GONZALES US 90 (0026-01-028)

Items: 71

County: GONZALES
Length: 0.0000 MILES
Highway: US 90
District: YOAKUM
Control Number: 0026-01-028
DBE Goal: 0.0%
Project: C 26-1-28
Guaranty: $100,000.00
Time: 201 WORKING DAYS
Engineer's Estimate: $5,467,250.60
Date: 04/04/2025 (1 year ago)
Contract Number: 4253213
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00196770
Project Description: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$5,467,250.60
1
Awarded
$5,381,995.91
Over/Under Est: -1.56% -$85,254.69
Over/Under Est: 4.1% $224,304.31
Amt Left: 5.75% $309,559.00
Over/Under Est: 8.29% $453,465.40
Amt Left: 10.01% $538,720.09
Delta: -4.03% -$229,161.09
Over/Under Est: 14.84% $811,375.40
Amt Left: 16.66% $896,630.09
Delta: -6.05% -$357,910.00
Over/Under Est: 17.69% $967,328.65
Amt Left: 19.56% $1,052,583.34
Delta: -2.48% -$155,953.25
$6,565,010.00
Over/Under Est: 20.08% $1,097,759.40
Amt Left: 21.98% $1,183,014.09
Delta: -2.03% -$130,430.75
Over/Under Est: 21.25% $1,161,790.19
Amt Left: 23.17% $1,247,044.88
Delta: -0.98% -$64,030.79
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 7.12% $383,198.11
TRP CONSTRUCTION GROUP, LLC 1.54% $82,882.74
NL CONTRACTORS LLC 0.57% $30,677.38
ROADWAY TRAFFIC CONTROL LLC 0.39% $20,989.78
Total: 9.62% $517,748.01

Bid Items & Bid Tabulations

71 Total 0 of 71
GONZALES  |  US 90  |  YOAKUM  |  0026-01-028  |  04/04/2025  |  $5,467,250.60  |  C 26-1-28  |  HAZARD ELIM & SAFETY  |  201 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STX CIVIL
HUNTER INDUSTRIES, LTD.
BEAR CREEK CONTRACTING, LLC
MB WESTERN INDUSTRIAL CONTRACTING CO.
ACME BRIDGE COMPANY, INC.
ICOS MANAGEMENT, LLC
SCOUT 5 CONSTRUCTION LLC
PREPARING ROW
STA 10.000 $8,500.000 $2,200.000 $3,815.600 $2,327.000 $5,000.000 $8,150.000 $4,400.000 $1,500.000
REMOV CONC (RIPRAP)
SY 23.000 $10.900 $10.000 $31.500 $318.000 $51.000 $75.400 $220.000 $18.530
EMBANK (VEH)(OC)(TY C)
CY 829.000 $28.000 $20.000 $70.400 $20.000 $68.000 $94.200 $55.000 $88.500
FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS)
CY 572.000 $200.000 $78.000 $126.240 $104.000 $140.000 $175.000 $88.000 $109.620
D-GR HMA TY-B PG64-22
TON 1,240.000 $200.000 $184.000 $173.800 $207.000 $160.000 $165.000 $308.000 $110.430
D-GR HMA TY-D SAC-B PG70-22
TON 310.000 $210.000 $262.000 $173.800 $295.000 $140.000 $175.000 $440.000 $130.620
TACK COAT
GAL 281.000 $7.500 $6.300 $5.120 $7.000 $10.000 $3.200 $44.000 $3.900
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 1,340.000 $125.000 $69.000 $129.650 $77.000 $95.000 $200.000 $308.000 $157.500
CUT & RESTORE ASPH PAVING
SY 573.000 $75.000 $170.000 $183.600 $382.000 $138.000 $198.000 $330.000 $142.350
CEM STABIL BKFL
CY 1,015.000 $200.000 $160.000 $172.800 $230.000 $283.000 $186.000 $242.000 $234.740
TRENCH EXCAVATION PROTECTION
LF 367.000 $10.000 $5.000 $5.400 $11.000 $57.000 $5.800 $22.000 $15.000
TEMPORARY SPL SHORING
SF 5,135.000 $55.000 $2.000 $10.800 $21.000 $23.000 $11.700 $11.000 $52.500
RIPRAP (CONC)(5 IN)
CY 91.000 $650.000 $550.000 $594.000 $476.000 $771.000 $641.000 $880.000 $227.250
RIPRAP (STONE PROTECTION)(12 IN)
CY 145.000 $220.000 $130.000 $170.560 $277.000 $250.000 $334.000 $330.000 $173.130
RETROFIT RAIL (TY C1W)
LF 1,730.000 $125.000 $320.000 $300.180 $308.000 $284.000 $340.000 $275.000 $295.920
RETROFIT RAIL (TY T131RC)
LF 2,000.000 $100.000 $315.000 $238.800 $273.000 $255.000 $205.000 $308.000 $216.150
CMP (GAL STL 18 IN)
