GREGG FM 2275 (2158-01-019)

Items: 167

County: GREGG
Length: 0.0000 MILES
Highway: FM 2275
District: TYLER
Control Number: 2158-01-019
DBE Goal: 4.0%
Project: F 2025(527)
Guaranty: $100,000.00
Time: 473 WORKING DAYS
Engineer's Estimate: $25,999,390.20
Date: 08/07/2025 (10 months ago)
Contract Number: 8253002
Type: WIDEN ROAD - ADD LANES
Project ID: A00049652
Contract Type: Federal
Project Description: WIDEN 2 LNS TO 4 LN DIVIDED ROADWAY W/FLUSH MEDIAN
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$25,999,390.20
$22,863,768.44
Over/Under Est: -12.06% -$3,135,621.76
Over/Under Est: -8.41% -$2,186,134.36
Amt Left: 4.15% $949,487.40
$24,260,513.64
Over/Under Est: -6.69% -$1,738,876.56
Amt Left: 6.11% $1,396,745.20
Delta: -1.88% -$447,257.80
Over/Under Est: 16.29% $4,236,104.80
Amt Left: 32.24% $7,371,726.56
Delta: -24.63% -$5,974,981.36
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 1.48% $338,383.77
FARR FOUNDATION, INC. 1.45% $331,524.64
CAP RIVER LLC 1.24% $283,510.73
TORO BRAVO CONSTRUCTION, LLC 1.20% $274,365.22
WITHERS CONSTRUCTION, LLC 1.17% $267,506.09
STRIPING TECHNOLOGY, L.P. 0.63% $144,041.74
KITECO PROPERTY SOLUTIONS INC. 0.30% $68,591.31
SOUTHWEST ENVIRONMENT SERVICES LLC 0.17% $38,868.41
MORRIS COUNTY CONTRACTORS, L.L.C. 0.13% $29,722.90
FLEX SUPPLY, LLC 0.10% $22,863.77
Total: 7.87% $1,799,378.58

Bid Items & Bid Tabulations

167 Total 0 of 167
GREGG  |  FM 2275  |  TYLER  |  2158-01-019  |  08/07/2025  |  $25,999,390.20  |  F 2025(527)  |  WIDEN ROAD - ADD LANES  |  473 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONGVIEW BRIDGE AND ROAD, LTD.
TRUE ROADS CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
JAMES CONSTRUCTION GROUP, LLC
PREPARING ROW
STA 107.000 $6,000.000 $8,500.000 $3,350.000 $7,000.000 $28,037.390
REMOV CONC (DRIVEWAYS)
SY 1,986.000 $25.000 $16.000 $12.000 $16.000 $12.420
REMOV CONC (MISC)
SY 236.000 $25.000 $30.000 $16.000 $16.000 $13.580
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 31,202.000 $10.000 $5.750 $4.250 $5.400 $3.070
RMV (0"-6") TRT/UNTRT BASE & ASPH PAV
SY 2,383.000 $12.000 $8.500 $5.500 $6.500 $3.070
EXCAV (ROADWAY)
CY 86,171.000 $10.000 $6.000 $12.500 $10.000 $15.550
EMBANK (FNL)(DC)(TY C)
CY 29,672.000 $18.000 $11.000 $16.500 $15.000 $15.230
FURN & PLACE TOPSOIL (4")
SY 46,173.000 $2.500 $2.600 $2.750 $2.000 $1.240
BLOCK SODDING
SY 14,772.000 $10.000 $6.300 $5.600 $5.750 $5.120
BROADCAST SEED (PERM_RURAL_SAND)
SY 23,087.000 $0.500 $0.250 $0.140 $0.150 $0.130
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 46,173.000 $1.000 $0.950 $0.580 $0.590 $0.530
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 23,087.000 $0.750 $0.920 $0.570 $0.580 $0.520
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 23,087.000 $0.750 $0.920 $0.570 $0.580 $0.520
VEGETATIVE WATERING
TGL 1,083.000 $10.000 $14.500 $12.000 $5.000 $35.000
FL BS (CMP IN PLC)(TY A GR 1-2) (8")
SY 77,406.000 $28.000 $29.000 $30.500 $28.000 $33.920
LIME (QUICKLIME (DRY))
TON 673.000 $300.000 $390.000 $360.000 $375.000 $380.360
LIME TRT (EXIST MATL)(8")
SY 37,395.000 $8.000 $2.250 $5.250 $4.250 $5.820
CEMENT
TON 673.000 $275.000 $290.000 $265.000 $285.000 $283.790
CEMENT TRT (EXIST MATL)(8")
SY 37,395.000 $5.000 $2.250 $3.750 $3.250 $2.340
PRIME COAT & BLOTTER (MC-30)
