GUADALUPE SH 123 (0366-02-096)

Items: 78

County: GUADALUPE
Length: 7.3030 MILES
Highway: SH 123
District: SAN ANTONIO
Control Number: 0366-02-096
DBE Goal: 0.0%
Project: F 2026(379)
Guaranty: $99,000.00
Time: 109 WORKING DAYS
Engineer's Estimate: $4,974,109.85
Date: 02/05/2026 (4 months ago)
Contract Number: 2263202
Type: RESURFACE ROADWAY
Project ID: A00188227
Contract Type: Federal
Project Description: BASE REPAIR, MILL, INLAY & PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ADDRESSLUKE STORY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$4,974,109.85
$4,323,419.08
Over/Under Est: -13.08% -$650,690.77
Over/Under Est: -10.86% -$540,225.53
Amt Left: 2.56% $110,465.24
Over/Under Est: -8.81% -$438,075.95
Amt Left: 4.92% $212,614.82
Delta: -2.30% -$102,149.58
Over/Under Est: -8.09% -$402,171.41
Amt Left: 5.75% $248,519.36
Delta: -0.79% -$35,904.54
Over/Under Est: -8.02% -$398,914.08
Amt Left: 5.82% $251,776.69
Delta: -0.07% -$3,257.33
$4,799,863.26
Over/Under Est: -3.5% -$174,246.59
Amt Left: 11.02% $476,444.18
Delta: -4.91% -$224,667.49
$5,564,516.41
Over/Under Est: 11.87% $590,406.56
Amt Left: 28.71% $1,241,097.33
Delta: -15.93% -$764,653.15

Bid Items & Bid Tabulations

78 Total 0 of 78
GUADALUPE  |  SH 123  |  SAN ANTONIO  |  0366-02-096  |  02/05/2026  |  $4,974,109.85  |  F 2026(379)  |  RESURF ROADWAY  |  109 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CLARK CONSTRUCTION OF TEXAS, INC.
HUNTER INDUSTRIES, LTD.
LONE STAR PAVING COMPANY
DEAN WORD COMPANY, LTD.
TEXAS MATERIALS GROUP, INC.
BOBCAT SERVICES, INC.
ALLEN KELLER COMPANY
REMOV CONC (MOWSTRIP)
CY 414.000 $195.000 $35.000 $148.400 $73.000 $80.600 $120.000 $104.600 $146.960
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 4,436.000 $78.000 $96.870 $75.410 $96.000 $96.800 $95.000 $84.960 $102.770
SP MIXES SP-C SAC-B PG76-22
TON 25,980.000 $87.000 $92.080 $75.360 $84.300 $80.000 $83.000 $87.150 $100.830
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 4,281.000 $52.000 $49.410 $41.580 $48.000 $59.500 $51.000 $44.130 $54.090
PLANE ASPH CONC PAV(2")
SY 225,915.000 $1.500 $0.880 $1.060 $1.500 $1.200 $1.500 $1.050 $0.950
RIPRAP (CONC)(4 IN)
CY 92.000 $641.000 $600.000 $892.000 $518.000 $572.400 $800.000 $1,005.060 $867.890
RIPRAP (MOW STRIP)(5 IN)
CY 409.000 $396.000 $615.000 $550.000 $512.000 $628.600 $650.000 $543.210 $525.990
CLEANING AND SEALING EXISTING JOINTS
LF 434.000 $36.000 $50.000 $52.000 $38.000 $51.600 $40.000 $46.900 $38.960
MOBILIZATION
LS 1.000 $449,451.830 $62,000.000 $250,565.080 $174,000.000 $315,000.000 $145,000.000 $283,197.370 $528,800.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,900.000 $1,732.000 $9,961.520 $1,700.000 $20,500.000 $8,000.000 $14,369.120 $4,527.110
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,623.130 $1,167.010 $4,221.810 $10,063.000 $12,550.000 $3,500.000 $4,580.470 $11,763.700
TMA (STATIONARY)
DAY 62.000 $180.000 $90.000 $84.440 $300.000 $468.200 $10.000 $312.000 $259.780
TMA (MOBILE OPERATION)
DAY 149.000 $106.060 $90.000 $225.160 $300.000 $10.000 $10.000 $312.000 $383.910
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $3.000 $3.500 $3.640 $3.000 $1.000 $5.000 $3.030 $3.610
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $1.000 $0.500 $0.520 $1.500 $1.000 $1.000 $1.520 $0.740
ONE-WAY TRAF CONT (PILOT CAR)
HR 344.000 $80.500 $100.000 $77.000 $100.000 $10.000 $75.000 $57.410 $197.600
MTL W-BEAM GD FEN (TIM POST)
LF 4,962.500 $25.000 $28.500 $25.270 $22.000 $24.200 $22.000 $23.070 $22.330
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $33.000 $38.000 $87.840 $30.000 $33.100 $30.000 $25.640 $77.610
