GONZALES SH 80 (0287-03-036)

Items: 119

County: GONZALES
Length: N/A
Highway: SH 80
District: YOAKUM
Control Number: 0287-03-036
DBE Goal: 400.0%
Project: F 2B24(283)
Guaranty: N/A
Time: 240 WORKING DAYS
Engineer's Estimate: $17,978,197.80
Date: 07/10/2024 (1 year ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD LANES
Mail/Deliver Bids To: N/A
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$17,978,197.80
$14,520,545.76
Over/Under Est: -19.23% -$3,457,652.04
Over/Under Est: -14.79% -$2,659,379.95
Amt Left: 5.5% $798,272.09
$16,360,619.84
Over/Under Est: -9% -$1,617,577.96
Amt Left: 12.67% $1,840,074.08
Delta: -6.80% -$1,041,801.99
$16,601,246.13
Over/Under Est: -7.66% -$1,376,951.67
Amt Left: 14.33% $2,080,700.37
Delta: -1.47% -$240,626.29
$17,326,782.97
Over/Under Est: -3.62% -$651,414.83
Amt Left: 19.33% $2,806,237.21
Delta: -4.37% -$725,536.84
$19,061,370.85
Over/Under Est: 6.02% $1,083,173.05
Amt Left: 31.27% $4,540,825.09
Delta: -10.01% -$1,734,587.88
Subcontractor Percentage Amount
TEXAS GUARDRAIL CONTRACTORS LLC 7.77% $1,128,246.41
INTERSTATE BARRICADES & MARKINGS, INC. 3.04% $441,424.59
4E TREE WORX LLC 0.81% $117,616.42
J. H. ODEN CONTRACTING COMPANY 0.70% $101,643.82
DEPENDABLE FENCE 0.38% $55,178.07
MURRAY CONSTRUCTION 0.20% $29,041.09
SOUTH TEXAS TRAFFIC ALLIANCE INC. 0.14% $20,328.76
PROFESSIONAL TRAFFIC CONTROL LLC 0.09% $13,068.49
Total: 13.13% $1,906,547.65

Bid Items & Bid Tabulations

119 Total 0 of 119
GONZALES  |  SH 80  |  YOAKUM  |  0287-03-036  |  07/10/2024  |  $17,978,197.80  |  F 2B24(283)  |  WIDEN ROAD - ADD LANES  |  240 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
TEXAS MATERIALS GROUP, INC.
CK NEWBERRY, LLC
J. CARROLL WEAVER, INC.
C. E. BARKER, LTD.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 15.500 $5,000.000 $3,500.000 $4,040.000 $5,000.000 $4,950.000 $101,000.000 $80,000.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 14.000 $1,500.000 $1,265.000 $1,150.000 $1,250.000 $2,200.000 $1,175.000 $2,000.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 67.000 $2,500.000 $1,870.000 $1,700.000 $1,900.000 $2,750.000 $2,250.000 $2,500.000
REMOVING CONC (DRIVEWAYS)
SY 294.000 $26.500 $24.500 $28.000 $50.000 $17.310 $28.000 $20.000
REMOVING CONC (CURB)
LF 160.000 $10.500 $14.000 $7.500 $25.000 $7.950 $21.880 $20.000
EXCAVATION (ROADWAY)
CY 19,705.000 $23.000 $17.500 $15.250 $20.000 $14.750 $8.000 $10.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 19,562.000 $25.000 $17.500 $16.900 $24.000 $10.690 $8.000 $25.000
BLADING
HR 30.000 $170.000 $108.000 $175.000 $200.000 $82.500 $291.670 $150.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 3,186.000 $0.500 $0.400 $0.400 $0.310 $0.390 $0.280 $1.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 253,581.000 $0.400 $0.180 $0.180 $0.250 $0.280 $0.220 $0.350
DRILL SEEDING (TEMP) (WARM)
SY 63,397.000 $0.400 $0.130 $0.130 $0.170 $0.130 $0.170 $0.350
DRILL SEEDING (TEMP) (COOL)
SY 63,397.000 $0.400 $0.130 $0.130 $0.170 $0.130 $0.170 $0.350
VEGETATIVE WATERING
MG 2,134.530 $25.000 $14.000 $20.000 $20.000 $19.800 $33.330 $20.000
FL BS (CMP IN PLC)(TY E GR 5)(FNL POS)
CY 26,808.000 $90.000 $62.720 $76.350 $84.500 $91.150 $65.500 $55.000
FL BS(RDWY DEL)(TY E GR 5)(IN VEH)
CY 274.000 $90.000 $103.580 $75.000 $125.000 $86.470 $65.500 $100.000
REWORK BASE MTL (TY C)(14")
SY 7,154.000 $3.000 $4.800 $2.500 $3.000 $4.230 $7.000 $15.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 1,023.000 $325.000 $330.000 $376.000 $350.000 $336.950 $302.000 $350.000
LIME TRT (EXST MATL)(8")
SY 64,930.000 $4.000 $3.120 $4.000 $3.500 $3.640 $3.500 $6.000
CEMENT
