PREPARING ROW
|
STA
|
28.700
|
$3,500.000
|
$3,100.000
|
$6,500.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,935.000
|
$20.000
|
$24.000
|
$28.950
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
5,088.000
|
$25.000
|
$24.000
|
$24.870
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
761.000
|
$12.000
|
$25.000
|
$80.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
5,124.000
|
$25.000
|
$25.000
|
$75.000
|
|
|
BLADING
|
HR
|
62.000
|
$125.000
|
$60.000
|
$300.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
17,570.000
|
$0.250
|
$0.350
|
$0.450
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
4,393.000
|
$0.250
|
$0.310
|
$0.400
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
4,393.000
|
$0.250
|
$0.310
|
$0.400
|
|
|
VEGETATIVE WATERING
|
MG
|
372.100
|
$50.000
|
$20.000
|
$35.000
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
2,855.000
|
$80.000
|
$118.000
|
$120.000
|
|
|
CEMENT
|
TON
|
237.000
|
$240.000
|
$265.000
|
$250.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
14,781.000
|
$3.750
|
$5.000
|
$6.500
|
|
|
ASPH (RC-250)
|
GAL
|
1,936.000
|
$40.000
|
$6.200
|
$6.600
|
|
|
AGGR(TY-E GR-5 SAC-B)
|
CY
|
71.000
|
$250.000
|
$540.000
|
$570.000
|
|
|
AGGR(TY-PE GR-3 SAC-B)
|
CY
|
115.000
|
$250.000
|
$244.000
|
$260.000
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
141.000
|
$250.000
|
$405.000
|
$430.000
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
9,994.000
|
$6.000
|
$4.900
|
$5.200
|
|
|
CEM STABIL BKFL
|
CY
|
418.000
|
$200.000
|
$366.000
|
$360.000
|
|
|
CUT & RESTORING PAV
|
SY
|
595.000
|
$80.000
|
$68.500
|
$134.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
92.000
|
$10.000
|
$20.000
|
$97.400
|
|
|
TEMPORARY SPL SHORING
|
SF
|
4,242.000
|
$28.000
|
$20.000
|
$26.900
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
690.000
|
$250.000
|
$225.000
|
$580.000
|
|
|
CL C CONC (ABUT)
|
CY
|
31.200
|
$1,400.000
|
$1,200.000
|
$1,430.000
|
|
|
CL C CONC (CAP)
|
CY
|
24.600
|
$1,400.000
|
$1,200.000
|
$1,970.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
16.400
|
$1,700.000
|
$2,200.000
|
$1,720.000
|
|
|
CL C CONC (MISC)
|
CY
|
3.600
|
$800.000
|
$2,200.000
|
$1,640.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
4,658.000
|
$25.000
|
$33.000
|
$23.000
|
|
|
APPROACH SLAB
|
CY
|
98.100
|
$500.000
|
$925.000
|
$700.000
|
|
|
PRESTR CONC SLAB BEAM (4SB15)
|
LF
|
886.320
|
$250.000
|
$333.000
|
$210.000
|
|
|
PRESTR CONC SLAB BEAM (5SB15)
|
LF
|
196.960
|
$250.000
|
$333.000
|
$225.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
129.000
|
$700.000
|
$749.000
|
$600.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
1,263.000
|
$180.000
|
$245.000
|
$203.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOTS)
|
LF
|
618.400
|
$115.000
|
$290.000
|
$110.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
90.000
|
$140.000
|
$145.000
|
$138.000
|
|
|
CONC BOX CULV (8 FT X 4 FT)
|
LF
|
263.200
|
$800.000
|
$1,420.000
|
$1,025.000
|
|
|
CONC BOX CULV (9 FT X 7 FT)
|
LF
|
310.800
|
$1,200.000
|
$1,160.000
|
$1,350.000
|
|
|
CONC BOX CULV (10 FT X 7 FT)
|
LF
|
126.000
|
$1,700.000
|
$2,074.000
|
$1,725.000
|
|
|
CONC BOX CULV (10 FT X 10 FT)
|
LF
|
92.000
|
$1,300.000
|
$2,440.000
|
$2,100.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
56.000
|
$150.000
|
$200.000
|
$158.000
|
|
|
WINGWALL (FW - 0) (HW=12 FT)
|
EA
|
2.000
|
$45,000.000
|
$70,000.000
|
$37,200.000
|
|
|
WINGWALL (FW-0) (HW=6 FT) (MOD)
|
EA
|
2.000
|
$20,000.000
|
$54,000.000
|
$17,900.000
|
|
|
WINGWALL (FW-0)(HW=5FT)(MOD)
|
EA
|
2.000
|
$20,000.000
|
$51,000.000
|
$11,900.000
|
|
|
WINGWALL(FW-S)(HW=5FT)(MOD)
|
EA
|
1.000
|
$20,000.000
|
$48,000.000
|
$10,400.000
|
|
|
WINGWALL(FW-S)(HW=6FT)(MOD)
|
EA
|
1.000
|
$20,000.000
|
$55,000.000
|
$12,500.000
|
|
|
SET (TY II) (15 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$4,800.000
|
$3,660.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$2,100.000
|
$3,800.000
|
$2,820.000
|
|
|
REMOV STR (BOX CULVERT)
|
EA
|
2.000
|
$10,000.000
|
$14,760.000
|