GAL 21,817.000 $7.000 $6.750 $7.000 $5.750 $7.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 66,951.000 $6.000 $4.500 $5.250 $5.000 $6.000
AGGR (TY-PD OR PL, GR-3)(SAC-A)
CY 74.000 $200.000 $210.000 $320.000 $195.000 $300.000
AGGR (TY-PD OR PL, GR-4)
CY 1,383.000 $200.000 $185.000 $225.000 $185.000 $200.000
SP MIXES SP-B PG64-22
TON 864.000 $220.000 $185.000 $190.000 $177.000 $230.000
SP MIXES SP-C PG64-22
TON 14,556.000 $160.000 $162.000 $172.000 $176.000 $188.000
SP MIXES SP-C SAC-A PG70-22
TON 8,735.000 $170.000 $178.000 $178.000 $182.000 $205.000
SP MIXES SP-D SAC-A PG64-22 (EXEMPT)
TON 266.000 $200.000 $200.000 $235.000 $180.000 $267.000
TACK COAT
GAL 15,213.000 $2.500 $4.000 $0.100 $5.000 $1.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 600.000 $65.000 $95.000 $135.000 $75.000 $67.300
PLANE ASPH CONC PAV(2")
SY 13,241.000 $2.500 $4.500 $2.950 $2.750 $1.720
CUT & RESTORE ASPH PAVING
SY 125.000 $135.000 $170.000 $160.000 $135.000 $141.320
CEM STABIL BKFL
CY 651.000 $325.000 $218.000 $300.000 $225.000 $166.180
FLOWABLE BACKFILL
CY 3.000 $415.000 $1,000.000 $465.000 $300.000 $393.120
TRENCH EXCAVATION PROTECTION
LF 3,349.000 $10.000 $9.500 $6.000 $10.000 $1.130
TEMPORARY SPL SHORING
SF 880.000 $50.000 $65.000 $44.000 $48.000 $51.880
SOIL NAIL ANCHORS
LF 7,917.000 $37.000 $33.000 $28.000 $32.000 $24.790
DRILL SHAFT (18 IN)
LF 56.000 $200.000 $275.000 $84.000 $70.000 $62.610
DRILL SHAFT (36 IN)
LF 1,712.000 $375.000 $320.000 $260.000 $270.000 $246.510
CL A CONC (MISC)
CY 47.000 $900.000 $675.000 $875.000 $1,000.000 $980.590
CL C CONC (ABUT)
CY 101.700 $1,250.000 $1,125.000 $1,125.000 $1,200.000 $1,600.000
CL C CONC (CAP)
CY 140.800 $1,500.000 $1,200.000 $1,000.000 $1,125.000 $1,700.000
CL C CONC (COLUMN)
CY 39.200 $1,600.000 $1,700.000 $2,000.000 $1,200.000 $2,500.000
REINF CONC SLAB
SF 41,854.000 $30.000 $26.500 $27.500 $30.000 $50.000
APPROACH SLAB
CY 163.000 $660.000 $815.000 $740.000 $900.000 $800.000
RETAINING WALL (SOIL NAIL) (FASCIA)
SF 8,034.000 $90.000 $105.000 $90.000 $85.000 $101.000
PRESTR CONC GIRDER (TX54)
LF 5,150.240 $230.000 $240.000 $280.000 $255.000 $240.860
RIPRAP (MOW STRIP)(4 IN)
CY 40.000 $725.000 $650.000 $700.000 $750.000 $735.000
RIPRAP (STONE TY R)(DRY)(18 IN)
CY 649.000 $250.000 $280.000 $190.000 $205.000 $224.240
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 1,789.000 $210.000 $210.000 $185.000 $205.000 $252.620
STR STEEL (MISC NON-BRIDGE)
LB 293.000 $30.000 $55.000 $25.000 $40.000 $28.190
RAIL (TY T223)
LF 544.000 $180.000 $210.000 $120.000 $125.000 $124.000
RAIL (TY C223)
LF 568.400 $250.000 $230.000 $185.000 $175.000 $164.840
RAIL (TY PR11)
LF 874.100 $200.000 $135.000 $110.000 $140.000 $110.740
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 245.000 $200.000 $220.000 $225.000 $200.000 $195.270
RC PIPE (CL III)(24 IN)
LF 6,894.000 $75.000 $75.000 $74.000 $87.000 $99.500
RC PIPE (CL III)(30 IN)
LF 802.000 $90.000 $100.000 $110.000 $115.000 $120.580
RC PIPE (CL III)(36 IN)
LF 406.000 $150.000 $150.000 $145.000 $155.000 $148.500
RC PIPE (CL IV)(24 IN)
LF 108.000 $135.000 $90.000 $95.000 $110.000 $100.950
RC PIPE (CL IV)(36 IN)
LF 272.000 $265.000 $180.000 $170.000 $185.000 $159.510
MANH (COMPL)(PRM)(48IN)
EA 1.000 $5,500.000 $7,500.000 $6,500.000 $8,500.000 $8,937.510
MANH (COMPL)(PRM)(60IN)
EA 2.000 $9,200.000 $9,900.000 $8,000.000 $10,000.000 $9,289.310