TON 741.000 $250.000 $214.500 $205.000 $210.000 $220.140 $187.250 $300.000
CEMENT TREAT(EXIST MATL)(8")
SY 64,930.000 $4.000 $3.120 $2.900 $2.500 $1.970 $3.500 $6.000
CEMENT TREAT (MX EXST MTL & NW BS)(8")
SY 11,232.000 $5.000 $4.080 $3.200 $2.750 $2.660 $3.180 $12.000
PRIME COAT (MC-30)
GAL 23,134.000 $6.000 $5.300 $4.700 $5.000 $4.880 $4.000 $5.000
PRIME COAT (RC-250)
GAL 2,177.000 $6.250 $5.300 $6.000 $5.250 $5.910 $5.000 $5.000
AGGR(TY-E GR-5 SAC-B)
CY 80.000 $140.000 $183.010 $238.000 $200.000 $257.940 $255.000 $200.000
AGGR(TY-PE GR-4 SAC-B)
CY 1,616.000 $150.000 $124.130 $170.000 $125.000 $137.480 $235.000 $200.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 70,828.000 $5.000 $4.920 $4.450 $4.000 $4.110 $5.000 $5.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 500.000 $105.000 $118.800 $89.250 $115.000 $77.170 $160.000 $110.000
PLANE ASPH CONC PAV(0" TO 1")
SY 2,416.000 $7.750 $4.880 $3.800 $6.000 $17.100 $3.000 $20.000
PLANE ASPH CONC PAV (1.5")
SY 2,402.000 $7.750 $4.880 $4.000 $6.000 $17.100 $4.000 $20.000
CEM STABIL BKFL
CY 520.000 $220.000 $174.970 $162.000 $225.000 $192.500 $200.000 $250.000
CUT & RESTORING PAV
SY 102.000 $170.000 $54.000 $105.000 $125.000 $104.500 $100.000 $200.000
CUT AND RESTORE PAV (FLEX BASE)
SY 190.000 $85.000 $55.080 $61.000 $30.000 $94.600 $70.000 $100.000
TRENCH EXCAVATION PROTECTION
LF 111.000 $25.000 $7.560 $7.000 $45.000 $19.800 $5.000 $10.000
TEMPORARY SPL SHORING
SF 3,467.000 $65.000 $23.760 $22.000 $35.000 $34.100 $35.000 $55.000
CL C CONC (RAIL FOUNDATION)(HPC)
CY 24.000 $1,500.000 $1,458.040 $1,350.000 $1,500.000 $1,952.500 $705.000 $2,000.000
RIPRAP (CONC)(5 IN)
CY 45.000 $700.000 $588.620 $545.000 $725.000 $660.000 $530.000 $650.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 88.000 $235.000 $220.760 $315.000 $225.000 $198.000 $116.670 $185.000
RAIL (TY SSTR)
LF 143.000 $200.000 $269.100 $225.000 $325.000 $214.500 $185.000 $300.000
RETROFIT RAIL (TY SSTR)
LF 73.000 $295.000 $294.130 $225.000 $325.000 $357.500 $235.000 $500.000
CONC BOX CULV (3 FT X 3 FT)
LF 78.000 $600.000 $422.290 $391.000 $1,000.000 $454.300 $283.170 $650.000
CONC BOX CULV (5 FT X 4 FT)
LF 130.000 $860.000 $640.460 $593.000 $1,250.000 $640.200 $414.620 $750.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 73.000 $700.000 $479.530 $444.000 $1,000.000 $753.500 $283.170 $700.000
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 51.000 $750.000 $668.540 $620.000 $1,000.000 $788.700 $278.220 $700.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 58.000 $795.000 $710.660 $658.000 $1,000.000 $788.700 $342.020 $750.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 9.000 $825.000 $880.230 $815.000 $1,400.000 $851.400 $414.620 $800.000
CONC BOX CULV (5 FT X 6.5 FT)(EXTEND)
LF 34.000 $950.000 $1,021.710 $946.000 $1,500.000 $853.600 $584.570 $1,000.000
RC PIPE (CL III)(18 IN)
LF 862.000 $106.000 $78.840 $73.000 $130.000 $95.700 $83.520 $85.000
RC PIPE (CL III)(24 IN)
LF 28.000 $140.000 $99.360 $92.000 $175.000 $123.200 $92.870 $105.000
RC PIPE (CL III)(36 IN)
LF 81.000 $200.000 $193.330 $179.000 $325.000 $188.100 $140.170 $175.000
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
EA 4.000 $6,500.000 $8,460.970 $7,840.000 $10,000.000 $12,870.000 $4,750.000 $12,500.000
SET (TY I)(S=3 FT)(HW= 5 FT)(3:1)(C)
EA 2.000 $7,000.000 $14,109.540 $13,100.000 $11,000.000 $13,530.000 $5,050.000 $16,500.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 4.000 $8,000.000 $8,919.990 $8,260.000 $10,000.000 $13,970.000 $5,250.000 $16,500.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 4.000 $8,600.000 $13,665.650 $12,700.000 $12,000.000 $16,170.000 $6,850.000 $18,500.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