LF 6.000 $110.000 $85.000 $91.800 $299.000 $108.000 $99.100 $440.000 $322.020
CONC BOX CULV (3 FT X 2 FT)
LF 189.000 $400.000 $335.000 $361.800 $389.000 $670.000 $390.000 $1,210.000 $442.050
CONC BOX CULV (4 FT X 2 FT)
LF 68.000 $475.000 $365.000 $394.200 $402.000 $670.000 $425.000 $1,320.000 $477.750
CONC BOX CULV (4 FT X 3 FT)
LF 89.000 $525.000 $410.000 $442.800 $438.000 $730.000 $478.000 $1,320.000 $549.150
CONC BOX CULV (6 FT X 5 FT)
LF 110.000 $850.000 $700.000 $755.990 $849.000 $1,167.000 $816.000 $1,430.000 $1,016.400
CONC BOX CULV (8 FT X 5 FT)
LF 83.000 $1,200.000 $1,150.000 $1,241.990 $1,080.000 $1,500.000 $1,340.000 $1,540.000 $1,349.250
CONC BOX CULV (8 FT X 8 FT)
LF 74.000 $1,750.000 $1,360.000 $1,468.790 $1,425.000 $1,750.000 $1,590.000 $1,540.000 $1,664.250
CONC BOX CULV (10 FT X 7 FT)
LF 292.000 $1,875.000 $1,475.000 $1,592.990 $1,524.000 $1,540.000 $1,720.000 $1,540.000 $2,163.000
CONC BOX CULV (12 FT X 5 FT)
LF 316.000 $1,900.000 $1,730.000 $1,868.390 $1,812.000 $1,900.000 $2,020.000 $1,760.000 $2,569.350
RC PIPE (CL III)(18 IN)
LF 2.000 $100.000 $85.000 $86.400 $355.000 $195.000 $93.300 $440.000 $60.900
WINGWALL (FW - 0) (HW=6 FT)
EA 2.000 $10,750.000 $15,000.000 $16,199.880 $9,085.000 $18,000.000 $17,500.000 $16,500.000 $13,500.000
WINGWALL (FW - 0) (HW=8 FT)
EA 2.000 $18,000.000 $18,000.000 $19,439.850 $11,502.000 $24,000.000 $21,000.000 $17,600.000 $22,500.000
WINGWALL (FW - S) (HW=6 FT)
EA 2.000 $21,000.000 $26,000.000 $28,079.790 $9,590.000 $53,000.000 $30,300.000 $17,600.000 $16,500.000
SET (TY I)(S= 3 FT)(HW= 2 FT)(4:1)(C)
EA 6.000 $5,500.000 $10,000.000 $10,799.920 $10,497.000 $12,000.000 $11,700.000 $8,800.000 $919.500
SET (TY I)(S= 4 FT)(HW= 2 FT)(6:1)(P)
EA 2.000 $6,500.000 $12,000.000 $12,959.900 $10,313.000 $11,000.000 $14,000.000 $13,200.000 $1,636.500
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1)(C)
EA 4.000 $8,000.000 $13,500.000 $14,579.890 $12,437.000 $14,000.000 $15,700.000 $13,200.000 $2,049.000
SET (TY I)(S= 8 FT)(HW= 6 FT)(3:1)(C)
EA 2.000 $17,250.000 $18,000.000 $19,439.850 $17,482.000 $25,000.000 $21,000.000 $16,500.000 $4,401.000
SET (TY I)(S= 8 FT)(HW= 9 FT)(3:1)(C)
EA 2.000 $23,000.000 $30,000.000 $32,399.760 $25,978.000 $37,000.000 $35,000.000 $19,800.000 $11,035.500
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 14.000 $1,400.000 $1,350.000 $1,457.990 $2,053.000 $1,300.000 $1,570.000 $2,750.000 $6,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $2,500.000 $2,200.000 $2,375.980 $1,792.000 $1,850.000 $2,560.000 $3,300.000 $6,000.000
CLEAN EXIST CULVERTS
EA 11.000 $1,000.000 $2,300.000 $2,483.980 $1,223.000 $3,200.000 $2,680.000 $8,800.000 $3,000.000
REMOV STR (BOX CULVERT)
EA 10.000 $11,950.000 $10,000.000 $10,799.920 $1,910.000 $5,400.000 $11,700.000 $5,500.000 $5,250.000
MOBILIZATION
LS 1.000 $485,000.000 $450,000.000 $436,135.940 $516,534.000 $425,000.000 $600,000.000 $100,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $8,000.000 $2,000.000 $7,379.930 $3,035.000 $5,000.000 $10,000.000 $1.000 $2,100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $3,500.000 $7,500.000 $5,832.000 $5,000.000 $17,000.000 $11,000.000 $2,231.250
TMA (STATIONARY)
DAY 190.000 $400.000 $5.000 $125.000 $275.000 $275.000 $391.000 $275.000 $195.000
TMA (MOBILE OPERATION)
DAY 34.000 $400.000 $10.000 $350.000 $315.000 $275.000 $898.000 $440.000 $195.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 380.000 $50.000 $40.000 $48.000 $58.000 $52.000 $49.500 $10.000 $11.550