MANH (COMPL)(PRM)(72IN)
EA 4.000 $16,000.000 $13,850.000 $12,000.000 $13,500.000 $10,777.430
INLET (COMPL)(PSL)(RC)(3FTX3FT)
EA 2.000 $6,700.000 $7,000.000 $6,000.000 $7,700.000 $5,729.360
INLET (COMPL)(PSL)(RC)(4FTX4FT)
EA 1.000 $8,000.000 $8,000.000 $6,500.000 $8,500.000 $6,106.880
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 4.000 $8,500.000 $7,400.000 $6,500.000 $8,200.000 $8,604.110
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
EA 6.000 $8,500.000 $9,400.000 $8,500.000 $10,500.000 $8,507.300
INLET (COMPL)(CCO)(3FT)(BOTH)
EA 39.000 $5,000.000 $6,700.000 $7,800.000 $7,400.000 $5,430.240
INLET (COMPL)(CCO)(4FT)(BOTH)
EA 7.000 $8,000.000 $6,900.000 $8,200.000 $7,600.000 $6,363.240
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 2.000 $8,500.000 $9,500.000 $9,500.000 $8,500.000 $9,833.830
HEADWALL (CH - FW - 15) (DIA= 36 IN)
EA 3.000 $8,000.000 $9,200.000 $10,000.000 $7,000.000 $9,348.310
HEADWALL (CH - FW - 45) (DIA= 24 IN)
EA 2.000 $6,500.000 $9,000.000 $9,000.000 $6,500.000 $9,479.200
HEADWALL (CH - FW - 45) (DIA= 36 IN)
EA 2.000 $14,000.000 $10,750.000 $11,000.000 $10,500.000 $14,667.060
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $1,400.000 $1,450.000 $1,200.000 $1,150.000 $2,194.530
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 8.000 $1,500.000 $1,650.000 $1,400.000 $1,375.000 $2,293.610
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $3,000.000 $4,500.000 $3,500.000 $4,200.000 $4,707.620
REMOV STR (SET)
EA 22.000 $400.000 $545.000 $325.000 $250.000 $622.480
REMOV STR (PIPE)
LF 1,000.000 $16.000 $13.000 $14.000 $12.000 $13.940
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $175,000.000 $25,000.000 $30,000.000 $35,000.000 $44,303.800
MOBILIZATION
LS 1.000 $2,200,000.000 $2,150,000.000 $1,750,000.000 $2,000,000.000 $3,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 31.000 $7,500.000 $5,000.000 $2,500.000 $5,000.000 $27,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 100.000 $140.000 $135.000 $50.000 $100.000 $69.160
TMA (STATIONARY)
DAY 60.000 $350.000 $250.000 $200.000 $150.000 $743.150
TMA (MOBILE OPERATION)
DAY 30.000 $560.000 $375.000 $50.000 $150.000 $1,139.640
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 667.000 $35.000 $39.000 $40.000 $40.000 $37.000
ROCK FILTER DAMS (REMOVE)
LF 667.000 $12.000 $11.000 $11.000 $11.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 111.000 $45.000 $50.000 $38.500 $40.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 111.000 $9.000 $11.000 $12.000 $13.000 $12.000
EXCAV (EROSN & SEDMT CONT, IN VEH)
CY 200.000 $40.000 $25.000 $20.000 $25.000 $28.840
BACKHOE WORK (EROSION & SEDMT CONT)
HR 300.000 $163.000 $50.000 $75.000 $75.000 $95.140
TEMP SEDMT CONT FENCE (INSTALL)
LF 18,366.000 $4.000 $3.750 $4.000 $4.050 $3.680
TEMP SEDMT CONT FENCE (REMOVE)
LF 18,366.000 $1.000 $1.250 $0.300 $0.350 $0.300
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,250.000 $6.000 $5.500 $5.350 $5.400 $4.880
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,250.000 $1.000 $1.250 $1.100 $1.100 $1.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 300.000 $110.000 $95.000 $75.000 $85.000 $207.870
CONSTRUCTING DETOURS
SY 9,095.000 $110.000 $81.000 $84.000 $115.000 $100.880
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 8,820.000 $95.000 $12.000 $90.000 $80.000 $40.380
