GONZALES SH 304 (0573-03-022)

Items: 145

County: GONZALES
Length: 12.8580 MILES
Highway: SH 304
District: YOAKUM
Control Number: 0573-03-022
DBE Goal: 0.0%
Project: C 573-3-22
Guaranty: $100,000.00
Time: 330 WORKING DAYS
Engineer's Estimate: $13,648,816.35
Date: 06/05/2025 (1 year ago)
Contract Number: 6253205
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00195596
Project Description: RESTORE ROADWAY AND ADD SHOULDER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$13,648,816.35
$10,569,339.08
Over/Under Est: -22.56% -$3,079,477.27
$11,738,721.03
Over/Under Est: -13.99% -$1,910,095.32
Amt Left: 11.06% $1,169,381.95
Over/Under Est: -9.27% -$1,265,660.27
Amt Left: 17.16% $1,813,817.00
Delta: -5.49% -$644,435.05
Over/Under Est: -5.48% -$748,271.95
Amt Left: 22.06% $2,331,205.32
Delta: -4.18% -$517,388.32
$14,218,684.70
Over/Under Est: 4.18% $569,868.35
Amt Left: 34.53% $3,649,345.62
Delta: -10.22% -$1,318,140.30
Subcontractor Percentage Amount
STX CIVIL 11.59% $1,218,265.43
DIIBS SPECIALISTS, LLC 3.94% $414,147.18
D. I. J. CONSTRUCTION, INC. 3.87% $406,789.23
THIRD COAST SERVICES LLC 2.47% $259,630.34
LONE STAR EROSION CONTROL 1.25% $131,391.87
MURRAY CONSTRUCTION 0.79% $83,039.66
SOUTH TEXAS TRAFFIC ALLIANCE INC. 0.34% $35,738.59
PROFESSIONAL TRAFFIC CONTROL LLC 0.24% $25,227.24
PRIMATE CONSTRUCTION, LP 0.22% $23,124.97
4E TREE WORX LLC 0.11% $11,562.48
Total: 24.82% $2,608,916.99

Bid Items & Bid Tabulations

145 Total 0 of 145
GONZALES  |  SH 304  |  YOAKUM  |  0573-03-022  |  06/05/2025  |  $13,648,816.35  |  C 573-3-22  |  REHAB EXIST ROADWAY  |  330 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
DEAN WORD COMPANY, LTD.
CLARK CONSTRUCTION OF TEXAS, INC.
ACME BRIDGE COMPANY, INC.
CK NEWBERRY, LLC
PREPARING ROW
STA 3.100 $3,000.000 $5,346.350 $14,100.000 $3,613.000 $10,600.000 $5,000.000
REMOV CONC (RIPRAP)
SY 63.000 $16.000 $13.200 $57.900 $23.000 $21.900 $135.000
REMOV CONC (DRIVEWAYS)
SY 38.000 $25.000 $16.500 $65.800 $27.000 $30.710 $225.000
REMOV CONC (WINGWALL)
CY 23.000 $2,000.000 $420.290 $79.700 $350.000 $174.000 $500.000
EXCAV (ROADWAY)
CY 87.000 $18.000 $30.800 $20.900 $125.000 $32.800 $100.000
SUBGR WIDEN (OC)
STA 265.690 $500.000 $610.500 $1,144.000 $716.590 $558.000 $625.000
EMBANK (VEH)(OC)(TY C)
CY 5,016.000 $60.000 $15.400 $29.800 $18.890 $7.900 $50.000
BACKFILL (TY A)
STA 410.220 $225.000 $143.000 $179.100 $478.830 $155.000 $475.000
BLADING
HR 50.000 $125.000 $93.500 $25.300 $100.000 $42.400 $185.000
BROADCAST SEED (TEMP_WARM)
SY 7,873.000 $0.140 $0.290 $0.200 $0.150 $0.270 $0.350
BROADCAST SEED (TEMP_COOL)
SY 7,873.000 $0.140 $0.330 $0.200 $0.180 $0.310 $0.350
DRILL SEED (PERM_RURAL_SAND)
SY 89,896.000 $0.300 $0.290 $0.300 $0.250 $0.270 $0.300
DRILL SEED (TEMP_WARM)
SY 22,474.000 $0.250 $0.180 $0.200 $0.150 $0.160 $0.300
DRILL SEED (TEMP_COOL)
SY 22,474.000 $0.250 $0.220 $0.200 $0.150 $0.200 $0.300
VEGETATIVE WATERING
TGL 756.680 $26.000 $19.800 $10.000 $32.750 $40.800 $30.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 19,181.000 $82.000 $58.630 $59.100 $77.340 $95.140 $80.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 679.000 $360.000 $385.000 $307.200 $325.000 $433.000 $325.000
LIME TRT (EXIST MATL)(6")
SY 74,445.000 $5.000 $1.760 $4.700 $3.250 $2.140 $3.000