ROCK FILTER DAMS (REMOVE)
LF 380.000 $20.000 $5.000 $18.000 $7.000 $14.000 $12.500 $5.000 $7.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,110.000 $5.500 $3.000 $4.200 $5.000 $6.000 $5.300 $2.000 $2.850
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,110.000 $2.000 $1.000 $1.080 $3.000 $2.000 $0.530 $1.000 $1.500
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 12.000 $6,000.000 $4,000.000 $11,000.000 $2,291.000 $6,500.000 $3,240.000 $1.000 $6,300.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,160.000 $54.000 $85.000 $40.000 $93.000 $90.000 $97.200 $105.000 $100.500
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 9,270.000 $12.000 $14.000 $15.000 $18.000 $23.000 $18.500 $22.000 $15.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 2,160.000 $18.000 $15.000 $15.000 $17.000 $23.000 $35.600 $33.000 $15.000
MTL W-BEAM GD FEN (TIM POST)
LF 4,375.000 $30.250 $27.000 $29.900 $27.000 $26.000 $25.500 $24.000 $42.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 20.000 $2,900.000 $2,185.000 $2,799.140 $2,188.000 $2,100.000 $2,650.000 $2,750.000 $2,625.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 275.000 $95.000 $115.000 $105.500 $127.000 $115.000 $82.800 $132.000 $117.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,200.000 $1,525.000 $1,378.370 $1,527.000 $1,500.000 $1,430.000 $1,650.000 $41.820
REMOVE METAL BEAM GUARD FENCE
LF 4,739.000 $3.500 $1.000 $2.120 $4.000 $3.000 $2.650 $2.000 $1.500
REMOVE TERMINAL ANCHOR SECTION
EA 18.000 $200.000 $300.000 $227.960 $325.000 $245.000 $265.000 $550.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 32.000 $3,250.000 $3,500.000 $3,583.750 $3,956.000 $3,900.000 $3,290.000 $3,740.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $360.000 $300.000 $344.590 $325.000 $311.000 $265.000 $550.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 34.000 $1,640.000 $1,300.000 $1,484.390 $1,005.000 $965.000 $1,530.000 $2,200.000 $2,250.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $1,000.000 $1,000.000 $848.220 $886.000 $850.000 $1,090.000 $5,500.000 $750.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 8.000 $9,500.000 $7,700.000 $8,227.780 $9,750.000 $8,900.000 $7,590.000 $11,000.000 $9,225.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 1.000 $275.000 $170.000 $185.580 $200.000 $200.000 $421.000 $1,100.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 122.000 $50.000 $60.000 $31.810 $30.000 $35.000 $25.200 $55.000 $30.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 19,205.000 $1.100 $1.120 $1.780 $2.000 $3.000 $1.350 $2.000 $1.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 308.000 $12.250 $18.880 $21.350 $19.000 $12.000 $15.900 $2.000 $21.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 16,430.000 $1.250 $1.120 $1.780 $2.000 $3.000 $1.350 $2.000 $1.500
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 13,493.000 $0.950 $3.010 $2.060 $7.000 $5.000 $1.550 $2.000 $1.800
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 3,919.000 $0.950 $3.010 $2.420 $8.000 $6.000 $1.800 $2.000 $1.800
REFL PAV MRKR TY II-A-A
EA 172.000 $4.500 $14.160 $11.390 $31.000 $8.000 $8.500 $22.000 $15.000
ELIM EXT PM & MRKS (4")
LF 3,919.000 $1.250 $7.670 $2.140 $5.000 $9.000 $1.600 $2.000 $1.500
Totals: $5,467,250.600 $5,381,995.910 $5,691,554.910 $5,920,716.000 $6,278,626.000 $6,434,579.250 $6,565,010.000 $6,629,040.790
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $1,500.00