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,990.000 $2,500.000 $2,499.550 $1,830.000 $2,019.400 $2,100.000 $2,083.500 $2,785.270
SHORT RADIUS (28")
LF 137.500 $45.000 $38.000 $53.930 $40.000 $44.200 $40.000 $36.210 $47.660
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,287.000 $1,200.000 $1,822.840 $1,260.000 $1,396.000 $1,260.000 $1,213.200 $1,610.660
MTL BM GD FEN TRANS (31"-28")
EA 5.000 $473.000 $500.000 $2,115.290 $1,580.000 $1,746.900 $1,575.000 $1,146.490 $1,869.080
REMOVE METAL BEAM GUARD FENCE
LF 5,525.000 $5.130 $3.000 $2.890 $2.300 $2.600 $2.350 $6.060 $2.550
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $300.000 $225.000 $160.340 $200.000 $222.300 $200.000 $569.740 $141.680
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $327.000 $500.000 $192.640 $200.000 $222.300 $200.000 $313.630 $170.220
GUARDRAIL END TREATMENT (REMOVE)
EA 38.000 $306.000 $250.000 $230.980 $226.000 $250.100 $225.000 $419.680 $204.100
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 37.000 $3,255.000 $3,200.000 $3,537.340 $3,370.000 $3,723.300 $3,350.000 $3,401.100 $3,125.600
REMOVE ELECTRICAL SERVICES
EA 2.000 $1,536.000 $583.510 $2,090.430 $765.000 $1,787.200 $1,610.000 $1,624.080 $1,566.090
ALUMINUM SIGNS (TY A)
SF 27.000 $37.000 $25.000 $26.000 $30.000 $27.800 $25.000 $30.300 $130.140
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 64.000 $731.000 $650.000 $624.010 $680.000 $666.900 $600.000 $701.950 $852.790
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 28.000 $794.000 $750.000 $728.010 $780.000 $778.000 $700.000 $802.950 $967.240
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 7.000 $800.000 $810.000 $806.010 $830.000 $861.400 $775.000 $858.500 $1,073.530
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $858.000 $885.000 $780.010 $830.000 $833.600 $750.000 $934.250 $1,094.040
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $1,096.000 $785.000 $936.010 $805.000 $1,000.300 $900.000 $833.250 $1,273.700
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $1,236.000 $885.000 $1,014.010 $905.000 $1,083.600 $975.000 $934.250 $1,777.460
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,163.000 $940.000 $1,014.010 $956.000 $1,083.600 $975.000 $1,010.000 $1,324.390
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 3.000 $1,302.000 $1,095.000 $1,040.010 $1,107.000 $1,111.400 $1,000.000 $1,136.250 $1,444.760
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 1.000 $1,960.000 $1,980.000 $1,456.020 $2,013.000 $1,556.000 $1,400.000 $2,474.500 $1,808.080
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 3.000 $333.000 $145.000 $156.000 $150.000 $166.700 $150.000 $151.500 $825.920
REMOVE SM RD SN SUP&AM
EA 111.000 $113.000 $95.000 $104.000 $100.000 $111.100 $100.000 $111.100 $61.660
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 3.000 $53.000 $30.000 $26.000 $35.000 $27.800 $25.000 $50.500 $61.620
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2(BI)
EA 142.000 $38.000 $30.000 $31.200 $35.000 $33.300 $30.000 $25.780 $25.710
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 55.000 $24.000 $25.000 $26.000 $25.000 $27.800 $25.000 $15.820 $38.320
INSTL OM ASSM (OM-2Z)(WFLX)GNDHH
EA 10.000 $114.000 $190.000 $130.000 $200.000 $138.900 $125.000 $211.730 $132.190
INSTL OM ASSM (OM-2Z)(WFLX)SRFHH
EA 30.000 $60.000 $190.000 $130.000 $200.000 $138.900 $125.000 $211.750 $132.160
INSTL OM ASSM (OM-2Z)(WFLX)SRFHH(BI)
EA 5.000 $400.000 $190.000 $130.000 $200.000 $138.900 $125.000 $211.800 $132.120
INSTL OM SM RD SIGN (1-OM-PW)Y
EA 99.000 $11.000 $65.000 $10.400 $70.000 $11.100 $10.000 $18.220 $42.330
INSTL OM SM RD SIGN (1-OM-PW)R