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 1,080.000 $90.000 $14.000 $90.000 $85.000 $42.850
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 700.000 $35.000 $23.000 $18.000 $25.000 $23.940
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 8,646.000 $36.000 $8.000 $14.000 $12.000 $10.200
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 800.000 $26.000 $10.000 $14.000 $14.000 $10.910
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 700.000 $25.000 $22.000 $18.000 $20.000 $19.080
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 8,820.000 $16.000 $11.000 $15.000 $10.000 $14.520
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 1,080.000 $60.000 $13.000 $15.000 $10.000 $19.820
CONC CURB & GUTTER (TY II)
LF 19,463.000 $35.000 $25.000 $32.000 $28.000 $32.420
CONC CURB (DOWELED)
LF 142.000 $80.000 $28.000 $46.000 $26.000 $11.140
DRIVEWAYS (CONC)
SY 1,561.000 $175.000 $105.000 $100.000 $110.000 $115.000
DRIVEWAYS (CONC) (HES)
SY 1,078.000 $135.000 $115.000 $125.000 $120.000 $135.000
DRIVEWAYS (ACP)
SY 1,825.000 $85.000 $55.000 $70.000 $45.000 $91.010
CONC SIDEWALKS (5")
SY 9,775.000 $80.000 $67.000 $75.000 $78.000 $75.000
CURB RAMPS (TY 1)
EA 4.000 $3,000.000 $2,300.000 $2,200.000 $3,000.000 $2,550.000
CURB RAMPS (TY 7)
EA 5.000 $3,500.000 $2,300.000 $2,200.000 $3,000.000 $2,550.000
CURB RAMPS (TY 22)
EA 1.000 $4,500.000 $3,000.000 $4,500.000 $3,800.000 $4,500.000
CONC DIRECTIONAL ISLAND
SY 109.000 $200.000 $130.000 $120.000 $135.000 $130.000
MTL W-BEAM GD FEN (STEEL POST)
LF 388.000 $35.000 $31.000 $30.000 $30.000 $27.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,200.000 $2,200.000 $2,150.000 $2,200.000 $1,950.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $2,000.000 $1,500.000 $1,450.000 $1,450.000 $1,325.000
REMOVE METAL BEAM GUARD FENCE
LF 550.000 $4.000 $2.250 $2.200 $2.200 $2.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $190.000 $165.000 $165.000 $165.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,050.000 $3,300.000 $3,300.000 $3,250.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $325.000 $225.000 $220.000 $220.000 $200.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 4.000 $500.000 $740.000 $700.000 $740.000 $775.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 19.000 $375.000 $350.000 $250.000 $350.000 $275.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 5.000 $325.000 $400.000 $300.000 $400.000 $315.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $800.000 $720.000 $740.000 $720.000 $625.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 13.000 $800.000 $890.000 $940.000 $900.000 $715.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $850.000 $1,125.000 $1,250.000 $1,125.000 $1,190.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 5.000 $1,260.000 $1,350.000 $1,200.000 $1,350.000 $1,395.000
REMOVE SM RD SN SUP&AM
EA 33.000 $80.000 $110.000 $110.000 $110.000 $79.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 16.000 $30.000 $17.000 $16.500 $20.000 $15.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1
EA 3.000 $30.000 $17.000 $16.500 $20.000 $15.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 6.000 $30.000 $28.000 $27.500 $30.000 $25.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 1.000 $125.000 $73.000 $62.000 $75.000 $55.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 2.000 $165.000 $330.000 $220.000 $325.000 $295.000
