GONZALES UA0090 (6428-74-001)

Items: 9

County: GONZALES
Length: N/A
Highway: UA0090
District: YOAKUM
Control Number: 6428-74-001
DBE Goal: N/A
Project: RMC - 642874001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $987,500.00
Date: 01/06/2023 (3 years ago)
Contract Number: N/A
Type: SPOT BASE REPAIR
Mail/Deliver Bids To: N/A
MICHAEL BRZOZOWSKI
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$987,500.00
Over/Under Est: -0.17% -$1,700.00
Over/Under Est: 4.19% $41,401.89
Amt Left: 4.37% $43,101.89
Over/Under Est: 58.94% $582,000.00
Amt Left: 59.21% $583,700.00
Delta: -52.54% -$540,598.11
Over/Under Est: 169.27% $1,671,521.46
Amt Left: 169.73% $1,673,221.46
Delta: -69.42% -$1,089,521.46

Bid Items & Bid Tabulations

9 Total 0 of 9
GONZALES  |  UA0090  |  YOAKUM  |  6428-74-001  |  01/06/2023  |  $987,500.00  |  RMC - 642874001  |  SPOT BASE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
HUNTER INDUSTRIES, LTD.
LONE STAR PAVING COMPANY
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,500.000 $55.000 $70.050 $50.290 $99.000 $186.480
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 5,000.000 $70.000 $85.850 $69.200 $115.000 $203.800
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 2,500.000 $110.000 $117.100 $100.290 $148.000 $240.780
MOBILIZATION (CALLOUT)
EA 3.000 $25,000.000 $2,500.000 $50,778.880 $15,000.000 $92,058.070
TMA (STATIONARY)
DAY 60.000 $200.000 $150.000 $407.160 $550.000 $321.680
1 LANE CLOSURE-2 LANE ROAD, NO SHLDR
EA 25.000 $1,000.000 $25.000 $872.480 $2,500.000 $993.870
1 LANE CLOSURE-2 LANE ROAD, PAVED SHLDR
EA 35.000 $1,000.000 $25.000 $988.810 $2,500.000 $943.870
1 LANE CLOSURE-4 LANE ROAD
EA 15.000 $1,200.000 $25.000 $1,105.140 $2,000.000 $1,381.370
WORK AREA ON SHOULDER
EA 10.000 $500.000 $25.000 $639.820 $2,000.000 $1,131.370
Totals: $987,500.000 $985,800.000 $1,028,901.890 $1,569,500.000 $2,659,021.460