EA 17.000 $11.000 $65.000 $10.400 $70.000 $11.100 $10.000 $18.200 $42.310
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,783.000 $0.840 $0.530 $1.720 $0.750 $2.300 $1.000 $0.450 $3.280
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,718.000 $1.390 $0.530 $1.720 $0.750 $2.000 $1.000 $0.470 $3.310
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 39.000 $1.190 $1.000 $1.560 $1.000 $1.100 $1.000 $1.010 $1.460
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,175.000 $1.000 $1.000 $0.880 $1.000 $0.900 $0.800 $1.010 $0.830
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 449.000 $5.340 $8.000 $8.320 $8.000 $6.700 $6.000 $8.080 $7.800
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 20.000 $136.000 $150.000 $135.200 $150.000 $164.500 $148.000 $176.750 $126.610
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 20.000 $186.000 $175.000 $161.200 $176.000 $166.700 $150.000 $202.000 $150.960
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 5.000 $60.000 $35.000 $58.240 $35.000 $44.500 $40.000 $35.350 $54.540
REFL PAV MRK TY I (Y)6"(DOT)(100MIL)
LF 30.000 $1.300 $1.000 $1.560 $1.000 $1.100 $1.000 $1.010 $1.460
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 6.000 $357.000 $375.000 $364.010 $378.000 $361.200 $325.000 $378.750 $340.870
PAVEMENT SLER 6"
LF 175,833.000 $0.200 $0.200 $0.180 $0.200 $0.160 $0.140 $0.200 $0.170
PAVEMENT SLER 8"
LF 5,175.000 $0.300 $0.250 $0.310 $0.250 $0.200 $0.180 $0.250 $0.290
PAVEMENT SLER 24"
LF 449.000 $2.450 $2.000 $3.120 $2.000 $0.800 $0.700 $2.020 $2.920
PAVEMENT SLER (ARROW)
EA 20.000 $74.000 $75.000 $104.000 $76.000 $11.100 $10.000 $75.750 $97.390
PAVEMENT SLER (WORD)
EA 20.000 $84.000 $75.000 $130.000 $76.000 $11.100 $10.000 $75.750 $121.740
PAVEMENT SLER (MED NOSE)
EA 6.000 $134.000 $100.000 $260.000 $100.000 $44.500 $40.000 $101.000 $243.480
PAVEMENT SLER (YLD TRI)
EA 5.000 $10.000 $15.000 $36.400 $15.000 $111.100 $30.000 $15.150 $34.090
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 8,410.000 $0.600 $0.520 $0.570 $0.500 $0.600 $0.550 $0.570 $0.530
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 74,250.000 $0.610 $0.520 $0.570 $0.500 $0.600 $0.550 $0.570 $0.530
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 4,080.000 $0.520 $0.520 $0.570 $0.500 $0.600 $0.550 $0.570 $0.530
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 89,024.000 $0.510 $0.520 $0.570 $0.500 $0.600 $0.550 $0.570 $0.530
REFL PAV MRKR TY I-C
EA 691.000 $4.950 $3.750 $4.160 $3.800 $4.000 $3.650 $4.290 $3.890
REFL PAV MRKR TY II-A-A
EA 2,708.000 $4.800 $3.750 $4.160 $3.800 $3.900 $3.650 $4.290 $3.890
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 2.000 $756.000 $583.510 $2,459.630 $2,013.000 $2,102.800 $1,900.000 $1,912.940 $1,842.690
LITTER REMOVAL
CYC 14.000 $5,000.000 $1.180 $2,000.000 $50.000 $877.900 $1,200.000 $1,935.810 $2,434.830
LITTER REMOVAL (SPOT)
AC 129.000 $10.000 $4.550 $110.000 $50.000 $10.200 $85.000 $37.790 $73.050
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
CYC 14.000 $75.000 $1.180 $2,200.000 $50.000 $580.600 $1,200.000 $1,865.240 $1,947.870
DEBRIS REMOVAL (SPOT DEBRIS)
MI 7.100 $2,500.000 $82.200 $1,400.000 $50.000 $175.900 $1,200.000 $1,725.230 $486.970
UNDERSEAL COURSE
GAL 52,577.000 $4.000 $0.020 $3.890 $3.200 $0.010 $3.350 $3.210 $4.230
BONDING COURSE
GAL 856.000 $1.320 $3.930 $2.850 $3.200 $3.700 $3.350 $2.860 $4.280
Totals: $4,974,109.850 $4,323,419.080 $4,433,884.310 $4,536,033.900 $4,571,938.440 $4,575,195.770 $4,799,863.253 $5,564,516.402
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $64,800.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $69,800.00