EA 6.000 $10,000.000 $12,409.570 $11,500.000 $13,000.000 $14,410.000 $6,950.000 $20,000.000
SET (TY I)(S= 5 FT)(HW= 8 FT)(3:1) (C)
EA 2.000 $14,000.000 $28,236.360 $26,200.000 $30,000.000 $22,660.000 $11,527.000 $32,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 58.000 $1,500.000 $2,079.060 $1,925.000 $2,000.000 $1,650.000 $2,850.000 $1,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,100.000 $2,435.470 $2,255.000 $2,500.000 $2,640.000 $3,100.000 $2,250.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 4.000 $2,400.000 $4,330.930 $4,010.000 $6,000.000 $4,290.000 $4,100.000 $3,500.000
REMOV STR (SMALL)
EA 9.000 $1,500.000 $842.430 $1,310.000 $1,500.000 $1,650.000 $2,250.000 $2,500.000
MOBILIZATION
LS 1.000 $1,626,000.000 $1,181,947.330 $1,500,000.000 $1,250,000.000 $1,166,065.680 $1,565,000.000 $1,900,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $6,500.000 $4,241.530 $9,000.000 $10,000.000 $9,350.000 $7,810.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 452.000 $50.000 $65.000 $40.000 $40.000 $60.500 $39.260 $30.000
ROCK FILTER DAMS (REMOVE)
LF 452.000 $15.000 $20.000 $20.000 $16.500 $26.400 $16.400 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,925.000 $5.000 $4.500 $4.500 $3.250 $4.950 $3.050 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,925.000 $2.000 $1.000 $1.000 $1.500 $1.540 $1.490 $2.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 360.000 $100.000 $68.490 $36.000 $75.000 $56.590 $74.860 $95.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 720.000 $22.000 $46.050 $23.000 $40.000 $56.590 $17.500 $20.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 360.000 $25.000 $49.330 $34.000 $40.000 $56.590 $39.720 $20.000
INTERSECTIONS (ACP)
SY 954.000 $65.000 $55.200 $56.550 $80.000 $101.200 $60.000 $45.000
DRIVEWAYS (CONC)
SY 226.000 $115.000 $97.200 $94.000 $150.000 $170.500 $110.000 $95.000
DRIVEWAYS (SURF TREAT)
SY 2,587.000 $50.000 $41.400 $41.750 $40.000 $20.190 $37.000 $45.000
RUMBLE STRIPS (SHOULDER)
LF 64,045.000 $0.300 $0.130 $0.120 $0.300 $0.110 $0.060 $0.250
RUMBLE STRIPS (CENTERLINE)
LF 32,265.000 $0.300 $0.150 $0.120 $0.300 $0.160 $0.070 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $35.000 $27.000 $30.000 $30.000 $57.750 $28.210 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,400.000 $2,850.000 $3,000.000 $2,200.000 $2,585.000 $2,255.350 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 825.000 $5.000 $4.000 $4.000 $5.000 $3.030 $3.960 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,600.000 $3,365.000 $2,500.000 $2,500.000 $3,630.000 $2,486.100 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $400.000 $250.000 $200.000 $200.000 $275.000 $187.850 $1,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,200.000 $850.000 $1,000.000 $1,000.000 $1,650.000 $688.790 $6,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $750.000 $725.000 $1,000.000 $1,100.000 $525.950 $2,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $8,250.000 $8,430.000 $10,000.000 $9,350.000 $7,511.990 $30,000.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 24.000 $275.000 $150.000 $150.000 $200.000 $256.300 $150.000 $1,000.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 4.000 $320.000 $165.000 $165.000 $200.000 $280.500 $165.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $840.000 $625.000 $625.000 $700.000 $990.000 $625.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $960.000 $775.000 $775.000 $900.000 $1,100.000 $775.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 28.000 $450.000 $500.000 $500.000 $550.000 $627.000 $500.