INSTL OM ASSM (OM-3R)(TWT)GND
EA 1.000 $30.000 $110.000 $220.000 $325.000 $295.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 5,480.000 $0.500 $0.450 $0.440 $0.430 $0.400
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 38,380.000 $0.500 $0.450 $0.440 $0.430 $0.350
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 818.000 $4.000 $3.300 $3.300 $3.300 $6.350
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 4,860.000 $1.000 $0.450 $0.440 $0.430 $0.400
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 59,100.000 $0.500 $0.450 $0.440 $0.430 $0.380
WK ZN PAV MRK REMOV (REFL) TY I-C
LF 116.000 $5.000 $5.500 $5.500 $5.500 $5.500
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,970.000 $5.000 $4.750 $4.700 $4.750 $5.500
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 1,020.000 $1.000 $2.750 $2.750 $2.650 $1.250
WK ZN PAV MRK REMOV (W)12"(SLD)
LF 50.000 $2.000 $8.800 $8.800 $8.750 $7.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 1,220.000 $1.750 $1.100 $2.750 $2.750 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,960.000 $2.000 $1.650 $1.650 $1.250 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,960.000 $1.500 $1.650 $1.650 $1.250 $3.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 668.000 $1.500 $2.200 $2.200 $2.200 $2.250
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 341.000 $2.000 $2.200 $2.200 $2.200 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,500.000 $2.500 $1.500 $1.400 $1.400 $1.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 798.000 $8.000 $7.500 $7.450 $7.500 $11.250
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 4,160.000 $1.500 $1.100 $1.100 $1.100 $0.970
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 3,784.000 $1.500 $1.100 $1.100 $1.100 $0.950
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 3,920.000 $4.500 $1.100 $1.100 $1.100 $0.970
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 22,587.000 $1.000 $0.780 $0.770 $0.750 $0.950
PREFAB PM TY C (W)(ARROW)
EA 17.000 $225.000 $245.000 $240.000 $240.000 $327.000
PREFAB PM TY C (W)(WORD)
EA 5.000 $275.000 $280.000 $280.000 $280.000 $377.000
REFL PAV MRKR TY I-C
EA 324.000 $6.000 $6.600 $6.600 $6.500 $5.950
REFL PAV MRKR TY II-A-A
EA 718.000 $7.000 $6.600 $6.600 $6.500 $5.950
ELIM EXT PM & MRKS (4")
LF 47,867.000 $0.500 $0.550 $1.000 $0.750 $0.650
ELIM EXT PM & MRKS (8")
LF 1,700.000 $1.500 $1.100 $1.250 $2.000 $0.650
ELIM EXT PM & MRKS (24")
LF 362.000 $8.000 $5.500 $2.000 $4.000 $6.000
ELIM EXT PM & MRKS (ARROW)
EA 8.000 $100.000 $110.000 $275.000 $100.000 $100.000
ELIM EXT PM & MRKS (WORD)
EA 6.000 $100.000 $110.000 $275.000 $100.000 $120.000
RELOCATE RDSD FLASH BEACON ASSEMBLY
EA 1.000 $4,000.000 $4,500.000 $5,500.000 $4,500.000 $4,500.000
FULL - WIDTH MOWING
CYC 5.000 $3,500.000 $5,500.000 $5,000.000 $3,500.000 $2,500.000
LITTER REMOVAL
CYC 5.000 $4,000.000 $3,300.000 $1,600.000 $3,500.000 $911.240
LED ROADSIDE SIGN
EA 4.000 $4,700.000 $4,400.000 $2,250.000 $6,500.000 $2,500.000
Totals: $25,999,390.200 $22,863,768.440 $23,813,255.840 $24,260,513.640 $30,235,494.996
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $60,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
Total: $105,000.00