ASPH (RC-250)
GAL 11,937.000 $5.000 $4.840 $5.000 $6.520 $9.800 $8.000
AGGR (TY-E, GR-5)(SAC-B)
CY 426.000 $135.000 $82.420 $109.900 $182.550 $259.000 $350.000
AGGR (TY-PE, GR-3)(SAC-B)
CY 702.000 $140.000 $105.550 $120.000 $138.050 $226.000 $250.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 2,466.000 $140.000 $105.590 $107.700 $130.070 $138.000 $130.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 132,876.000 $4.100 $4.070 $3.900 $4.740 $3.940 $4.500
D-GR HMA TY-B SAC-B PG64-22
TON 7,938.000 $115.000 $90.200 $86.000 $103.850 $104.000 $115.000
D-GR HMA TY-D SAC-B PG70-22
TON 32,596.000 $125.000 $96.250 $95.000 $101.100 $114.000 $110.000
TACK COAT
GAL 31.000 $5.000 $6.600 $40.400 $5.000 $1.000 $4.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 500.000 $55.000 $62.920 $46.700 $99.630 $96.100 $95.000
PLANE ASPH CONC PAV(2")
SY 24,817.000 $1.400 $1.980 $1.800 $2.200 $2.050 $2.000
PLANE ASPH CONC PAV (1.5")
SY 21,867.000 $1.100 $1.980 $1.600 $2.220 $1.800 $1.500
CEM STABIL BKFL
CY 133.000 $200.000 $209.340 $207.300 $145.000 $199.000 $225.000
FLOWABLE BACKFILL
CY 2.000 $500.000 $597.560 $466.300 $700.000 $511.000 $2,225.000
TEMPORARY SPL SHORING
SF 7,586.000 $33.000 $17.440 $21.300 $18.000 $20.400 $14.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 210.000 $500.000 $154.180 $151.900 $142.790 $146.000 $300.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 93.000 $565.000 $220.280 $216.900 $340.000 $148.000 $350.000
PNEUMATICALLY PLACED CONC (REPAIR)
CF 55.000 $560.000 $422.200 $415.700 $440.000 $738.000 $800.000
RIPRAP (CONC)(5 IN)
CY 88.100 $570.000 $680.730 $832.400 $600.000 $537.000 $550.000
RIPRAP (CONC)(CL B)
CY 7.350 $1,200.000 $1,065.490 $964.000 $800.000 $920.000 $900.000
RIPRAP (MOW STRIP)(6 IN)
CY 4.000 $500.000 $1,479.850 $1,124.300 $1,250.000 $1,280.000 $1,500.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 247.000 $200.000 $254.790 $209.100 $185.000 $188.000 $300.000
RIPRAP (STONE PROTECTION)(21 IN)
CY 140.000 $250.000 $229.450 $267.100 $200.000 $365.000 $325.000
CLEANING AND SEALING EXISTING JOINTS
LF 319.000 $24.000 $78.300 $105.300 $41.640 $32.700 $55.000
RETROFIT RAIL (TY T631)
LF 348.140 $258.000 $86.380 $85.100 $101.920 $81.800 $115.000
RETROFIT RAIL (TY T131RC)
LF 600.000 $258.000 $238.870 $237.500 $265.630 $238.000 $300.000
CMP (GAL STL 18 IN)
LF 112.000 $90.000 $151.190 $237.200 $150.000 $48.000 $135.000
CONC BOX CULV (4 FT X 3 FT)
LF 8.000 $475.000 $476.830 $2,408.500 $1,100.000 $1,710.000 $700.000
CONC BOX CULV (5 FT X 3 FT)
LF 24.000 $610.000 $604.760 $2,197.500 $978.000 $1,540.000 $725.000
CONC BOX CULV (6 FT X 6 FT)
LF 64.000 $1,300.000 $790.840 $1,459.200 $1,400.000 $910.000 $1,200.000
CONC BOX CULV (8 FT X 6 FT)
LF 16.000 $1,450.000 $843.170 $3,543.700 $2,000.000 $2,400.000 $2,000.000
CONC BOX CULV (8 FT X 7 FT)
LF 46.000 $1,500.000 $1,099.030 $1,786.600 $1,848.000 $1,180.000 $1,800.000
CONC BOX CULV (10 FT X 10 FT)
LF 44.000 $1,600.000 $2,070.130 $2,212.700 $2,380.000 $1,570.000 $2,500.000
RC PIPE (CL III)(18 IN)
LF 31.000 $110.000 $104.670 $620.700 $212.000 $97.100 $400.000
RC PIPE (CL III)(24 IN)
LF 5.000 $150.000 $139.560 $1,267.400 $328.000 $169.000 $1,200.000
RC PIPE (CL III)(30 IN)
LF 16.000 $160.000 $191.890 $777.000 $293.000 $107.000 $450.000