$12,200.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
4.000
|
$30,000.000
|
$14,760.000
|
$19,500.000
|
|
|
REMOV STR (PIPE)
|
EA
|
1.000
|
$375.000
|
$800.000
|
$1,760.000
|
|
|
REMOV STR (SMALL FENCE)
|
LF
|
234.000
|
$3.500
|
$2.000
|
$27.500
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$525,000.000
|
$200,000.000
|
$602,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
11.000
|
$3,500.000
|
$1,500.000
|
$6,600.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
240.000
|
$35.000
|
$30.000
|
$40.050
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
240.000
|
$12.000
|
$8.000
|
$15.800
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,352.000
|
$2.500
|
$3.290
|
$3.800
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,352.000
|
$1.000
|
$1.180
|
$1.050
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
7.000
|
$5,000.000
|
$10,000.000
|
$3,660.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
3,120.000
|
$38.000
|
$28.000
|
$21.700
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
4,170.000
|
$20.000
|
$16.000
|
$9.650
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
3,120.000
|
$30.000
|
$2.500
|
$21.700
|
|
|
DRIVEWAYS (ACP)
|
SY
|
104.000
|
$50.000
|
$200.000
|
$217.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
166.000
|
$30.000
|
$188.000
|
$139.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,525.000
|
$38.000
|
$24.000
|
$25.400
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
19.000
|
$2,200.000
|
$1,905.000
|
$2,060.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
2,154.000
|
$3.000
|
$2.250
|
$2.450
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
19.000
|
$3,400.000
|
$3,005.000
|
$3,250.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
12.000
|
$250.000
|
$275.000
|
$300.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
22.000
|
$1,560.000
|
$500.000
|
$540.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
18.000
|
$830.000
|
$300.000
|
$320.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
1.000
|
$21,500.000
|
$29,000.000
|
$6,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
18.000
|
$8,800.000
|
$9,300.000
|
$13,000.000
|
|
|
WIRE FENCE (TY A)
|
LF
|
148.000
|
$30.000
|
$35.000
|
$86.700
|
|
|
WIRE FENCE (TY C)
|
LF
|
234.000
|
$30.000
|
$35.000
|
$44.300
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
3.000
|
$300.000
|
$195.000
|
$224.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
2.000
|
$250.000
|
$206.000
|
$260.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
1.000
|
$500.000
|
$818.000
|
$520.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
22.000
|
$25.000
|
$16.500
|
$21.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
55.000
|
$30.000
|
$21.500
|
$27.650
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
16,400.000
|
$0.650
|
$0.700
|
$0.700
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
144.000
|
$8.000
|
$5.000
|
$17.200
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
20,990.000
|
$0.650
|
$0.700
|
$0.700
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
8,062.000
|
$1.000
|
$1.250
|
$1.050
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
|
LF
|
3,043.000
|
$1.000
|
$1.350
|
$1.200
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
14,670.000
|
$1.000
|
$1.000
|
$1.050
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
377.000
|
$3.000
|
$7.000
|
$5.350
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
16,690.000
|
$0.370
|
$0.380
|
$0.600
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
4,645.000
|
$107.000
|
$102.000
|
$108.000
|
|
|
D-GR HMA TY-D SAC-A PG70-22
|
TON
|
908.000
|
$130.000
|
$154.000
|
$164.000
|
|
|
TACK COAT
|
GAL
|
866.000
|
$3.750
|
$4.900
|
$5.200
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
6.000
|
$8,500.000
|
$17,500.000
|
$21,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
24.000
|
$200.000
|
$350.000
|
$228.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
36.000
|
$300.000
|
$245.000
|
$810.000
|
|
Totals: |
$5,761,078.050
|
$6,351,464.790
|
$6,940,512.610
|