.550 $1,723,384.182 $1,787,048.250 $2,343,781.750