RC PIPE (CL III)(36 IN)
LF 8.000 $200.000 $226.780 $1,347.900 $408.000 $92.000 $850.000
WINGWALL (FW - 0) (HW=7 FT)
EA 1.000 $17,174.000 $20,352.400 $29,712.000 $8,800.000 $28,100.000 $22,000.000
WINGWALL (FW - 0) (HW=8 FT)
EA 3.000 $16,500.000 $22,096.900 $31,503.900 $16,880.000 $29,600.000 $30,000.000
WINGWALL (FW - 0) (HW=9 FT)
EA 3.000 $30,000.000 $23,841.390 $16,725.300 $9,100.000 $15,400.000 $20,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 2.000 $45,290.820 $35,296.890 $38,862.000 $30,878.000 $36,300.000 $60,000.000
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $89,134.050 $45,007.890 $68,210.000 $63,114.000 $62,400.000 $150,000.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1)(C)
EA 2.000 $13,000.000 $14,188.530 $25,499.500 $18,996.000 $21,100.000 $20,000.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1)(C)
EA 6.000 $14,000.000 $9,536.560 $10,015.600 $6,778.000 $7,920.000 $7,500.000
SET (TY I)(S= 6 FT)(HW= 7 FT)(3:1)(C)
EA 8.000 $19,000.000 $15,816.730 $19,619.600 $16,064.000 $15,300.000 $18,000.000
SET (TY I)(S= 8 FT)(HW= 7 FT)(3:1)(C)
EA 8.000 $15,006.390 $18,142.720 $14,528.900 $7,941.000 $11,000.000 $10,000.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 28.000 $1,635.000 $1,511.890 $1,212.000 $2,035.000 $1,640.000 $4,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 2.000 $1,800.000 $1,628.190 $1,341.400 $2,253.000 $2,810.000 $5,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 2.000 $1,750.000 $1,977.090 $1,341.400 $2,253.000 $3,070.000 $5,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $1,850.000 $1,977.090 $1,484.600 $2,795.000 $1,690.000 $5,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $2,300.000 $1,977.090 $1,651.500 $3,120.000 $2,200.000 $5,000.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $3,400.000 $3,023.790 $1,887.500 $3,825.000 $2,450.000 $6,000.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $4,200.000 $3,721.580 $2,376.200 $4,800.000 $4,400.000 $8,000.000
CLEAN EXIST CULVERTS
EA 1.000 $1,500.000 $4,651.980 $3,070.700 $2,000.000 $4,625.000 $3,500.000
MOBILIZATION
LS 1.000 $950,000.000 $696,797.660 $865,000.000 $1,031,200.000 $1,000,000.000 $1,400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $4,100.000 $7,869.880 $13,000.000 $5,440.000 $14,100.000 $8,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $11,000.000 $7,773.770 $19,018.800 $16,500.000 $11,200.000 $20,000.000
TMA (STATIONARY)
DAY 20.000 $300.000 $518.250 $371.900 $225.000 $153.000 $400.000
TMA (MOBILE OPERATION)
DAY 20.000 $300.000 $829.200 $650.000 $350.000 $616.000 $775.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 380.000 $50.000 $40.430 $42.500 $40.000 $37.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 380.000 $15.000 $12.280 $12.800 $12.000 $11.200 $15.000
SANDBAGS FOR EROSION CONTROL
EA 100.000 $12.000 $5.580 $13.900 $13.000 $8.200 $30.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,550.000 $5.000 $4.640 $4.100 $3.800 $4.200 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,550.000 $1.250 $1.040 $1.100 $1.000 $0.950 $2.000
DRIVEWAYS (CONC)
SY 38.000 $125.000 $124.310 $289.900 $125.000 $235.000 $300.000
DRIVEWAYS (ACP)
SY 2,253.000 $70.000 $26.400 $38.900 $28.300 $80.210 $40.000
DRIVEWAYS (SURF TREAT)