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 3.000 $500.000 $525.000 $525.000 $575.000 $715.000 $525.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 30.000 $110.000 $100.000 $100.000 $100.000 $176.000 $100.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $35.000 $25.000 $25.000 $25.000 $23.100 $25.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $30.000 $31.500 $31.500 $31.500 $34.100 $31.500 $100.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 18.000 $90.000 $65.000 $65.000 $65.000 $102.300 $65.000 $100.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 64,528.000 $0.450 $0.350 $0.550 $0.550 $0.610 $0.550 $0.750
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 70,468.000 $0.450 $0.350 $0.550 $0.550 $0.610 $0.550 $0.750
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 840.000 $1.250 $4.000 $1.250 $1.250 $1.380 $1.250 $1.500
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 840.000 $1.250 $4.000 $1.250 $1.250 $1.380 $1.250 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,759.000 $1.850 $1.630 $1.500 $1.000 $1.100 $1.500 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 5,198.000 $2.000 $1.630 $1.500 $1.000 $1.100 $1.500 $6.000
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
LF 2,239.000 $2.100 $0.950 $1.500 $1.500 $1.650 $1.500 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,148.000 $2.100 $1.250 $1.250 $1.250 $1.380 $1.250 $1.500
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 4,889.000 $0.850 $0.850 $0.650 $0.650 $0.720 $0.650 $1.500
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 64,528.000 $0.850 $0.950 $0.850 $1.000 $0.940 $0.900 $1.500
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 70,468.000 $1.100 $0.950 $0.850 $1.000 $0.940 $0.900 $1.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 46.000 $17.000 $15.000 $12.000 $12.000 $13.200 $12.000 $20.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $270.000 $200.000 $225.000 $225.000 $247.500 $225.000 $250.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 12.000 $500.000 $450.000 $400.000 $400.000 $440.000 $400.000 $500.000
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $325.000 $250.000 $275.000 $275.000 $302.500 $275.000 $300.000
REFL PAV MRKR TY I-C
EA 54.000 $6.000 $5.000 $4.750 $5.000 $5.230 $4.750 $6.000
REFL PAV MRKR TY II-A-A
EA 1,586.000 $6.000 $5.000 $4.750 $5.000 $5.230 $4.750 $6.000
ELIM EXT PAV MRK & MRKS (6")
LF 194,690.000 $1.000 $0.580 $0.400 $0.750 $1.230 $0.400 $0.500
D-GR HMA TY-B PG64-22
TON 20,542.000 $115.000 $93.400 $93.000 $95.000 $103.720 $103.000 $110.000
D-GR HMA TY-D SAC-B PG70-22
TON 44,243.000 $125.000 $104.400 $110.000 $115.000 $124.900 $125.000 $125.000
TACK COAT
GAL 32,315.000 $4.000 $3.660 $3.600 $5.000 $3.850 $4.000 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,000.000 $12,547.300 $13,000.000 $20,000.000 $12,100.000 $8,000.000 $16,500.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $12,000.000 $13,638.370 $13,500.000 $12,000.000 $13,200.000 $15,000.000 $5,000.000
TMA (STATIONARY)
DAY 100.000 $300.000 $381.870 $250.000 $500.000 $253.000 $1,275.000 $250.000
TMA (MOBILE OPERATION)
DAY 80.000 $400.000 $981.960 $575.000 $100.000 $264.000 $700.000 $550.000
HPPM-RIB W/RET REQ TYI(W)6"(BRK)100MIL
LF 4,889.000 $0.900 $0.850 $0.700 $0.700 $0.770 $0.700 $1.000
HPPM-RIB W/RET REQ TYI(W)6"(SLD)100MIL
LF 64,528.000 $0.900 $0.850 $0.650 $0.650 $0.720 $0.700 $1.000
HPPM-RIB W/RET REQ TYI(Y)6"(SLD)100MIL
LF 70,468.000 $0.900 $0.850 $0.650 $0.650 $0.720 $0.700 $1.000
Totals: $17,978,197.800 $14,520,545.760 $15,318,817.850 $16,360,619.840 $16,601,246.134 $17,326,782.975 $19,061,370.850