GREGG US0259 (6318-13-001)

Items: 20

County: GREGG
Length: N/A
Highway: US0259
District: TYLER
Control Number: 6318-13-001
DBE Goal: N/A
Project: BPM - 631813001
Guaranty: N/A
Time: 77 W
Engineer's Estimate: $196,634.83
Date: 02/06/2018 (8 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (12)
E
Engineer's Estimate
$196,634.83
Over/Under Est: -14.63% -$28,775.33
Over/Under Est: -11.53% -$22,668.83
Amt Left: 3.64% $6,106.50
$177,164.09
Over/Under Est: -9.9% -$19,470.74
Amt Left: 5.54% $9,304.59
Delta: -1.84% -$3,198.09
Over/Under Est: -7.46% -$14,664.83
Amt Left: 8.41% $14,110.50
Delta: -2.71% -$4,805.91
$195,194.50
Over/Under Est: -0.73% -$1,440.33
Amt Left: 16.28% $27,335.00
Delta: -7.27% -$13,224.50
Over/Under Est: -0.22% -$433.13
Amt Left: 16.88% $28,342.20
Delta: -0.52% -$1,007.20
Over/Under Est: 4.5% $8,851.17
Amt Left: 22.42% $37,626.50
Delta: -4.73% -$9,284.30
Over/Under Est: 5.12% $10,071.17
Amt Left: 23.14% $38,846.50
Delta: -0.59% -$1,220.00
Over/Under Est: 14.85% $29,200.17
Amt Left: 34.54% $57,975.50
Delta: -9.25% -$19,129.00
Over/Under Est: 15.36% $30,212.07
Amt Left: 35.14% $58,987.40
Delta: -0.45% -$1,011.90
Over/Under Est: 25.91% $50,946.17
Amt Left: 47.49% $79,721.50
Delta: -9.14% -$20,734.10
Over/Under Est: 81.08% $159,425.17
Amt Left: 112.12% $188,200.50
Delta: -43.82% -$108,479.00

Bid Items & Bid Tabulations

20 Total 0 of 20
GREGG  |  US0259  |  TYLER  |  6318-13-001  |  02/06/2018  |  $196,634.83  |  BPM - 631813001  |  BRIDGE PREVENT MAINT  |  77 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
RED BARON BUILDING COMPANY, L.L.C.
CHAMPION INFRASTRUCTURE, LLC
L.C. JORDAN & SON
HARTBEAT CONSTRUCTION
PIERCE R & B LLC
CROSS PLUS CONSTRUCTION, LLC
STATELINE CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
R & G CONSTRUCTION, LLC
HIGHWAY 19 CONSTRUCTION LLC
IOWA BRIDGE & CULVERT, LC
EXCAVATION (CHANNEL)
CY 784.000 $25.000 $16.000 $30.000 $17.000 $25.000 $24.000 $23.000 $19.000 $30.000 $35.000 $70.000 $15.000 $100.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 124.000 $65.000 $24.000 $35.000 $20.000 $30.000 $32.000 $29.000 $45.000 $30.000 $35.000 $100.000 $30.000 $250.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 82.000 $5.000 $1.750 $5.000 $3.000 $5.000 $2.000 $12.000 $25.000 $5.000 $50.000 $10.000 $1.000 $30.000
VEGETATIVE WATERING
MG 0.900 $1,000.000 $1,000.000 $600.000 $0.100 $100.000 $85.000 $123.000 $1,000.000 $40.000 $2,500.000 $1.000 $10.000 $5,000.000
FLOWABLE BACKFILL
CY 74.000 $300.000 $300.000 $210.000 $400.000 $320.000 $350.000 $223.000 $385.000 $300.000 $350.000 $300.000 $250.000 $500.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 36.000 $300.000 $150.000 $180.000 $200.000 $300.000 $185.000 $154.000 $225.000 $185.000 $1,000.000 $190.000 $250.000 $200.000
RIPRAP (CONC) (CL B) (6")
CY 4.000 $600.000 $650.000 $940.000 $750.000 $714.000 $850.000 $567.000 $1,000.000 $650.000 $650.000 $450.000 $750.000 $1,000.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 91.000 $300.000 $225.000 $320.000 $200.000 $170.000 $175.000 $360.000 $195.000 $185.000 $185.000 $177.000 $250.000 $350.000
CLEANING AND SEALING EXISTING JOINTS
LF 424.000 $50.000 $34.000 $60.000 $40.000 $36.000 $45.000 $54.000 $55.000 $40.000 $50.000 $26.000 $45.000 $150.000
REMOV STR (PIPE)
LF 30.000 $10.000 $25.000 $40.000 $25.000 $30.000 $50.000 $45.000 $15.000 $100.000 $35.000 $10.000 $50.000 $100.000
MOBILIZATION
LS 1.000 $17,194.260 $40,000.000 $21,000.000 $20,000.000 $30,000.000 $19,300.000 $20,000.000 $19,000.000 $20,000.000 $22,000.000 $15,000.000 $40,000.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $1,500.000 $3,200.000 $3,000.000 $7,500.000 $6,000.000 $4,000.000 $8,500.000 $10,000.000 $8,500.000 $1,500.000 $5,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 100.000 $50.000 $45.000 $60.000 $35.000 $55.000 $55.000 $23.000 $30.000 $50.000 $30.000 $100.000 $35.000 $100.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $20.000 $35.000 $15.000 $5.000 $10.000 $12.000 $23.000 $10.000 $6.000 $15.000 $50.000 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 270.000 $3.150 $4.500 $5.000 $5.000 $5.000 $3.500 $3.000 $3.000 $3.000 $4.000 $10.000 $3.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 270.000 $2.000 $3.500 $2.000 $1.000 $3.000 $1.500 $3.000 $1.000 $1.500 $2.000 $5.000 $1.000 $5.000
TREE AND BRUSH REMOVAL
AC 0.790 $7,633.000 $5,000.000 $2,600.000 $2,500.000 $3,000.000 $12,000.000 $4,000.000 $15,000.000 $30,000.000 $5,000.000 $6,000.000 $10,000.000 $5,000.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 30.000 $75.000 $50.000 $15.000 $20.000 $20.000 $150.000 $34.000 $125.000 $40.000 $50.000 $159.000 $50.000 $100.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 341.000 $100.000 $45.000 $42.000 $105.000 $50.000 $75.000 $99.000 $75.000 $50.000 $50.000 $115.000 $200.000 $50.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 80.000 $100.000 $125.000 $85.000 $155.000 $100.000 $185.000 $200.000 $115.000 $150.000 $100.000 $165.000 $250.000 $50.000
Totals: $196,634.830 $167,859.500 $173,966.000 $177,164.090 $181,970.000 $195,194.500 $196,201.700 $205,486.000 $206,706.000 $225,835.000 $226,846.900 $247,581.000 $356,060.000