SY 968.000 $45.000 $17.600 $60.500 $41.520 $47.600 $25.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 135,440.000 $0.150 $0.130 $0.100 $0.150 $0.110 $0.250
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 67,720.000 $0.200 $0.110 $0.100 $0.150 $0.100 $0.300
MTL W-BEAM GD FEN (TIM POST)
LF 3,955.020 $26.000 $24.500 $25.000 $23.570 $25.000 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,300.000 $1,950.000 $2,933.100 $2,067.000 $2,370.000 $2,500.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 121.840 $87.000 $79.500 $112.100 $105.340 $81.300 $120.000
REMOVE METAL BEAM GUARD FENCE
LF 4,158.260 $3.250 $2.500 $3.700 $3.500 $2.550 $4.000
GUARDRAIL END TREATMENT (INSTALL)
EA 36.000 $3,200.000 $3,100.000 $3,524.500 $3,315.000 $3,170.000 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 36.000 $425.000 $250.000 $292.400 $275.000 $256.000 $310.000
WIRE FENCE (TY A)
LF 325.000 $25.000 $46.500 $28.700 $46.500 $20.400 $55.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 17.000 $125.000 $135.000 $207.300 $135.000 $138.000 $150.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 2.000 $225.000 $155.000 $249.800 $155.000 $158.000 $175.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 21.000 $6,800.000 $4,860.120 $5,167.300 $4,860.120 $4,970.000 $7,500.000
CONDT (PVC) (SCH 40) (2")
LF 2,807.000 $18.000 $8.270 $8.800 $8.270 $8.500 $15.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,041.000 $20.000 $16.970 $18.100 $16.970 $17.400 $45.000
ELEC CONDR (NO.8) BARE
LF 3,848.000 $2.000 $1.710 $1.800 $1.710 $1.750 $2.500
ELEC CONDR (NO.8) INSULATED
LF 7,660.000 $2.150 $1.990 $2.100 $1.990 $2.050 $3.000
GROUND BOX TY A (122311)W/APRON
EA 22.000 $1,500.000 $1,188.750 $1,263.900 $1,188.750 $1,220.000 $1,700.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 1.000 $8,800.000 $8,127.750 $8,641.500 $8,127.750 $8,310.000 $6,000.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 2.000 $8,800.000 $7,416.550 $7,885.400 $7,416.550 $7,580.000 $7,500.000
ALUMINUM SIGNS (TY A)
SF 32.000 $45.000 $43.960 $46.700 $43.960 $28.600 $50.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $710.000 $740.000 $574.100 $740.000 $756.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 13.000 $810.000 $775.000 $715.500 $775.000 $792.000 $875.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 1.000 $825.000 $800.000 $754.900 $800.000 $818.000 $900.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 11.000 $925.000 $900.000 $850.600 $900.000 $920.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $980.000 $975.000 $946.300 $975.000 $997.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,100.000 $1,000.000 $863.400 $1,000.000 $1,020.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 2.000 $1,150.000 $1,100.000 $981.300 $1,100.000 $1,120.000 $1,250.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 50.000 $500.000 $450.000 $265.800 $450.000 $460.000 $500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $575.000 $640.000 $384.900 $640.000 $654.000 $725.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $2,200.000 $3,573.680 $3,477.700 $3,000.000 $2,990.000 $1,200.000
REMOVE SM RD SN SUP&AM
EA 102.000 $85.000 $75.000 $79.700 $75.000 $76.700 $100.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)SRF(BI)
