GREGG IH 20 (0495-07-081)
Items: 139
County: GREGG
Length: 0.0000 MILES
Highway: IH 20
District: TYLER
Control Number: 0495-07-081
DBE Goal: 200.0%
Project: BR 2B25(109)
Guaranty: $100,000.00
Time: 723 WORKING DAYS
Engineer's Estimate: $40,248,855.54
Date: 09/05/2025 (9 months ago)
Contract Number: 9253237
Type: BRIDGE REPLACEMENT
Project ID: A00063821
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
KYLE DYKES
STACY WYLIE
GREGG IH 20 (0495-07-081)
Project Name: N/A
Project: BR 2B25(109)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: .955 MI W OF SABINE RIVER
Limits To: .842 MI E OF SABINE RIVER
Project Description: BRIDGE REPLACEMENT
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$40,248,855.54 | |||
| $36,971,034.60 |
-8.14%
-$3,277,820.94
|
|||
| $37,531,651.19 |
-6.75%
-$2,717,204.35
|
1.52%
$560,616.59
|
||
| $38,685,253.73 |
-3.88%
-$1,563,601.81
|
4.64%
$1,714,219.13
|
-3.07%
-$1,153,602.54
|
|
| $39,770,109.38 |
-1.19%
-$478,746.16
|
7.57%
$2,799,074.78
|
-2.80%
-$1,084,855.65
|
|
| $41,535,504.05 |
3.2%
$1,286,648.51
|
12.35%
$4,564,469.45
|
-4.44%
-$1,765,394.67
|
|
| $43,513,669.19 |
8.11%
$3,264,813.65
|
17.7%
$6,542,634.59
|
-4.76%
-$1,978,165.14
|
|
| $44,068,020.78 |
9.49%
$3,819,165.24
|
19.2%
$7,096,986.18
|
-1.27%
-$554,351.59
|
|
| $44,523,476.98 |
10.62%
$4,274,621.44
|
20.43%
$7,552,442.38
|
-1.03%
-$455,456.20
|
|
| $47,554,430.52 |
18.15%
$7,305,574.98
|
28.63%
$10,583,395.92
|
-6.81%
-$3,030,953.54
|
|
|
10
|
$48,556,553.54 |
20.64%
$8,307,698.00
|
31.34%
$11,585,518.94
|
-2.11%
-$1,002,123.02
|
E
Engineer's Estimate
$40,248,855.54
1
Awarded
$36,971,034.60
Over/Under Est:
-8.14%
-$3,277,820.94
$37,531,651.19
Over/Under Est:
-6.75%
-$2,717,204.35
Amt Left:
1.52%
$560,616.59
$38,685,253.73
Over/Under Est:
-3.88%
-$1,563,601.81
Amt Left:
4.64%
$1,714,219.13
Delta:
-3.07%
-$1,153,602.54
$39,770,109.38
Over/Under Est:
-1.19%
-$478,746.16
Amt Left:
7.57%
$2,799,074.78
Delta:
-2.80%
-$1,084,855.65
$41,535,504.05
Over/Under Est:
3.2%
$1,286,648.51
Amt Left:
12.35%
$4,564,469.45
Delta:
-4.44%
-$1,765,394.67
$43,513,669.19
Over/Under Est:
8.11%
$3,264,813.65
Amt Left:
17.7%
$6,542,634.59
Delta:
-4.76%
-$1,978,165.14
$44,068,020.78
Over/Under Est:
9.49%
$3,819,165.24
Amt Left:
19.2%
$7,096,986.18
Delta:
-1.27%
-$554,351.59
$44,523,476.98
Over/Under Est:
10.62%
$4,274,621.44
Amt Left:
20.43%
$7,552,442.38
Delta:
-1.03%
-$455,456.20
$47,554,430.52
Over/Under Est:
18.15%
$7,305,574.98
Amt Left:
28.63%
$10,583,395.92
Delta:
-6.81%
-$3,030,953.54
10
$48,556,553.54
Over/Under Est:
20.64%
$8,307,698.00
Amt Left:
31.34%
$11,585,518.94
Delta:
-2.11%
-$1,002,123.02
| Subcontractor | Percentage | Amount |
|---|---|---|
| HODGES AND SON CONSTRUCTION COMPANY, INC. | 4.23% | $1,563,874.76 |
| WITHERS CONSTRUCTION, LLC | 1.98% | $732,026.49 |
| CAP RIVER LLC | 1.16% | $428,864.00 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 0.73% | $269,888.55 |
| TORO BRAVO CONSTRUCTION, LLC | 0.56% | $207,037.79 |
| STRIPING TECHNOLOGY, L.P. | 0.52% | $192,249.38 |
| KITECO PROPERTY SOLUTIONS INC. | 0.36% | $133,095.72 |
| DIAMOND ELITE BARRICADES, LLC | 0.08% | $29,576.83 |
| CHEROKEE SERVICES | 0.03% | $11,091.31 |
| SOUTHWEST ENVIRONMENT SERVICES LLC | 0.03% | $11,091.31 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.02% | $7,394.21 |
| Total: | 9.70% | $3,586,190.35 |
Bid Items & Bid Tabulations
139
Total
0 of 139
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $50,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $200,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $200,000.00 |
| Total: | $450,000.00 |