EA 4.000 $22.000 $75.000 $122.200 $75.000 $76.700 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1 (BI)
EA 36.000 $28.000 $25.000 $13.900 $25.000 $25.600 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 118.000 $35.000 $35.000 $20.300 $35.000 $35.800 $50.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 48.000 $75.000 $65.000 $114.800 $65.000 $66.400 $75.000
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 24.000 $50.000 $75.000 $122.200 $75.000 $76.700 $85.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 28.000 $10.000 $15.000 $31.900 $15.000 $15.300 $20.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 401,586.000 $0.350 $0.250 $0.300 $0.500 $0.310 $0.500
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 144.000 $11.000 $6.780 $7.000 $8.000 $7.200 $8.000
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 4.000 $175.000 $153.990 $159.400 $600.000 $358.000 $400.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 27,203.000 $0.350 $0.310 $0.300 $0.500 $0.510 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 210,440.000 $0.350 $0.290 $0.300 $0.500 $0.310 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 18,104.000 $1.500 $1.630 $2.100 $2.000 $1.800 $0.500
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 130.000 $3.500 $10.270 $10.700 $6.000 $5.100 $6.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 330.000 $3.500 $10.730 $11.100 $6.000 $0.360 $4.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 140,892.000 $0.850 $0.770 $0.800 $0.750 $0.610 $0.750
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 13,053.000 $0.850 $0.800 $0.800 $0.750 $0.660 $0.750
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 75,950.000 $0.850 $0.770 $0.800 $0.750 $0.610 $0.750
PRFB RUMBLE STRIP (BLK)(4')(TRANSVERSE)
LF 160.000 $10.000 $15.400 $16.000 $25.000 $11.200 $12.000
PREFAB PM TY C (W)(24")(SLD)
LF 192.000 $13.000 $20.530 $21.300 $12.000 $14.300 $15.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $275.000 $472.230 $489.100 $200.000 $307.000 $350.000
PREFAB PM TY C (W)(RR XING)
EA 2.000 $550.000 $590.290 $611.300 $475.000 $818.000 $1,000.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 12.000 $50.000 $87.260 $90.400 $25.000 $76.700 $52.000
REFL PAV MRKR TY II-A-A
EA 1,520.000 $5.000 $7.750 $8.000 $6.000 $6.100 $7.000
ELIM EXT PM & MRKS (6")
LF 58,321.000 $0.500 $0.560 $0.600 $2.500 $0.510 $1.000
VEH SIG SEC (12")LED(RED)
EA 4.000 $290.000 $241.420 $256.700 $241.420 $247.000 $225.000
TRF SIG CBL (TY A)(14 AWG)(3 CONDR)
LF 328.000 $2.500 $1.820 $1.900 $1.820 $1.850 $4.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 2.000 $10,000.000 $4,413.000 $4,691.900 $4,413.000 $4,510.000 $4,000.000
RELOCATE RDSD FLASH BEACON ASSEMBLY
EA 1.000 $1,995.000 $1,761.980 $1,873.300 $1,761.980 $1,800.000 $1,500.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $12,000.000 $7,773.770 $26,899.100 $35,750.000 $8,110.000 $40,000.000
REMOVE BACKLIT LED RDSD SGN
EA 2.000 $850.000 $873.000 $928.200 $873.000 $892.000 $500.000
Totals: $13,648,816.345 $10,569,339.082 $11,738,721.042 $12,383,156.076 $12,900,544.411 $14,218,684.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $7,200.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $20,000.00
Total: $28,700.00